I see that Mark Wild (CEO of HS2 Ltd) is now saying that the overspend on HS2 phase 1 is likely to be 50% to 100%.
www.theguardian.com
EDIT: The official video of the Transport Committe session is available here:
HS2 already billions over budget with work ‘just over halfway done’, says rail boss
Total overspend on high-speed rail could be as high as 100%, Mark Wild, who runs the project, told MPs
HS2 construction contracts priced at £19.5bn have already cost £26bn despite being “just over halfway done”, the boss of the high-speed rail project has told MPs.
Civil engineering to build tunnels and cuttings for the 100-mile line should be almost finished but is closer to 60% complete, while only a third of the wider project – including laying tracks and wiring – is done, the transport select committee heard on Wednesday.