South Wales 'Metro' updates

Bob Price

Established Member
Joined
8 Aug 2019
Messages
1,243
Does anyone know how well the two week closure of the Rhymney line has gone? Are the wires up where they are planned?
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

MikePJ

Member
Joined
10 Dec 2015
Messages
1,016
Modern Railways has a couple of articles about the Cardiff area and Metro works this month - here are a few highlights:

- the additional trackwork needed for the Queen St South Junction upgrade is all being stored at Barry Depot (formerly Barry Tourist Railway), with the works having been postponed to help with TfW's cashflow. (I take back what I said years ago about cashflow... you were right and I was wrong).

- Mainline driver training has started on the 231s, but there are 200 drivers to train.
- 756s use less than 1% of their diesel fuel per day at the moment, and the software is configured to run the diesel engine if the battery charge drops below 30%. (This helps with battery longevity - running them flat shortens their usable lifetime).
- "advanced discussions" are being held with Stadler on putting pantographs on the 231s, but it's apparently quite an invasive process and Stadler want to take the trains to Switzerland to do it, whereas TfW want it done in the UK (presumably to save transit time)
- 756s are being considered for routes to Bristol and to Ebbw Vale (this will need extra units, however)
- There are more than 400 Valleys drivers who need training on the 398s
- 398s were delivered to Taffs Well long before the depot was finished, as TfW found this was going to be cheaper than sending them elsewhere for storage.
- 398s are due into service "early next year", so the November date in the June project plan has already slipped.
- Acceptance testing for 398s has been ongoing all summer and TfW have now accepted the first few units. Some mileage accumulation for later units may be done on the main line between Cardiff and Newport in the future.
- Some 150s will be retained for "some Vale of Glamorgan services" until enough 398s are in traffic to make enough 756s available.
- Street running to Central via Callaghan Square is supposedly due to start in 2028.
 
Joined
22 Jun 2013
Messages
603
Modern Railways has a couple of articles about the Cardiff area and Metro works this month - here are a few highlights:

- the additional trackwork needed for the Queen St South Junction upgrade is all being stored at Barry Depot (formerly Barry Tourist Railway), with the works having been postponed to help with TfW's cashflow. (I take back what I said years ago about cashflow... you were right and I was wrong).

- Mainline driver training has started on the 231s, but there are 200 drivers to train.
- 756s use less than 1% of their diesel fuel per day at the moment, and the software is configured to run the diesel engine if the battery charge drops below 30%. (This helps with battery longevity - running them flat shortens their usable lifetime).
- "advanced discussions" are being held with Stadler on putting pantographs on the 231s, but it's apparently quite an invasive process and Stadler want to take the trains to Switzerland to do it, whereas TfW want it done in the UK (presumably to save transit time)
- 756s are being considered for routes to Bristol and to Ebbw Vale (this will need extra units, however)
- There are more than 400 Valleys drivers who need training on the 398s
- 398s were delivered to Taffs Well long before the depot was finished, as TfW found this was going to be cheaper than sending them elsewhere for storage.
- 398s are due into service "early next year", so the November date in the June project plan has already slipped.
- Acceptance testing for 398s has been ongoing all summer and TfW have now accepted the first few units. Some mileage accumulation for later units may be done on the main line between Cardiff and Newport in the future.
- Some 150s will be retained for "some Vale of Glamorgan services" until enough 398s are in traffic to make enough 756s available.
- Street running to Central via Callaghan Square is supposedly due to start in 2028.
Thanks, very interesting.There are so many projects on a go slow or severely delayed that cash flow had to be the cause. Mind blown by the number of drivers employed by the way, wow!
 

slowroad

Member
Joined
23 Jul 2021
Messages
371
Location
Wales
Do we know how far the cash flow issues are the result of costs being higher than planned v revenues being lower (presuming both apply to some extent)?
 

tigermonstera

Member
Joined
11 Mar 2025
Messages
150
Location
UK
I’ve had a look and although I can’t find any news about Rhymney’s second platform, I did notice a tender from 2022 (Link) which indicates that the OLE on the Coryton Line was designed with passive provision for a passing loop between just north of Ty Glas and just south of Whitchurch (i.e. with provision for second platforms at Birchgrove and Rhiwbina stations).
 

