• Our new ticketing site is now live! Using either this or the original site (both powered by TrainSplit) helps support the running of the forum with every ticket purchase! Find out more and ask any questions/give us feedback in this thread!

Major Power Failure Between Kings Cross and Stevenage 27/07/25

Status
Not open for further replies.

800001

Established Member
Joined
24 Oct 2015
Messages
7,382
Was it a requirement at some point? I vaguely recall some massive ‘hoo-ha’ over it (may have been cold starting though) around the Neville Hill Azuma vs HST incident
In the very very early days if you started the GU on an 801 Hitachi used to get very angry and say no you can't do it unless an emergency ie train with wires wrapped around it.

It changed to as long as LNER tell hitachi they are doing it , then it happens.

A cold start on either an 800 or an 801 knocks some many hours or something of the engine life/maintenance schedule etc so preferably a pre-heat is the preferred option for either class
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

Crossover

Established Member
Joined
4 Jun 2009
Messages
9,493
Location
Yorkshire
In the very very early days if you started the GU on an 801 Hitachi used to get very angry and say no you can't do it unless an emergency ie train with wires wrapped around it.

It changed to as long as LNER tell hitachi they are doing it , then it happens.

A cold start on either an 800 or an 801 knocks some many hours or something of the engine life/maintenance schedule etc so preferably a pre-heat is the preferred option for either class
Sounds like positive progress - at least the tail doesn’t wag the dog now by the sound of it!
 

LNW-GW Joint

Veteran Member
Joined
22 Feb 2011
Messages
21,934
Location
Mold, Clwyd
There's also the different maintenance regimes to consider between the IEP fleet (LNER 800/801) and the later AT300s (HT/TPE/Lumo 802/803), all running on the ECML.
 

High Dyke

Established Member
Joined
1 Jan 2013
Messages
5,017
Location
Yellabelly Country
Was there a wires down incident as well as the power failure? The announcements at Peterborough did seem to be blaming two separate causes for the delays in and out of Kings Cross (plus a road vehicle hitting a bridge was mentioned, although that wasn't on the ECML; IIRC it was an EMR Sheffield to Norwich train that was affected).
Not certain. The announcements I heard appertained to "overrunning engineering work" and the "power failure". I believe the engineering issue was around a set of points, but NRE doesn't always give accurate updates.
 

alxndr

Established Member
Joined
3 Apr 2015
Messages
1,694
Not certain. The announcements I heard appertained to "overrunning engineering work" and the "power failure". I believe the engineering issue was around a set of points, but NRE doesn't always give accurate updates.
The possession at Kings Cross overran due to an issue with the points.
 

Banham7

Member
Joined
12 Aug 2020
Messages
227
Location
Lincolnshire
I was actually kind of expecting this sort of incident to happen with the recovery of a lot of services after the original overrunning engineering works. There were absolutely loads of services in the Finsbury Park - Alexandra Palace area immediately after and with that "failure of the electricity supply" has been known to happen in that area in the past with many services together in a small area. The supply just cannot seem to cope.

== Doublepost prevention - post automatically merged: ==

Was there a wires down incident as well as the power failure? The announcements at Peterborough did seem to be blaming two separate causes for the delays in and out of Kings Cross (plus a road vehicle hitting a bridge was mentioned, although that wasn't on the ECML; IIRC it was an EMR Sheffield to Norwich train that was affected).
I don't believe there was a wires down incident, the train manager initially did not have any information when my service stopped at New Barnet, however after 15 minutes it came around that it was just a complete loss of power in the Harringay area and that Kings Cross was full with no electric trains being permitted to leave.
 

mike57

Established Member
Joined
13 Mar 2015
Messages
2,403
Location
East coast of Yorkshire
Kings Cross was full with no electric trains being permitted to leave.
Every time there is a major incident the inability to get trains out of Kings Cross platforms and parked up locally magnifies the problem. We had the same problem returning from holiday last year caused by a fatality at Gratham. Trains stacked up outside Kings Cross with passengers on for up to 2hrs because all the platforms were full with empty trains with nowhere to go.

