Hmm... I knew that they had put the bases in while rebuilding the line but I'm slightly surprised they're putting the masts up already.
Indeed- it seems they have gone from nothing to masts with SPS etc. Really fantastic to see.Wow! This is amazing to see! Can't wait to get down there and have a look for myself...
Nice to see progress up in Fife as well now! I guess teams are moving on now work on East Kilbride is finished.Seeing as this forum thread has wandered north of Dalmeny....
Masts have gone up just west of Cameron Bridge, about 20 of them so far, you can see the west end of Diageo's complex at the back right of one of the photos.View attachment 186792View attachment 186793
One of the efficiency that they have introduced is to attach the SPS in the yard before erecting the mast.Indeed- it seems they have gone from nothing to masts with SPS etc. Really fantastic to see.
I did have to google Cameron Bridge though!
I guess teams are moving on
The electrification of this line is supposed to be complete within 3-5 years (2028-2030), but I doubt they'll take that long to electrify 9km of double track railway. They'll most likely restart other projects during that period as well.To the wrong place, given that this electrification will be absolutely useless for several years to come.
If you look at the map in post 4, you’ll see that there is quite a bit to be done before the Fife lines will be ready to accept BEMUs. On the assumption that the Leven branch is the start of work on the four lines radiating from Thornton, it’s not unreasonable to tie the completion of the infrastructure work with the approximate time suitable rolling stock becomes available.To the wrong place, given that this electrification will be absolutely useless for several years to come.
the approximate time suitable rolling stock becomes available.
That question is best asked on the relevant thread to avoid going off topic, but if you read through it you will see that a further step in the process is due next month. The good news is that the process is underway, and that whilst I am sure people would wish it was faster, investment in such a large fleet is not a simple process, and takes time.Does anyone, including Scotrail and Network Rail, even know when that will be?!!
Just wondering, what's the difference between these (being lightweight) and other masts (that aren't)? What makes them such a type?It’s also nice to see lightweight masts being used too on local lines (he says, thinking of the Valleys electrification project in particular.)
And the grid feeder surely?If you look at the map in post 4, you’ll see that there is quite a bit to be done before the Fife lines will be ready to accept BEMUs. On the assumption that the Leven branch is the start of work on the four lines radiating from Thornton, it’s not unreasonable to tie the completion of the infrastructure work with the approximate time suitable rolling stock becomes available.
This thread suggests it will be in place long before then, so I discounted it as a constraint.And the grid feeder surely?
Looking at the plates, "Echo Quebec" seems to be the Route Code for the Levenmouth branch. Perhaps "Q" for "Quay"?Seeing as this forum thread has wandered north of Dalmeny....
Masts have gone up just west of Cameron Bridge, about 20 of them so far, you can see the west end of Diageo's complex at the back right of one of the photos.View attachment 186792View attachment 186793
All mine, i've also taken a video running through the area yesterday which i've yet to upload anywhere.but what is the source from those images? Is it an independant source?
To the wrong place, given that this electrification will be absolutely useless for several years to come.
Exactly this - Keeping electrification costs low, and having the lines ready when the new trains arrive is ideal.Given that you've railed against electrification of East Kilbride for the lack of EMUs, and now Fife, where do you think is the right place? Bear in mind of course that this is ScotGov wiring with Scottish money, and therefore wiring the Oxford or Bristol lines would appear to be a questionable use of funds.
There is an Invitation to Tender out right now, with an award expected to commence in the next 18 months, which will provide a lot of lovely shiny new EMUs and BEMUs to work these lines.
If you think they shouldn't be wiring until the trains arrive, then they'd have trains lying around doing nothing. If you think that they should have wired somewhere else, then they'd still have no units to work the wired lines.
Yes, they could have ordered them earlier, but they didn't, and here we are. Surely it's better to continue wiring at pace, in advance of the units arriving, to keep the teams together and keep costs low?
Ah, thanks for getting those images and posting them here, absolute legend!All mine, i've also taken a video running through the area yesterday which i've yet to upload anywhere.
As an update, I counted 31 masts up yesterday.
+1 from me too.Exactly this - Keeping electrification costs low, and having the lines ready when the new trains arrive is ideal.
Any chance you could upload it to YouTube or Vimeo?All mine, i've also taken a video running through the area yesterday which i've yet to upload anywhere.
As an update, I counted 31 masts up yesterday.

Importantly, keeping the team together! The loss of skill and experience involved in constantly demobilising and re-mobilising is such a serious issue.Exactly this - Keeping electrification costs low, and having the lines ready when the new trains arrive is ideal.
I’d actually quite like the Scottish Govt to bid for English (or Welsh) wiring. It seems to be able to do it at a much lower price and with more pragmatism as to what is done.Given that you've railed against electrification of East Kilbride for the lack of EMUs, and now Fife, where do you think is the right place? Bear in mind of course that this is ScotGov wiring with Scottish money, and therefore wiring the Oxford or Bristol lines would appear to be a questionable use of funds.
The contractor doing most of the work in Scotland - SPL - does also do work in England, and they were the contractor for the MMLe, until that got cancelled.I’d actually quite like the Scottish Govt to bid for English (or Welsh) wiring. It seems to be able to do it at a much lower price and with more pragmatism as to what is done.
Thames Valley branches anyone?
It was somewhat tongue in cheek, but there is clearly something that Scotland is doing to keep costs per single track km lower (and I’m not convinced it’s just that atm it is short branch lines).The contractor doing most of the work in Scotland - SPL - does also do work in England, and they were the contractor for the MMLe, until that got cancelled.
Not cancelling projects halfway through seems to be a pretty good place to start...It was somewhat tongue in cheek, but there is clearly something that Scotland is doing to keep costs per single track km lower (and I’m not convinced it’s just that atm it is short branch lines).
Agree. Nor changing the spec several times (Euston).Not cancelling projects halfway through seems to be a pretty good place to start...
Given that you've railed against electrification of East Kilbride for the lack of EMUs
where do you think is the right place?
Of course, what we don't (I think) know is how much the Happy Train exercise cost, and who paid for it. I suspect Hitachi was on the hook for some fairly sizeable compensation, which made the short term procurement worthwhile for the flasghip electrification scheme between Scotland's two principal cities. I somewhat doubt a similar exercise to enable a full EMU service to East Kilbride would pass the value for money test.Scotrail did a remarkable job getting Class 365s for the E&G service when the 385s were delayed but that enterprising spirit seems to have disappeared.