I've come across some details regarding a level crossing that in the end was cancelled by one of the main local land owners.
It seems that early on at planning stage the local landowner stipulated that a public road level crossing would be required. At the location where it was to be at the time was open countryside but it's clear plots of land were being drawn out for new houses and streets etc. All of this happens between 1869 and 1874 and here I'm talking about the town of Padiham, Lancs.
In 1872 the eldest son inherits Gawthorpe Hall, Padiham when his mother dies and it seems later in 1874 he has a change of mind over this level crossing. After taking advice from his solicitor a draft agreement is written releasing the L&Y from their obligation of providing the crossing but instead he wants a bridge wing wall / abutment altering instead which will be at the L&Y's own expense not his.
This draft agreement is dated mid January 1875 which for me is extremely late in the day as goods trains started running 1 July that year.
Questions:
1. If you have a public level crossing, don't you need a box next to it to control the gates and necessary signals?
2. As built, on this section of line there were two signal boxes either side of the station, built by Saxby & Farmer. If you do need a box for the crossing and two for the station, wouldn't the L&Y order all three together?
3. What would have been a reasonable amount of time from ordering boxes to installation and testing? Three months? six months?
It seems that early on at planning stage the local landowner stipulated that a public road level crossing would be required. At the location where it was to be at the time was open countryside but it's clear plots of land were being drawn out for new houses and streets etc. All of this happens between 1869 and 1874 and here I'm talking about the town of Padiham, Lancs.
In 1872 the eldest son inherits Gawthorpe Hall, Padiham when his mother dies and it seems later in 1874 he has a change of mind over this level crossing. After taking advice from his solicitor a draft agreement is written releasing the L&Y from their obligation of providing the crossing but instead he wants a bridge wing wall / abutment altering instead which will be at the L&Y's own expense not his.
This draft agreement is dated mid January 1875 which for me is extremely late in the day as goods trains started running 1 July that year.
Questions:
1. If you have a public level crossing, don't you need a box next to it to control the gates and necessary signals?
2. As built, on this section of line there were two signal boxes either side of the station, built by Saxby & Farmer. If you do need a box for the crossing and two for the station, wouldn't the L&Y order all three together?
3. What would have been a reasonable amount of time from ordering boxes to installation and testing? Three months? six months?