I know these days contingency planning seems to be a dirty word because it costs money, but having a diesel thunderbird loco available to move stock out to the depot when things go wrong would limit disruption in all sorts of scenarios.
 

uglymonkey

Member
Joined
10 Aug 2018
Messages
708
Apart from that, money as you say, all the couplings are different so it would take ages, and there is a good chance of the thunderbird itself getting stuck behind an electric something that it can't get round or moved! Or the driver running out of hours or some such.
 

800001

Established Member
Joined
24 Oct 2015
Messages
7,382
Every time there is a major incident the inability to get trains out of Kings Cross platforms and parked up locally magnifies the problem. We had the same problem returning from holiday last year caused by a fatality at Gratham. Trains stacked up outside Kings Cross with passengers on for up to 2hrs because all the platforms were full with empty trains with nowhere to go.

I know these days contingency planning seems to be a dirty word because it costs money, but having a diesel thunderbird loco available to move stock out to the depot when things go wrong would limit disruption in all sorts of scenarios.
They could run them on the GU, but they would struggle on the banks on the way to Ferme Park etc
 
Last edited:

E27007

Member
Joined
25 May 2018
Messages
1,044
They could run them on the GU, but they would struggle on yet banks on the way to Ferme Park etc
Reports are the GU's are prone to overheating, is it the case when ascending the banks, they would overheat and shut down, or under-powered for the task?
 
Last edited:

800001

Established Member
Joined
24 Oct 2015
Messages
7,382
Reports are the GU's are prone to overheating, is it the case when ascending the banks, they would overheat and shut down, or under-powered for the task?
They would manage, and have done including in passenger use when there had been issues. The engine is literally revving like anything. Plus if it came to a stand on say the exit to Copenhagen Tunnel NR get twitchey incase it can't get going again.
 

ainsworth74

Forum Staff
Staff Member
Global Moderator
Joined
16 Nov 2009
Messages
31,122
Location
Redcar
Every time there is a major incident the inability to get trains out of Kings Cross platforms and parked up locally magnifies the problem. We had the same problem returning from holiday last year caused by a fatality at Gratham. Trains stacked up outside Kings Cross with passengers on for up to 2hrs because all the platforms were full with empty trains with nowhere to go.

I know these days contingency planning seems to be a dirty word because it costs money, but having a diesel thunderbird loco available to move stock out to the depot when things go wrong would limit disruption in all sorts of scenarios.
Yes I do sometimes wonder if disruption goes on a bit longer than perhaps it needs to were there a bit more flexibility and contingency built in but one thing I will say is that LNER are very good at making sure even significant disruption doesn't run into the next day's service.

Yesterday (28 July) and today (29 July) is a case in point. They had a horrendous Sunday with all sorts of cancellations and disruption and yet they ran the full service (as far as I can see) on the 28th other than the Flying Scotsman which was cancelled throughout. They then had a fatality in the afternoon of the 28th around 1645ish at Alexandra Palace which decimated the evening service and yet today (29 July) they've run the full service.

On the day recovery sometimes feels a bit patchy (though to be clear, and knowing some of the people involved, I have no doubt LNER staff are doing the best they can to get the show on the road as quickly as possible) but I cannot fault the way that they can take a body blow of disruption, sometimes multiple days on the trot, and yet the following morning you'd have no idea that the day before was a horror show.
 

mike57

Established Member
Joined
13 Mar 2015
Messages
2,403
Location
East coast of Yorkshire
Yes I do sometimes wonder if disruption goes on a bit longer than perhaps it needs to were there a bit more flexibility and contingency built in
We witnessed this back in October, if they had been able to clear the platforms at Kings Cross it would have been a lot easier all round. There were trains stacked up to the north unable to enter the station and offload because the trains that had already arrived had nowhere to go, so every platform was occupied by an empty train.

