Sorry if this is in the wrong forum, mods please move if needed.
So I’m doing a bit of armchair train planning, and I’m tryna sort out a branch line. It’s from a key station on the mainline (involving a shunt as the departure platform is not signalled for loaded arrivals) to a small station with no driver depot or anything, and I’m trying to get it to run hourly.
I have two options:
So I’m doing a bit of armchair train planning, and I’m tryna sort out a branch line. It’s from a key station on the mainline (involving a shunt as the departure platform is not signalled for loaded arrivals) to a small station with no driver depot or anything, and I’m trying to get it to run hourly.
I have two options:
- A six minute turnaround at the end, resulting 45 minutes at the mainline end. However, due to the timings of mainline trains (both up and down) there is only 4 minutes to turn it around for the shunt, and that involves “squeezing” the timings of the next mainline service on that platform, having it a couple minutes later and then tighter timings for the rest of its journey, which isn’t ideal and has a knock-on effect for the trains behind it. This requires 2 units
- The other option involves adding the omitted stop back in, so that it departs the “outpost” end around 5 minutes before the next one arrives, meaning a 55 minute turnaround, but no conflict on the mainline and therefore a more generous turnaround before the shunt. I’m not too bothered about this requiring an extra unit (this is part of a wider armchair timetable I’m doing), but I’m kinda worried about the 55 minute turnaround from the drivers POV. It’s a small outpost and I’m worried that 55 minutes is a bit too long, considering they’ll also get around 30 mins at the mainline end after the shunt. Is it possible to have it like this or am I overthinking it?