Aylesbury electrification - how would this happen?

Status
Not open for further replies.

Zomboid

Established Member
Joined
2 Apr 2025
Messages
2,299
Location
Oxford
It was mentioned that OOC might turn 4tph from Chiltern (HW, Banbury, Oxford, Aylesbury/MKC) - I'd think 2x 2tph better personally - but this would free up a decent amount of paths out of Marylebone
Is there going to be capacity at OOC for that much? I don't know what space there will be for platforms, but I had the impression that it was going to be just the one for the Ruislip line, and how much of the route that way will be doubled?

If you're going to go for 4tph to a variety of destinations then the line really needs to be doubled throughout and 2 or 3 platforms provided at OOC.
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

A S Leib

Established Member
Joined
9 Sep 2018
Messages
3,340
Only option that makes logical sense to me is cutting the Met back to Watford and Uxbridge, and maybe Rickmansworth at an absolute push if you could justify rebuilding it and extending the four tracks from Watford south junction to it (which I think you would struggle with, IMHO), though you would need at least a single track to the stabling there unless you recreated new provision elsewhere, such as reinstating the sidings at Watford Junction, or something at Watford Met.

Chiltern then provides the Amersham service, and Chesham goes back to a shuttle.
I think I've already said this elsewhere in this thread, but that doesn't seem like a desirable outcome given the loss of direct City services and the change from a direct service to walking from Marylebone to Baker Street; even if frequent options are available from Harrow-on-the-Hill, Uxbridge peak services aren't quiet enough for those to provide enough capacity.

TfL's statistics put Chesham to stations north of Moor Park inclusive at 417 passengers per day (counting "less than 10 passengers" as 9); it's 439 for stations between Great Portland Street and Euston inclusive.

My preferred option would be putting Chalfont & Latimer on the Elizabeth line if not keeping it on the Met. That would keep the current connections with everything except mainline services at Euston (some passengers would go to Watford Junction anyway), King's Cross and St. Pancras and the Victoria line. The negatives would be cost and adding in the possibility of delays from the Met (and by extension other sub-surface lines) in addition to those from the Great Western Main Line.

With the current infrastructure, would 4 tph as a Chesham shuttle be sustainably reliable? Admittedly if the plan is to run 6 tph to Amersham, it might be better to run 3 tph to Chesham and make sure connections match each way anyway.
 

Zomboid

Established Member
Joined
2 Apr 2025
Messages
2,299
Location
Oxford
Putting the Met north of Watford and the line to Aylesbury onto a crossrail type service would be operationally quite good (let's just park the bit where the tunnel gets built, but it could offer a service through to the city and better tube interchanges than Marylebone can), but would a tube train with ideas above it's station be popular with the outer end? I don't believe the Crossrail service was necessarily welcomed with open arms at places like Twyford because of the reduction in interior quality (though the GWR 38whatevers aren't exactly a lesson in comfort themselves).
 

HSTEd

Veteran Member
Joined
14 Jul 2011
Messages
20,330
Putting the Met north of Watford and the line to Aylesbury onto a crossrail type service would be operationally quite good (let's just park the bit where the tunnel gets built, but it could offer a service through to the city and better tube interchanges than Marylebone can), but would a tube train with ideas above it's station be popular with the outer end? I don't believe the Crossrail service was necessarily welcomed with open arms at places like Twyford because of the reduction in interior quality (though the GWR 38whatevers aren't exactly a lesson in comfort themselves).
I think they might complain a bit in the abstract, but once they understand what they are getting they will not regret it afterwards.

Even from Amersham the passenger split is approximately even-even, about the same as the number of trains provided. I don't think there is any great preference for the existing diesel trains as is, even versus literal S-Stock.
 

150219

Member
Joined
24 Nov 2009
Messages
471
And don't forget, they only have to get to Neasden. Tons of capacity between there and Harrow on the Hill.
Not with the current signalling there's not.