So any contingency to me would need to be set around being able to free platforms off by finding somewhere to put the trains once they had arrived and offloaded. My guess is back in October the disruption lasted about 60-90 mins longer than it need have done because of this issue. The impact obviously then mushrooms further because a crew sat a mile or two to the north being unable access a platform for an hour are then burning hours as well.

How does Kings Cross with 12 (or 11? not sure, haven't used the suburban platforms for 40 years) platforms stack up against the other major London terminals in terms of departures and arrivals per hour. It always seems to be one of the more heavily used stations and always has done, I know they added platform 0, but thats pretty much it, there is nowhere else to go without some serious demolition.

Maybe they need to have a word with Harry Potter and get Platform 9 3/4 back into passenger use:lol:
 

harz99

Member
Joined
14 Jul 2009
Messages
913
Yes I do sometimes wonder if disruption goes on a bit longer than perhaps it needs to were there a bit more flexibility and contingency built in but one thing I will say is that LNER are very good at making sure even significant disruption doesn't run into the next day's service.

Yesterday (28 July) and today (29 July) is a case in point. They had a horrendous Sunday with all sorts of cancellations and disruption and yet they ran the full service (as far as I can see) on the 28th other than the Flying Scotsman which was cancelled throughout. They then had a fatality in the afternoon of the 28th around 1645ish at Alexandra Palace which decimated the evening service and yet today (29 July) they've run the full service.

On the day recovery sometimes feels a bit patchy (though to be clear, and knowing some of the people involved, I have no doubt LNER staff are doing the best they can to get the show on the road as quickly as possible) but I cannot fault the way that they can take a body blow of disruption, sometimes multiple days on the trot, and yet the following morning you'd have no idea that the day before was a horror show.
And how much of that recovery is due to services run by Hull trains, Grand Central, and LUMO being given the short straw and pushed out of the way despite being able to run at line speed, and often in their correct paths, thus perpetuating a two tier railway, (LNER and the rest)..
.
 

D6130

Established Member
Joined
12 Jan 2021
Messages
9,114
Location
West Yorkshire/Tuscany
And how much of that recovery is due to services run by Hull trains, Grand Central, and LUMO being given the short straw and pushed out of the way despite being able to run at line speed, and often in their correct paths, thus perpetuating a two tier railway, (LNER and the rest)..
.
Don't think LUMO would be able to run at line speed - or at any speed at all really - during a power failure. Their trains are electric only.
 

Horizon22

Established Member
Associate Staff
Jobs & Careers
Joined
8 Sep 2019
Messages
11,010
Location
London
How does Kings Cross with 12 (or 11? not sure, haven't used the suburban platforms for 40 years) platforms stack up against the other major London terminals in terms of departures and arrivals per hour. It always seems to be one of the more heavily used stations and always has done, I know they added platform 0, but thats pretty much it, there is nowhere else to go without some serious demolition.

Maybe they need to have a word with Harry Potter and get Platform 9 3/4 back into passenger use:lol:

Kings Cross has a very high % of services as intercity, long-distance services which means longer turnarounds and therefore longer platform utilisation. With the exception of the Great Northern services this means that capacity is less than somewhere like Liverpool St (if the latter also had 12 platforms).
 
Joined
5 Aug 2015
Messages
913
Location
Norfolk
To clarify, is that faults at two grid to Network Rail substations, so they (NG) tried to send all the power through the next nearest substation? Which obviously was not able to cope with three substations of load so shut down?
Presumably Network Rail would have been involved in this decision making, unless it was very sudden?
The different feeder stations are all off different circuits so I interpreted it more like two feeding points were lost and a third one couldn't stretch to cover that distance/load no matter how much power was available to it. There aren't any grid power lines specifically for moving around load to/from railway substations so as far as I understand it, it doesn't really make sense to say that the grid operators tried to divert or send "the power" meant for one place instead to another.