AdamWW

Established Member
Joined
6 Nov 2012
Messages
5,954
I’ve had a look and although I can’t find any news about Rhymney’s second platform, I did notice a tender from 2022 (Link) which indicates that the OLE on the Coryton Line was designed with passive provision for a passing loop between just north of Ty Glas and just south of Whitchurch (i.e. with provision for second platforms at Birchgrove and Rhiwbina stations).

Though presumably not the original plan, given that there is unused trunking for 25 kV cabling in the way.

Much easier to remove that then move the catenary posts though...
 

Cardiff123

Established Member
Joined
10 Mar 2013
Messages
1,652
Location
South Wales
I'm amazed that there's not been a press release from TfW marking the re-opening of the Caerphilly to Rhymney line after months of extended closures. There's no more extended closures planned this year, so now would be a good time for TfW to talk about what work they've done and to encourage people back to the train.
 

edwin_m

Veteran Member
Joined
21 Apr 2013
Messages
28,668
Location
Nottingham
I'm amazed that there's not been a press release from TfW marking the re-opening of the Caerphilly to Rhymney line after months of extended closures. There's no more extended closures planned this year, so now would be a good time for TfW to talk about what work they've done and to encourage people back to the train.
Might have something to do with the by-election in Caerphilly?
 

MikePJ

Member
Joined
10 Dec 2015
Messages
1,016
TFW's press office have given the impression of being overworked for ages - often press releases come out weeks or months after the event has happened.
 

MikePJ

Member
Joined
10 Dec 2015
Messages
1,016
A photo from Cardiff Bay today showing the glass-reinforced plastic fencing (grey) that appears near the overhead line columns. There was also construction activity at Butetown’s southbound platform, with concrete pads being cast on the forecourt between Lloyd George Ave and the steps to the platform.
 

Attachments

  • IMG_3071.jpeg
    IMG_3071.jpeg
    3.3 MB · Views: 155

tigermonstera

Member
Joined
11 Mar 2025
Messages
150
Location
UK
TfW are consulting this month for a new active travel route (i.e. for walking/wheeling/cycling) to connect Pontypool and New Inn Station to Usk via Little Mill
 
Joined
1 Sep 2017
Messages
105
Do we know how far the cash flow issues are the result of costs being higher than planned v revenues being lower (presuming both apply to some extent)?
I think that depends on your baseline? The original (pre-covid) numbers are of course of no use anymore. Since then TfW has repeatedly replanned, and of course had cash injections by the Welsh Government.
 

tigermonstera

Member
Joined
11 Mar 2025
Messages
150
Location
UK
Ty Glas Level Crossing is back open (Link):
Ty Glas level crossing is now open. We'd like to remind the community to use the crossing safely.
Ty Glas station will remain closed whilst we carry out upgrades, and passengers should continue to use Birchgrove station to access rail services.
We'd like to thank the community for their patience.
Is anyone aware what works were done on the crossing?
 

Envoy

Established Member
Joined
29 Aug 2014
Messages
3,142
Does anyone know what engineering work is being carried out on the City line this week that warrants its closure? (Also closed some Sundays in November).
 

tigermonstera

Member
Joined
11 Mar 2025
Messages
150
Location
UK
Does anyone know what engineering work is being carried out on the City line this week that warrants its closure? (Also closed some Sundays in November).
Potentially this:
As part of our work to upgrade your rail network, we’ll be carrying out the second stage of the renovation works to platform 2 at Waun-gron station.
We’ll be working around the clock from 26 Oct at 00.30 to 2 Nov at 20.00. We’ll try and carry out as much of the noisier work during the daytime as possible.
In order to safely carry out these upgrades, we’ll need to close Waun-gron road at night from 22.00 to 06.00. We’ll then operate a single-lane closure beneath the bridge during daytime hours (06.00 – 22.00) controlled by 2-way lights. The lane will be swapped as needed.
(Link)
 

Envoy

Established Member
Joined
29 Aug 2014
Messages
3,142
Potentially this:

(Link)
Thanks for this. Not sure why TFW sees fit to put this on Facebook and not their own website. Not all people bother with Facebook.

