Following on from other threads on the interim reporting, the DfT has now published a report evaluating the early Impact of the line reopening.
LINK: https://www.gov.uk/government/publications/dartmoor-line-evaluation-of-re-opening
The summary is that the line is being well used and well received, with both locals and tourists. There are negative impacts to the local bus demand and education enrolment in Okehampton itself linked to the easier access to Exeter.
The line was delivered for slightly less than forecast (£51m vs £56.6m) which is credited to Project Speed, and at the moment is running an operating surplus.
Perhaps most critically for forum users, is the following paragraph on demand in the executive summary:
The overall indications at this time point to the line being a very solid success.
(Apologies if I've missed an existing thread)
3-years Thread:
www.railforums.co.uk
1-year Thread:
www.railforums.co.uk
LINK: https://www.gov.uk/government/publications/dartmoor-line-evaluation-of-re-opening
The summary is that the line is being well used and well received, with both locals and tourists. There are negative impacts to the local bus demand and education enrolment in Okehampton itself linked to the easier access to Exeter.
The line was delivered for slightly less than forecast (£51m vs £56.6m) which is credited to Project Speed, and at the moment is running an operating surplus.
Perhaps most critically for forum users, is the following paragraph on demand in the executive summary:
Comparison of actual and forecast passenger demand (as contained in the business case for the Line) on the Dartmoor Line shows that the forecasts under-estimated demand the first 2 full years of the Line’s operation with total demand 47% higher than forecast over this period. However, since November 2023 actual demand by period has typically been marginally lower than forecast. The large variance in the first two years is primarily due to the forecasting methodology assuming more conservative demand ramp-up factors. It is currently too early to draw conclusions, and a focus needs to be maintained on growing demand if the business case forecasts are to be achieved in the long-term.
The overall indications at this time point to the line being a very solid success.
(Apologies if I've missed an existing thread)
3-years Thread:
Okehampton - 3 Years On
The 1 year on thread is closed so here is a new one. Predictably, even more success and doom laden predictions wrong....again. https://dartmoorline.com/2023/11/celebrations-in-okehampton-as-more-than-550000-journeys-made-in-first-two-years-of-dartmoor-line-reopening/ The previously...
1-year Thread:
Okehampton - Exeter open a year- success?
It's been a year since "levelling up" reopened the 16 odd miles from Exeter to Okehampton. Passenger numbers seem up, has it been a success for all concerned?