The other thing to consider is which feeder stations we're talking about. The National Grid supplied ones are Corey's Mill and (i think?) Little Barford (both of which have 2 supplies each), but that's too far north. So if we mean "national grid" generically then we mean Wood Green, Ferme Park and Welwyn feeder stations which are all supplied by UKPN and are all directly relevant to an area described as "kings cross to Stevenage". This diagram is my understanding/guessing about the arrangement (the big Ns are of course neutral sections)
1753823677626.png
I was actually kind of expecting this sort of incident to happen with the recovery of a lot of services after the original overrunning engineering works. There were absolutely loads of services in the Finsbury Park - Alexandra Palace area immediately after and with that "failure of the electricity supply" has been known to happen in that area in the past with many services together in a small area. The supply just cannot seem to cope.
This seems believable to me and makes sense with the effected area and "3 into 1" thing. Ferme Park and Wood Green are both supplied from the same dual circuit 132kV powerline, so if demand was suddenly too much in the Finsbury Park area, the fault would trip Ferme Park - but Wood Green can't supply both the Hertford Loop and suddenly-high-demand mainline to Kings Cross and so also trips, presuming that it's programmed to automatically cover for Ferme Park which seems believable. The Welwyn supply then can't cover for both of those. Could also have been the case that either Wood Green or Ferme Park was already out of use at that particular time, as the full timetable is expected to be supported with one supply lost.
 

Tom B

Established Member
Joined
27 Jul 2005
Messages
4,681
Every time there is a major incident the inability to get trains out of Kings Cross platforms and parked up locally magnifies the problem. We had the same problem returning from holiday last year caused by a fatality at Gratham. Trains stacked up outside Kings Cross with passengers on for up to 2hrs because all the platforms were full with empty trains with nowhere to go.

I know these days contingency planning seems to be a dirty word because it costs money, but having a diesel thunderbird loco available to move stock out to the depot when things go wrong would limit disruption in all sorts of scenarios.
Disappointing given that there was a huge inquiry about this in 2014 after the disaster that was caused when they failed to finish works on time, and then tried to terminate everything at Finsbury Park, and then used overcrowding as the excuse - on an extremely busy day when funnelling people through a tiny station!

I thought then, and still wonder, if it wouldn't be beneficial to allow passengers to leave if desired at suburban stations when the train is stood there for a considerable time. New Southgate, New Barnet, Haringey, etc all have tube links not too far away.
 

Banham7

Member
Joined
12 Aug 2020
Messages
227
Location
Lincolnshire
I thought then, and still wonder, if it wouldn't be beneficial to allow passengers to leave if desired at suburban stations when the train is stood there for a considerable time. New Southgate, New Barnet, Haringey, etc all have tube links not too far away.
The Train Manager I had on 1A16 (10-car Azuma) stated that they were unable to release the doors as the train was too long for the platforms at New Barnet and New Southgate and we were not fully accommodated, so it would not be possible to get any fresh air, and that passengers should remain onboard and not attempt to pull the emergency egress handles.
 

Magdalia

Established Member
Joined
1 Jan 2022
Messages
7,404
Location
The Fens
We witnessed this back in October, if they had been able to clear the platforms at Kings Cross it would have been a lot easier all round. There were trains stacked up to the north unable to enter the station and offload because the trains that had already arrived had nowhere to go, so every platform was occupied by an empty train.
The long distance operators filling all the platforms in the main trainshed at Kings Cross during disruption is not a new thing. It was already happening when I finished commuting more than 15 years ago.

The problem isn't having nowhere for the trains to go, the problem is having nobody to drive them because of traincrew being out of place.

Disappointing given that there was a huge inquiry about this in 2014 after the disaster that was caused when they failed to finish works on time, and then tried to terminate everything at Finsbury Park, and then used overcrowding as the excuse - on an extremely busy day when funnelling people through a tiny station!
This incident is quite different from 27 December 2014, with the power supply problems spread over a wider area.