If there was a significant investment and change of the infrastructure to the point that OHLE and changes to signalling and points maybe, but not as it currently stands.
 

cle

Established Member
Joined
17 Nov 2010
Messages
5,644
Is there going to be capacity at OOC for that much? I don't know what space there will be for platforms, but I had the impression that it was going to be just the one for the Ruislip line, and how much of the route that way will be doubled?

If you're going to go for 4tph to a variety of destinations then the line really needs to be doubled throughout and 2 or 3 platforms provided at OOC.
I don't know about double tracking, but did recall two bays at OOC in the plan - which is more than enough. I think having two 2tph services would be easier for interworking/turns, but perhaps not.

I don't really know that the Amersham route is worth a Crossrail type set-up, it's quiet and very peak heavy. Crossrail works because it has multiple nodes, but also counter-peak demand (Stratford, Romford, Shenfield connections east, Slough/LHR/Reading west) so it does a lot of different journeys. And offers a ton of connections. The Amersham route is a one way street.

There aren't really jobs or bigger towns out on the Met line (Watford itself has some inbound demand but would never compete with Euston services) - - - it's sort of suburbia.

Whereas these investments work where either there is multiple use of capacity (airports, outer centres/counter-commutes/rail hubs) - OR - mass homebuilding like the Lea Valley. And that isn't happening in Metroland!
 
Joined
5 Aug 2015
Messages
913
Location
Norfolk
Most o
Not with the current signalling there's not.

If there was a significant investment and change of the infrastructure to the point that OHLE and changes to signalling and points maybe, but not as it currently stands.
Electrification quite often comes along with re-signalling and other enhancements. I think the MML is right now the only significant electrification project that doesn't have a resignalling component - and that makes it a bit unusual.
 

Zomboid

Established Member
Joined
2 Apr 2025
Messages
2,299
Location
Oxford
I don't know about double tracking, but did recall two bays at OOC in the plan - which is more than enough. I think having two 2tph services would be easier for interworking/turns, but perhaps not
2 platforms is probably enough, but you're not getting 4tph each way all the way to Ruislip without doubling a decent chunk of it. There's probably more margin if they didn't go to 4 different destinations as you wouldn't get a delay at Islip causing another delay at Aylesbury because of a stretch of single track or not having enough flexibility at OOC.
 

cle

Established Member
Joined
17 Nov 2010
Messages
5,644
I think 2tph to High Wycombe and 2tph to Oxford would be best, the Oxfords are more semi-fast now anyway - and it doesn't necsssarily need a Marylebone service. The Paddington is too competitive, and will get to OOC quicker!

But Bicester Village and Oxford Parkway will need their Marylebone - so potentially that could be peak only, or a 1tph on top of 2tph semi. The Village/tourists are counter-flow and off peak so we have to factor that in.
 

Zomboid

Established Member
Joined
2 Apr 2025
Messages
2,299
Location
Oxford
As a user of OXP, I'd probably prefer Marylebone. For each individual it'll depend on the final destination, but in general the faff of getting to the city centre more than offsets the slower journey time from Parkway, plus Baker Street is better connected than Paddington or OOC would be.

Be interesting to see if the Cowley branch traffic for London changes at OXF or if the single seat ride to MYB is more appealing. Will depend on the connection times I'd guess.
 

The Planner

Veteran Member
Joined
15 Apr 2008
Messages
19,697
2 platforms is probably enough, but you're not getting 4tph each way all the way to Ruislip without doubling a decent chunk of it. There's probably more margin if they didn't go to 4 different destinations as you wouldn't get a delay at Islip causing another delay at Aylesbury because of a stretch of single track or not having enough flexibility at OOC.
You could do 4tph on one platform if you can keep a 5 minute reoccupation and 10 minute turnaround.
 

Zomboid

Established Member
Joined
2 Apr 2025
Messages
2,299
Location
Oxford
Assuming they're evenly spaced and there's a passing place close by. All seems a bit too PSR to me when we're talking about a megaproject like OOC - a second platform for the Ruislip line must be a pretty marginal cost in the scheme of things.
 

