Class 701 'Aventra' trains for South Western Railway: progress updates

swr444

Member
Joined
26 Aug 2008
Messages
1,007
Location
London
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

GW43125

Established Member
Joined
8 Dec 2014
Messages
2,310
A good sign is the drag appears to have been manually activated judging by the time.
But I will wait and see how well the unit talks with 57306 and they get beyond Worcester before believing it is arriving today !.

Does anyone know which 701 (I assume one of 023, 045 or 049) ?.
57306 + 701023 showing
 

LUYMun

Established Member
Joined
15 Jul 2018
Messages
1,384
Location
Cancelled
701021 currently having an issue leaving Waterloo on the 1620 to Woking. Chances of a diagram swap to a 455 is increasing!
 

Nogoohwell

Member
Joined
14 Aug 2020
Messages
104
Location
London
Was on 021 yesterday when the driver had reset a few things at Motspur Park.
A two minute delay and all working again, but its clearly not a happy unit atm.
 

WWTownEnth

Member
Joined
21 Mar 2014
Messages
735
January is looking like the first month in a good while that we’ve had no new units into passenger service. Unless something happens today, of course……
 

CarrotPie

On Moderation
Joined
18 Mar 2021
Messages
1,128
Location
Seventeen out at once? How many were carrying passengers?
I think WWTownEnth meant that there are 17 units on the SWR network (e.g. at Wimbledon depot) that haven't yet entered service, but are being used for testing and training.
 
Last edited:

Goldfish62

Veteran Member
Joined
14 Feb 2010
Messages
13,183
It does seem strange that 701 introduction has ground to a halt, but it does tally with SWR's statement that they intend to introduce just another 10 units by the summer.
 

WWTownEnth

Member
Joined
21 Mar 2014
Messages
735
It does seem strange that 701 introduction has ground to a halt, but it does tally with SWR's statement that they intend to introduce just another 10 units by the summer.
I thought they said 50 by the summer? So that would be another 13/14.
 

Siemens Staines

Established Member
Joined
30 Jul 2015
Messages
1,516
It does seem strange that 701 introduction has ground to a halt, but it does tally with SWR's statement that they intend to introduce just another 10 units by the summer.

It is not so strange when SWR are relying upon the advertised 94% fleet availability and 34 * 1/0.94 = 36. So 36 is all they require for 34 diagrams so on paper you should not need to expand the fleet to cover the existing diagrams. Of course, in practice it is a different story!

I took a look at the availability figures that GA were aiming for with their comparable 720 fleet as their source diagrams are available on their website. They appear to have 125 diagrams for 133 units which is 94%, so the same. However 22 of the diagrams appear to be tied up in Q path stock transfers and the vast majority of these don't run. If you take these diagrams out of the equation, then 103 diagrams from 133 units is 77% so they have a lot of slack in their fleet when compared to SWR.
 

Andy1673

Member
Joined
10 May 2019
Messages
947
It is not so strange when SWR are relying upon the advertised 94% fleet availability and 34 * 1/0.94 = 36. So 36 is all they require for 34 diagrams so on paper you should not need to expand the fleet to cover the existing diagrams. Of course, in practice it is a different story!

I took a look at the availability figures that GA were aiming for with their comparable 720 fleet as their source diagrams are available on their website. They appear to have 125 diagrams for 133 units which is 94%, so the same. However 22 of the diagrams appear to be tied up in Q path stock transfers and the vast majority of these don't run. If you take these diagrams out of the equation, then 103 diagrams from 133 units is 77% so they have a lot of slack in their fleet when compared to S
We also shouldn't forget that there is a significant amount of unused (spare) rolling stock that needs to be placed somewhere. And it requires space.
 

Goldfish62

Veteran Member
Joined
14 Feb 2010
Messages
13,183
It is not so strange when SWR are relying upon the advertised 94% fleet availability and 34 * 1/0.94 = 36. So 36 is all they require for 34 diagrams so on paper you should not need to expand the fleet to cover the existing diagrams. Of course, in practice it is a different story!
But that implies "job done" with no plans to replace the 450s or 458s on metro work. On that basis 24 701/0s and 30 701/5s are surplus to requirements, but we know that's not the case, at least in respect of the 701/0s.

