A normal wire run length out from the junction would be appropriate in most cases. Notably at Westerleigh Jn the OLE continues quite far round towards Yate so that the mode change is on the straighter section.
My impression was that part of the reason for the length of OLE on the line between Westerleigh Junction and Yate South is so that an electric train can be diverted on to this line if needed, come to a stand. Driver the changes ends. And then reverse and return to Bristol Parkway (or wherever). This being the standard move if for whatever reason, the Up Badminton line is closed towards Swindon after Westerleigh Junction after a train has left Bristol Parkway.
I've not seen an IET do this, but have been on the operating floor of Bristol Panel when TVSC was temporary closed (fire alarm, but the place was evacuated). At the time, TVSC had recently taken control of the former Swindon Panel area. Hence a London bound HST from Cardiff was diverted towards Yate South and stopped clear of the junction. Then returned to Bristol Parkway.
yeah this is what i was trying to say. Putting out a contract for construction asap would be irresponsible, at least a bit of work - probably less than a year's worth would need to happen to make sure the plans are good to go and for the construction firms to get in gear themselves. Once again, the only work which is shovel ready is MML RS2, and the longer that time elapses with it not happening the greater the need to re-confirm the designs should it ever be authorised again
So, do you think all the existing columns that are present, and all the existing foundations (that are ready for columns) need "at least a bit of work" before anything can happen? If the items in the list I give below are completed, there is no reason I believe, why the existing columns can't start to be fitted with the parts needed to support the wiring.
In terms of Box Tunnel and Middle Hill tunnel, the railway does now have plenty of experience of Chipping Sodbury Tunnel and Severn Tunnel.
And there is an OHL maintenance department in the area now that will have details of any problems with the OLE that is currently fully operational.
As I said, yes, some places may need further preparation work.
Assuming that Network Rail have and can access the old plans, I would not expect preparation work to take 12 months for the section that was originally planned to be done.
However, the biggest delays would be:
- Arranging the manufacture of the OLE parts needed.
- Finding a suitable contractor.
- Getting the special train ready to work again, or getting a different one.
- Sorting out the T3 occupations and sorting out the timetable around this.
- Getting approval from the DfT and the funding from the Treasury.
So if some new surveys are needed, there is plenty of time for them. But, I do not believe a "start from scratch" full survey is needed.