MarkyT

Established Member
Joined
20 May 2012
Messages
7,576
Location
Torbay
Assuming they're evenly spaced and there's a passing place close by. All seems a bit too PSR to me when we're talking about a megaproject like OOC - a second platform for the Ruislip line must be a pretty marginal cost in the scheme of things.
If you're building a platform with access (and all that), you might as well put another track on the other side, even if there's a single lead junction in the throat serving both.
 

Dstock7080

Established Member
Joined
17 Feb 2010
Messages
3,522
Location
West London
With the current infrastructure, would 4 tph as a Chesham shuttle be sustainably reliable? Admittedly if the plan is to run 6 tph to Amersham, it might be better to run 3 tph to Chesham and make sure connections match each way anyway.
Currently 8½min running time each way on the Chesham branch, not including stand time, 3tph at best.
 

zwk500

Veteran Member
Joined
20 Jan 2020
Messages
18,569
Location
Northampton

Bletchleyite

Veteran Member
Joined
20 Oct 2014
Messages
113,489
Location
"Marston Vale mafia"
The problem with operating that service is that it'd get utterly swamped whenever there was WCML disruption if it was a through service. It's also not that useful as one.

My inclination would be to go for connectivity and do an MKC-Risborough service replacing the Chiltern shuttle. That could still be used in disruption, but at least it would mean people would be spread around by driving to various places and taking the Oxford, Marston Vale and Aylesbury services for connections rather than swamping one short DMU and preventing people from Aylesbury etc being able to board it at all.
 

Trainbike46

Established Member
Joined
18 Sep 2021
Messages
4,374
Location
belfast
Fastest Journey from Marylebone to Aylesbury is advertised as 49 minutes. Milton Keynes to Aylesbury was touted as 33 minutes in some early publicity a quick google has turned up. https://www.eastwestrail.org.uk/wp-content/uploads/2015/03/2013814_east_west_rail_leaflet_2.pdf

So somewhere in the 2h05-2h15 area depending on stops and exact timings, I'd say.
How does that follow?

49 minutes to Aylesbury + 5 minutes at Aylesbury + 33 minutes to MK = 87 minutes, or 1.5 hours approximately.

How do you get to 2h05-2h15?

The problem with operating that service is that it'd get utterly swamped whenever there was WCML disruption if it was a through service. It's also not that useful as one.

My inclination would be to go for connectivity and do an MKC-Risborough service replacing the Chiltern shuttle. That could still be used in disruption, but at least it would mean people would be spread around by driving to various places and taking the Oxford, Marston Vale and Aylesbury services for connections rather than swamping one short DMU and preventing people from Aylesbury etc being able to board it at all.
That does sound more useful!
 

Zomboid

Established Member
Joined
2 Apr 2025
Messages
2,299
Location
Oxford
The present normal stopping service from Aylesbury to Marylebone seems to take 64 minutes. Via Princes Risborough it's more like 80 minutes on a direct train.
 

Bletchleyite

Veteran Member
Joined
20 Oct 2014
Messages
113,489
Location
"Marston Vale mafia"
The present normal stopping service from Aylesbury to Marylebone seems to take 64 minutes. Via Princes Risborough it's more like 80 minutes on a direct train.

Aside from during engineering works and enthusiasts that (when it runs) isn't really used by people as a through service. It's about connectivity. Generally it runs as an all stations service with it being quicker to change at Risborough than stay on board all the way to Marylebone.
 

zwk500

Veteran Member
Joined
20 Jan 2020
Messages
18,569
Location
Northampton
How does that follow?

49 minutes to Aylesbury + 5 minutes at Aylesbury + 33 minutes to MK = 87 minutes, or 1.5 hours approximately.