Overcrowding on 27 December 2014 was not an excuse, it was a fact. In particular there were very long dwell times for up long distance trains terminating at Finsbury Park, because of the narrow gap between the station building and the platform edge, and the narrow stairway off the platform.

I thought then, and still wonder, if it wouldn't be beneficial to allow passengers to leave if desired at suburban stations when the train is stood there for a considerable time. New Southgate, New Barnet, Haringey, etc all have tube links not too far away.
A very long time ago I did this at New Barnet when an up train, formed of a single class 365, was held there because of a fire at New Southgate. I succeeded in persuading the driver to open the doors, and then led a crocodile of passengers up the hill to High Barnet. It is a long walk, about a mile, and High Barnet isn't called that for nothing.

The Train Manager I had on 1A16 (10-car Azuma) stated that they were unable to release the doors as the train was to long for the platforms at New Barnet and New Southgate and we were not fully accommodated
It was only possible to do this because the train that I abandoned at New Barnet was only 4 cars.
 

mike57

Established Member
Joined
13 Mar 2015
Messages
2,403
Location
East coast of Yorkshire
All the points raised by @Tom B @Banham7 and @Magdalia all really come back to the same thing, lack of contingency planning.

Set up a way to allow the train manager to open individual doors irrespective of location. No software interlocks, as systems can and do fail, maybe just a key release behind a keycoded key safe, which can be quickly restored once the incident is over. Deals with short platform issue and overcrowding, somewhere like Finsbury Park opening just two doors would limit the flow of passengers. If the passengers see that something is being done they will be less likely to take matters into their own hands and use the emergency exit handles. If you are worried about the train manager 'getting it wrong' set it up so that the procedure for any out of the ordinary opening has to be confirmed by the driver.

At somewhere as congested as Kings Cross having some sort of 'thunderbird' capability would seem to make sense, either to deal with a failed train or to assist with recovery in the event of disruption, but the bean counters dont like it, and in the current 'race to bottom' railway it doesn't happen.

The 'Balkanisation' of the railways hasn't helped. In the event of disruption 'ToC' should be binned, if the bean counters want to play monopoly behind the scenes afterwards let them, but things like ticket acceptance needs to be the default, not something that has to be confirmed.

There is a lot that could be done fairly simply, but the current structure and higher management (i.e. DfT micromanagement) means it doesn't happen. Incidents will happen, things will go wrong, having a robust plan B in place to cover likely forseeable impacts e.g. Kings Cross platforms blocked by empty trains, which is a likely outcome to a lot of initially dis-similar incidents would make sense.
 

Falcon1200

Established Member
Joined
14 Jun 2021
Messages
6,587
Location
Neilston, East Renfrewshire
At somewhere as congested as Kings Cross having some sort of 'thunderbird' capability would seem to make sense

A Thunderbird at Kings X would be useful for rescuing a failed or stranded train, but given the time it would take to attach to a train, haul it away to (presumably) Bounds Green, detach and return to the Cross, it might not not make a great difference to clearing platforms.
 

Magdalia

Established Member
Joined
1 Jan 2022
Messages
7,404
Location
The Fens
having a robust plan B in place to cover likely forseeable impacts e.g. Kings Cross platforms blocked by empty trains
The contingency plan exists, it involves terminating at Peterborough and Stevenage.

At somewhere as congested as Kings Cross having some sort of 'thunderbird' capability would seem to make sense
A Thunderbird is not much use for moving empty trains at Kings Cross because of the location of the carriage sidings at Bounds Green. A Thunderbird loco can't run round the train in the Bowes Park reversing siding, which would be required to get onto Bounds Green.
 

800001

Established Member
Joined
24 Oct 2015
Messages
7,382
The contingency plan exists, it involves terminating at Peterborough and Stevenage.


A Thunderbird is not much use for moving empty trains at Kings Cross because of the location of the carriage sidings at Bounds Green. A Thunderbird loco can't run round the train in the Bowes Park reversing siding, which would be required to get onto Bounds Green.
It would have to haul trains and leave them at Ferme Park sidings.

