However, that was felt to be too restrictive, as in many cases it slowed trains much more than necessary. And, as you say, it also led to drivers anticipating the signal clearing up as soon as the train passed the AWS magnet.
The basis of modern junction signalling is to give information about what route the train is taking, and that it is up to the driver to then control the train to the appropriate speed for that route.
Trying to get a conventional signalling system to control train speed with a wide variety of train characteristics is unrealistic, it is either going to be over-restrictive for some trains or not restrictive enough. It needs something more sophisticated, like ETCS.
Overspeeding at Cambridge Junction (Hitchin) -- 11/12/25
Saw this earlier: https://www.gov.uk/government/news/overspeeding-at-cambridge-junction At 10:39 on 11 December 2025, train reporting number 1T20, the 10:12 London Kings Cross to Ely service, operated by Great Northern (a trading name of Govia Thameslink Railway Ltd), was involved in an...
At one time, the controls for approach released from red signals would have been designed so that the junction signal would be held at yellow until the train had passed the AWS magnet.Having the train pass the signal to single yellow does create a hazard that the driver is accustomed to seeing it and then finding the next signal showing a proceed aspect.
A root cause of this and similar incidents is the vastly better acceleration of modern trains compared with those that existed when this signalling was designed.
However, that was felt to be too restrictive, as in many cases it slowed trains much more than necessary. And, as you say, it also led to drivers anticipating the signal clearing up as soon as the train passed the AWS magnet.
The basis of modern junction signalling is to give information about what route the train is taking, and that it is up to the driver to then control the train to the appropriate speed for that route.
Trying to get a conventional signalling system to control train speed with a wide variety of train characteristics is unrealistic, it is either going to be over-restrictive for some trains or not restrictive enough. It needs something more sophisticated, like ETCS.