Single lane working on Waungron Road by the station and also on nearby Cowbridge Road.

They ought to hack down all the Buddleia bushes while the line is shut. The seeds are blowing all over the place and taking root in crevices.
 

Cardiff4

Member
Joined
10 Aug 2011
Messages
33
Location
Cardiff
Ty Glas Level Crossing is back open (Link):

Is anyone aware what works were done on the crossing?
The first photograph shows the arrangements before the recent work took place. Passengers walked down the ramp, opened the gate and then turned right onto the crossing. Now there is additional fencing and a "dog-leg" in the path that means you are facing the crossing before you open the gate. This gives you the opportunity to look both left and right down the track before opening the gate
 

Attachments

  • Ty Glas Station Foot Crossing_2021_0227_01.JPG
    Ty Glas Station Foot Crossing_2021_0227_01.JPG
    616.8 KB · Views: 150
  • Updated Rail Crossing_Ty Glas Station_2025_1025_05.JPG
    Updated Rail Crossing_Ty Glas Station_2025_1025_05.JPG
    527.2 KB · Views: 146
  • Updated Rail Crossing_Ty Glas Station_2025_1025_06.JPG
    Updated Rail Crossing_Ty Glas Station_2025_1025_06.JPG
    569.7 KB · Views: 145
  • Updated Rail Crossing_Ty Glas Station_2025_1025_03.JPG
    Updated Rail Crossing_Ty Glas Station_2025_1025_03.JPG
    490.9 KB · Views: 144

tigermonstera

Member
Joined
11 Mar 2025
Messages
150
Location
UK
The first photograph shows the arrangements before the recent work took place. Passengers walked down the ramp, opened the gate and then turned right onto the crossing. Now there is additional fencing and a "dog-leg" in the path that means you are facing the crossing before you open the gate. This gives you the opportunity to look both left and right down the track before opening the gate
Thanks, good explanation!
 

MikePJ

Member
Joined
10 Dec 2015
Messages
1,016
There's a week-long shutdown of the Cardiff Bay line now programmed for 17th - 21st November. I'm not sure what's planned- hopefully it includes energising the overhead line. I took a quick look today and there are still some sections of old fencing that need to be replaced with non-conductive fence panels.

The concreting at Butetown is continuing and this morning the workforce were laying a concrete slab right up to the edge of the pavement on Lloyd George Avenue.
 

TT-ONR-NRN

Veteran Member
Joined
30 Dec 2016
Messages
12,864
Location
Cambridge
There's a week-long shutdown of the Cardiff Bay line now programmed for 17th - 21st November. I'm not sure what's planned- hopefully it includes energising the overhead line. I took a quick look today and there are still some sections of old fencing that need to be replaced with non-conductive fence panels.

The concreting at Butetown is continuing and this morning the workforce were laying a concrete slab right up to the edge of the pavement on Lloyd George Avenue.
Are we still only on one platform open (the new one) at Bay station?
 

MikePJ

Member
Joined
10 Dec 2015
Messages
1,016
Are we still only on one platform open (the new one) at Bay station?
We are, yes. None of the new pointwork has been installed yet - it turns out that this, and the double-tracking, was postponed along with the changes to Queen Street South Junction. TfW put out a tender for it recently and it's due to take place in "early 2027".

Meanwhile, the works at Butetown look like they're re-focussing work on the platform on the east (Lloyd George Ave) side, so there's a possibility that they'll try and open this alongside the introduction of 398s, and then open the second platform in 2027 when the dual-tracking is finished.

== Doublepost prevention - post automatically merged: ==

Also, correction to my post from earlier: the Cardiff Bay energisation isn't due until early December, so the November shutdown is unlikely to include it.
 
Last edited: