• Our new ticketing site is now live! Using either this or the original site (both powered by TrainSplit) helps support the running of the forum with every ticket purchase! Find out more and ask any questions/give us feedback in this thread!

HS2 Colne Valley Viaduct construction updates

Snow1964

Established Member
Joined
7 Oct 2019
Messages
11,141
Location
West Wiltshire
New drone video, with landscaping progressing,
replacing the temporary construction sites which are gradually disappearing

 
Last edited:
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

The Planner

Veteran Member
Joined
15 Apr 2008
Messages
19,689
With all the construction seemingly over - how come there's a project to put an HS2 works siding on the Up side of the Chiltern Main Line between Denham and West Ruislip? What will it be used for?
The one north of West Ruislip at Copthall is for delivering material. It isnt permanent.
 

Zomboid

Established Member
Joined
2 Apr 2025
Messages
2,294
Location
Oxford
That is just so beautiful. I thought for a moment that it was one of the CGI renders shown years ago visualising the viaduct! So polished and gleaming.

I know many look down at modern architecture, compared to Victorian examples, but I think this is special in it's own right, and I do forsee future generations will view it as a classic.
I agree, I saw it from the Chiltern line a week or two ago and thought it was a very attractive structure in a modern way, and I wouldn't be surprised if it became a part of the landscape in the same way as Ribblehead is.
 

Snow1964

Established Member
Joined
7 Oct 2019
Messages
11,141
Location
West Wiltshire
New video, It is a contractor who has been involved in removing temporary access and jetties used to build Colne Valley viaduct.

It shows the specially modified equipment, and range of equipment used to remove the temporary jetty sections that were used to get to sites of the piers and built them.

Posting it, as it is unusual to see videos posted of equipment removal including those in the water

 

TheHSRailFan

Member
Joined
16 Jun 2018
Messages
297
Wild to see the fields once taken up for factories for the Chiltern tunnels and Colne Valley Viaduct now feel so... empty, compared to say a video of the site a year or 2 back.

I wonder when the first field will reopen to the public and be walked on?
 

Snow1964

Established Member
Joined
7 Oct 2019
Messages
11,141
Location
West Wiltshire
A long drone video that seems to have been prepared for Chiltern Society as a presentation has been uploaded.

Covers the Colne Valley and Chiltern area and has lots of views of current state of construction in the area, plus some images of how some structures should look once finished.

Video Starts near Colne Valley viaduct, middle part is Chiltern tunnel

Also includes views and updates of the head houses along the Chiltern tunnel, all of which are being demobilised and will be finished Oct-Nov

The latter part of video is route north of Chiltern tunnel, various bridges and smaller viaducts

Nearly an hour long

 
Last edited:

Nicholas Lewis

Established Member
Joined
9 Aug 2019
Messages
8,008
Location
Surrey
A long drone video that seems to have been prepared for Chiltern Society as a presentation has been uploaded.

Covers the Colne Valley and Chiltern area and has lots of views of current state of construction in the area, plus some images of how some structures should look once finished.

Nearly an hour long

Excellent detail views of parts of the works and a good milestone for HS2 that the biggest viaduct is all but finished and ready to receive track and catenary masts. However, it might not see them for many years given Wilde's feedback at the Transport Select Committee saying that he wasn't mobilising railways systems prematurely like they tried to do on Crossrail.
 

hwl

Established Member
Joined
5 Feb 2012
Messages
8,257
Excellent detail views of parts of the works and a good milestone for HS2 that the biggest viaduct is all but finished and ready to receive track and catenary masts. However, it might not see them for many years given Wilde's feedback at the Transport Select Committee saying that he wasn't mobilising railways systems prematurely like they tried to do on Crossrail.
There is also the impact of having to manage the cashflow due to some of the civils contracts being very late running and very over budget. The percentage type metrics used in don't tell the whole completion picture.
Still realistically a about year before it is worth contemplating a start to rail systems and then only OOC to North Portal of Chiltern tunnel, there are just too many incomplete structures on the other two big civils contract areas for it to make sense for at least 18 months there an only for limited stretches initially as there wouldn't be a complete contiguous track bed.
I think one of the new HS2 tactics is not to give contractors a finish times is possible as it will only encourage them to need extra payments to get lots of bit finished ASAP.
Hence is it worth starting rail systems from the originally planned started single point for the OOC to North Portal of Chiltern tunnel section or wait till the it makes sense to start in parallel from the other sites further north too. Given poor progress further north anything installed soon would be gathering dust for a while, hence no point in going to early.

== Doublepost prevention - post automatically merged: ==

A long drone video that seems to have been prepared for Chiltern Society as a presentation has been uploaded.

Covers the Colne Valley and Chiltern area and has lots of views of current state of construction in the area, plus some images of how some structures should look once finished.

Video Starts near Colne Valley viaduct, middle part is Chiltern tunnel

Also includes views and updates of the head houses along the Chiltern tunnel, all of which are being demobilised and will be finished Oct-Nov

The latter part of video is route north of Chiltern tunnel, various bridges and smaller viaducts

Nearly an hour long

Worth pointing out that it is a review of what has happened in the last 6 months along the Chiltern portion of the route this means some of the content is very dated.

The key nugget in the entire video is HS2 leaning on the contractor to move construction equipment (excavators and off road Cat./Volvo tippers) and associated staff to the cut and cover tunnel at Wendover that is now on the critical path due to delays. This explains why there isn't too much of the simple earth moving going on elsewhere is everything is being thrown at this.

The HS2 site management legals the plan is that the civils contractors hand over the sections on completion to the track laying contractor who is then responsible for site management (including OHLE, singals, ventillation etc. contractors) till handover to HS2. Hence there have to be viable sections to hand over and MW dones thing there is much likely to be handoverable in the near future.

The 4 track laying logistics hubs (and start points):
  • West Ruislip (OOC to Chiltern Tunnel North Portal)
  • Calvert
  • Berkswell
  • Washwood Heath (Birmingham Spur only)
 
Last edited:

Snow1964

Established Member
Joined
7 Oct 2019
Messages
11,141
Location
West Wiltshire
HS2 has released a video that Colne Valley viaduct is now structurally complete. There are some fairly spectacular aerial images

 

Flying Phil

Established Member
Joined
18 Apr 2016
Messages
2,085
Thanks for posting and it was good to see a "team picture" at the end - they all (and the many others involved) should feel very proud.
 

Nicholas Lewis

Established Member
Joined
9 Aug 2019
Messages
8,008
Location
Surrey
Thanks for posting and it was good to see a "team picture" at the end - they all (and the many others involved) should feel very proud.
Its ironic that the longest structure on the project is completed already yet will sit there without track and catenary for many years due to slippage elsewhere.
 

J s

Member
Joined
5 Jun 2019
Messages
11
Really one of those very few times where the renders look like the end result! In fact maybe the structure which looks most like the proposed renders I can remember seeing!
 

Nottingham59

Established Member
Joined
10 Dec 2019
Messages
3,333
Location
Nottingham
Beautiful viaduct that.
Yes, sure is.

The big outstanding question is how noisy and intrusive it's going to be when operational. I know the viaduct has got sound barriers, but the experience from Japan seems to be that the noise from high speed lines is still unaccaptable for many people.
 

Snow1964

Established Member
Joined
7 Oct 2019
Messages
11,141
Location
West Wiltshire
HS2 has issued a press release (10th September) following finishing touches to structure of Colne valley viaduct.


There are new photos and video


 

vic-rijrode

Member
Joined
31 Aug 2016
Messages
446
HS2 has issued a press release (10th September) following finishing touches to structure of Colne valley viaduct.


There are new photos and video


That is truly breathtaking....
 

Snow1964

Established Member
Joined
7 Oct 2019
Messages
11,141
Location
West Wiltshire
New video of Colne Valley viaduct, including clear shots of the deck surface, showing central round drains, the walkways, and even inside where the steel cables are. Interesting.

 

Snow1964

Established Member
Joined
7 Oct 2019
Messages
11,141
Location
West Wiltshire
A new drone video of the viaduct, looks like majority of the temporary construction and haul road on landward end has now gone and the area restored with topsoil (although looks like bare mud at moment).

Second half is views of nearby old viaduct (used by Chiltern trains)

 

Snow1964

Established Member
Joined
7 Oct 2019
Messages
11,141
Location
West Wiltshire

chris2

Member
Joined
25 Apr 2023
Messages
204
Location
Southampton

paok

Member
Joined
3 May 2010
Messages
82

hwl

Established Member
Joined
5 Feb 2012
Messages
8,257

The Planner

Veteran Member
Joined
15 Apr 2008
Messages
19,689
Construction of this siding looks to be moving on now. Is it definitely not permanent? HS2 refer to "maintenance sidings".

Will it be a new junction further west of the existing junction for the West Ruislip Up Sidings one?

Yes
The siding is permanent but the connection to NR may not be (which is what I suspect The Planner is talking about)
And yes.
 

Top