== Doublepost prevention - post automatically merged: ==

All the points raised by @Tom B @Banham7 and @Magdalia all really come back to the same thing, lack of contingency planning.

Set up a way to allow the train manager to open individual doors irrespective of location. No software interlocks, as systems can and do fail, maybe just a key release behind a keycoded key safe, which can be quickly restored once the incident is over. Deals with short platform issue and overcrowding, somewhere like Finsbury Park opening just two doors would limit the flow of passengers. If the passengers see that something is being done they will be less likely to take matters into their own hands and use the emergency exit handles. If you are worried about the train manager 'getting it wrong' set it up so that the procedure for any out of the ordinary opening has to be confirmed by the driver.

At somewhere as congested as Kings Cross having some sort of 'thunderbird' capability would seem to make sense, either to deal with a failed train or to assist with recovery in the event of disruption, but the bean counters dont like it, and in the current 'race to bottom' railway it doesn't happen.

The 'Balkanisation' of the railways hasn't helped. In the event of disruption 'ToC' should be binned, if the bean counters want to play monopoly behind the scenes afterwards let them, but things like ticket acceptance needs to be the default, not something that has to be confirmed.

There is a lot that could be done fairly simply, but the current structure and higher management (i.e. DfT micromanagement) means it doesn't happen. Incidents will happen, things will go wrong, having a robust plan B in place to cover likely forseeable impacts e.g. Kings Cross platforms blocked by empty trains, which is a likely outcome to a lot of initially dis-similar incidents would make sense.
There are already procedures in place to open 'one or two' doors so customers can get fresh air, or alight and leave the service.

I've been on several trains that have done that. (XC at Willington one door opened).

Also been on a mk4 with no power and the staff requested help from off duty staff or willing customers to stand guard at opened doors where they put a door guard across while door was open (piece of fabric on a pole).

The above were both requested and granted by control.
 

800001

Established Member
Joined
24 Oct 2015
Messages
7,382
How much siding space is available at Ferme Park?

And would the Thunderbird still have to go to Bowes Park to get back to Kings Cross?
Can get at least 4-5 (poss more can't remember how many stable each night) full length sets in there.

Loco could go to Bowes Park if needed, or could reverse in a siding next to Hornsey station and return south via the Harringay Flyover.
 

Magdalia

Established Member
Joined
1 Jan 2022
Messages
7,404
Location
The Fens
or could reverse in a siding next to Hornsey station and return south via the Harringay Flyover.
I thought that the Hornsey reversing sidings were only accessible from the down slow lines, and not from Ferme Park, though it is a long time since I looked!
 

800001

Established Member
Joined
24 Oct 2015
Messages
7,382
I thought that the Hornsey reversing sidings were only accessible from the down slow lines, and not from Ferme Park, though it is a long time since I looked!
my mistake!! I'm thinking of when they run booked ecs Kings Cross to Bowes Park To Kings Cross.

You are indeed correct, no access to the reversing sidings from Ferme Park

Although that does mean that they can still be dragged to Ferme Park and loco can continue to Bowes Park to return to Kings Cross.
 

harz99

Member
Joined
14 Jul 2009
Messages
913
Why a Thunderbird loco, why not a Thunderbird driver trained on all stock types, and able to do ECS moves to the requisite stabling points? Admittedly only one train moved at a time and probably a maximum of 2 trains moved given the time required to get back, but still better than nothing.
 

800001

Established Member
Joined
24 Oct 2015
Messages
7,382
Why a Thunderbird loco, why not a Thunderbird driver trained on all stock types, and able to do ECS moves to the requisite stabling points? Admittedly only one train moved at a time and probably a maximum of 2 trains moved given the time required to get back, but still better than nothing.
I think people are on about when the OHL power is off and trains are cancelled.
They need shifting, as when services resume they are blocking platforms for arriving trains.
A thunderbird would be able to move the trains when no OHL power.
 