In respect of spare requirements the % spare has less meaning that the actual number spare the smaller the fleet is. In the current case I'd suggest just two spares is a tall order when expecting to reliably cover 34 diagrams daily. Back in the day only 24 458/0s were diagrammed daily with the remaining 6 as spares.
 

CarrotPie

On Moderation
Joined
18 Mar 2021
Messages
1,128
Location
In the current case I'd suggest just two spares is a tall order when expecting to reliably cover 34 diagrams daily. Back in the day only 24 458/0s were diagrammed daily with the remaining 6 as spares.
One hopes the 701s will be less unreliable than the 458/0s, especially as time goes on...
 

43096

On Moderation
Joined
23 Nov 2015
Messages
18,833
One hopes the 701s will be less unreliable than the 458/0s, especially as time goes on...
Given that the 458/0s were the most reliable trains in the country for a while once Porterbrook and SWT worked through their issues, you may be waiting some time.
 

Stephen42

Member
Joined
6 Aug 2020
Messages
807
Location
London
I thought they said 50 by the summer? So that would be another 13/14.
It's 50 diagrams as well not units in service. There are currently 34 diagrams which makes at least another 16 and rarely 34 have been out. That would be 17 to 19 more in passenger service depending on unit availability.
Is this because driver training needs to catch up with the number of units available?
There's enough drivers for the current diagrams which aren't all running as 701s due to lack of serviceable units.

The Clapham test runs had a break for three weeks (excluding a single run by 701028) making much of the gap the festive break.
It is not so strange when SWR are relying upon the advertised 94% fleet availability and 34 * 1/0.94 = 36. So 36 is all they require for 34 diagrams so on paper you should not need to expand the fleet to cover the existing diagrams. Of course, in practice it is a different story!
It would be bizarre to rely on a fleet availability figure they know doesn't hold up in practice. With small numbers it's harder to achieve, scheduled maintenance and two unlucky events together means game over.
 

Siemens Staines

Established Member
Joined
30 Jul 2015
Messages
1,516
In respect of spare requirements the % spare has less meaning that the actual number spare the smaller the fleet is. In the current case I'd suggest just two spares is a tall order when expecting to reliably cover 34 diagrams daily. Back in the day only 24 458/0s were diagrammed daily with the remaining 6 as spares.

I agree entirely, but I was just trying to think of a reason as to why the fleet has stuck at 36 units since the number of diagrams changed to 34 and a paper fleet availability of 94% was one possible answer. The current LTP diagrams end in a weeks time, so I imagine things will change within the next week in the run up to the next LTP period. Having only two units spare clearly has not worked or else we would not have the semi-permanent 2*450 vice 701 (2M03 etc) and 2*455 vice 2*450 (2J08 etc). Since 5th Jan, you can count on the fingers of one hand the number of peaks where 34 701s have been in service at the same time and is very definitely the exception not the rule.
 

Goldfish62

Veteran Member
Joined
14 Feb 2010
Messages
13,183
I agree entirely, but I was just trying to think of a reason as to why the fleet has stuck at 36 units since the number of diagrams changed to 34 and a paper fleet availability of 94% was one possible answer. The current LTP diagrams end in a weeks time, so I imagine things will change within the next week in the run up to the next LTP period. Having only two units spare clearly has not worked or else we would not have the semi-permanent 2*450 vice 701 (2M03 etc) and 2*455 vice 2*450 (2J08 etc). Since 5th Jan, you can count on the fingers of one hand the number of peaks where 34 701s have been in service at the same time and is very definitely the exception not the rule.
Agreed. I'd have thought that SWR would have gone all out to get 2-3 more 701s available for service so the 455s could finally be eliminated. But then maybe they have been going all out, but the remaining units are proving too problematic. They are after all mostly the earlier units, which have been in store for the longest.
 

adc82140

Established Member
Joined
10 May 2008
Messages
3,407
Alternatively they could be thinking that the 455s are available, so why not run them in to the ground and take the time to get the next batch of 701s properly right before introducing them.
 