How do you get to 2h05-2h15?
I will be honest, I think I must have just dropped an almighty howler and added an hour on. I won't even claim a mistype!
The problem with operating that service is that it'd get utterly swamped whenever there was WCML disruption if it was a through service. It's also not that useful as one.
The only people it'd be particularly useful to would be Winslow who would otherwise have no direct London serivce, but even they'd probably be quicker changing at Bletchley.
My inclination would be to go for connectivity and do an MKC-Risborough service replacing the Chiltern shuttle. That could still be used in disruption, but at least it would mean people would be spread around by driving to various places and taking the Oxford, Marston Vale and Aylesbury services for connections rather than swamping one short DMU and preventing people from Aylesbury etc being able to board it at all.
Agree, although keeping them separate may be necessary at first for initial introduction.
 

cle

Established Member
Joined
17 Nov 2010
Messages
5,644
The problem with operating that service is that it'd get utterly swamped whenever there was WCML disruption if it was a through service. It's also not that useful as one.

My inclination would be to go for connectivity and do an MKC-Risborough service replacing the Chiltern shuttle. That could still be used in disruption, but at least it would mean people would be spread around by driving to various places and taking the Oxford, Marston Vale and Aylesbury services for connections rather than swamping one short DMU and preventing people from Aylesbury etc being able to board it at all.
If through London services ended via Monks - and it was a shuttle, then yes, linking two shuttles is good.

But I'd suggest getting to High Wycombe would be much more successful. If it had a western-facing bay, that would be ideal.

On the other hand, is there any demand for Amersham (vs High Wycombe) - and those stations. Issue is they are much closer to WCML and M1 for anyone needing to travel to MK.
 

AlastairFraser

Established Member
Joined
12 Aug 2018
Messages
4,162
Would there be a micro-fleet?
Alstom still market the 'Movia' product, so I would assume that the service to Aylesbury would simply be run by another batch of S-stock. Assuming the fall in peak traffic since coronavirus is not sufficient to cover the extra diagrams by stretching the fleet.
Perhaps Chiltern ordering a mainline version of the Movia product with a slightly higher top speed of 75mph (plus battery capacity for AVP to Aylesbury/Neasden to Marylebone) would make sense.

Yes, it doesn't free up massive amounts of capacity at Marylebone, but it frees up some 165s for potential cascade, allows Chiltern to make good use of existing LU electrification, and with improved acceleration from electric operation, you could see some journey time improvements.

There's also the environmental incentive to remove some internal combustion powered units from London's last terminal and the order could provide work for the ex-Bombardier works at Derby (so there is political incentive to push for investment under the new GWR regime).
 

Railwaysceptic

Established Member
Joined
6 Nov 2017
Messages
1,737
The problem with operating that service is that it'd get utterly swamped whenever there was WCML disruption if it was a through service. It's also not that useful as one.
Whenever a major railway line is closed the result is inconvenience and sometimes chaos for the affected passengers. In the event of a WCML incident preventing access to Euston, alighting at Bletchley or Milton Keynes and taking a DMU to Aylesbury would be a pretty minor irritation.

Five days a week, Chiltern Railways lengthen their Marylebone to Aylesbury trains during peak periods. Once they were informed that the WCML was blocked, they would use longer trains. The question is how quickly they could respond.

As the WCML is not blocked very often, this issue is not a substantive argument against running trains between Aylesbury and Bletchley.
 

CR165022

Established Member
Joined
12 Nov 2019
Messages
1,410
Location
Buckinghamshire
Five days a week, Chiltern Railways lengthen their Marylebone to Aylesbury trains during peak periods.
I wish that was the case! Peak services are formed of either 3 or 4 carriages, which is the same as off peak, with some even being 2! 6 Carriages can't happen unless some are locked out, and there's only 2 5 cars booked, one early morning and one late night.
 

The Ham

Veteran Member
Joined
6 Jul 2012
Messages
12,036
The problem with operating that service is that it'd get utterly swamped whenever there was WCML disruption if it was a through service. It's also not that useful as one.

If we planned for "what if x happens" then either we'd have a lot more capacity or no new services.

I've heard of a similar argument with road traffic "when the major dual carriageway/motorway has an incident or local roads get grid locked, we therefore need more local road capacity"

The flaw with that is that almost whatever you do will likely result in more traffic and so the roads would end up grid locked anyway.

The same would be true here, either accept that there's going to be congestion and people will travel by whichever options are available to them 1% of the time or provide a service which is useful 99% of the time.
 