East Midlands Railway BEMUs by 2033: How could this be achieved?

Status
Not open for further replies.

QSK19

Member
Joined
29 Dec 2020
Messages
1,149
Location
Leicestershire
Moderator note: Split from

https://www.eastmidlandsrailway.co.uk/media/4062/download?inline
Region fleet strategy, though yet to be funded/confirmed – will see BEMUs
introduced from 2033
On a rather interesting side note, it states BEMUs replacing the Regional fleet from 2033.
 
Last edited by a moderator:
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

Killingworth

Established Member
Joined
30 May 2018
Messages
6,502
Location
Sheffield
On a rather interesting side note, it states BEMUs replacing the Regional fleet from 2033.
'From 2033' is probably near enough to satisfy the green lobby now and far enough away for those telling the story to be well out of the way when it actually happens.
 

Nym

Established Member
Joined
2 Mar 2007
Messages
9,800
Location
Somewhere, not in London
Got to wonder where these "Battery-Electric" multiple units are going to charge themselves on some of the more 'regional' routes on the network if they don't have a means of self powering.

Feels a lot more like a green-wash than a strategy to me.
 

Carntyne

Member
Joined
8 Jul 2015
Messages
1,026
Got to wonder where these "Battery-Electric" multiple units are going to charge themselves on some of the more 'regional' routes on the network if they don't have a means of self powering.

Feels a lot more like a green-wash than a strategy to me.
The OLE?
 

hwl

Established Member
Joined
5 Feb 2012
Messages
8,293
And where’s this “OLE” you speak of east of Grantham and Nottingham / Newark…?
About half should be replaceable with the expected MML wiring. The other half is a completely different matter as you say.

Hence BEMUs replacing the 158 fleet at 40 years old is probably on the cards with the 170 fleet remaining at the point.
 

poffle

Member
Joined
11 Oct 2023
Messages
239
Location
Dublin, Ireland
Got to wonder where these "Battery-Electric" multiple units are going to charge themselves on some of the more 'regional' routes on the network if they don't have a means of self powering.

Feels a lot more like a green-wash than a strategy to me.
They'll need battery charging at the termini.

Irish Rail are introducing a new fleet of BEMUs but one of the major issues is getting a high capacity grid connection for charging. Similar issues with Electric Bus introduction and getting chargers into garages.
 

duffield

Established Member
Joined
31 Jul 2013
Messages
3,302
Location
East Midlands
And where’s this “OLE” you speak of east of Grantham and Nottingham / Newark…?
Just considering the situation east of Nottingham with BEMUs, a Nottingham to Norwich service topping up at Nottingham, between Grantham and Peterborough (30+ minutes under the wires), at ELy (about 10 minutes in the wired section with the reversal) and at the terminus at Norwich (currently 30 minutes) should be possible, assuming Nottingham *does* get wired by 2033.

Although Ely to Norwich might be a stretch with some older generation BEMUs (50 mile range when fully charged) by 2033 it's not unreasonable to expect them to be able to manage this.

Nottingham to Skegness looks much more difficult, no decent charging opportunities the whole way except a brief topup at Grantham.

A Nottingham-Newark-Lincoln shuttle should easily be doable if you just had a charging bay and enough layover time at Lincoln, it's only 35 miles. But through services to Grimsby and Cleethorpes without significant charging stops at (say) Lincoln and Grimsby might be trickier.

So if the government is serious about getting rid of DMUs there will need to be some charging bays and at least some discontinuous OHLE in places where it's cheaper and simpler to erect, i.e. sections with few problem bridges, tunnels and junctions.

Although it all depends on how far and fast battery capacity, charging rates (and prices) improve in the next few years. A *lot* of money is being invested in this area mainly for electric road vehicles but much of the development should apply to rail vehicles as well.
 

tfw756rider

On Moderation
Joined
30 Nov 2024
Messages
1,997
Location
Wales (sometimes in England), thanks for replying!
About half should be replaceable with the expected MML wiring. The other half is a completely different matter as you say.

Hence BEMUs replacing the 158 fleet at 40 years old is probably on the cards with the 170 fleet remaining at the point.
I've previously said on this forum that if a certain set of lines in the West Midlands was electrified by/in the early 2030s (which would require new electric trains), the East Midlands could acquire the 172/2s and 172/3s (ideally with tables added) to replace the 158s, so that would've been going from [158s and 170s] to [170s and 172s].

Therefore, if the above mentioned project on the other side of the region were to happen, perhaps this side's regional operations could instead go from [158s and 170s] to [172s and BEMUs].
 

absolutelymilk

Established Member
Joined
18 Jul 2015
Messages
1,608
Although Ely to Norwich might be a stretch with some older generation BEMUs (50 mile range when fully charged) by 2033 it's not unreasonable to expect them to be able to manage this.
Possibly a silly question, but why is the range of BEMUs so much less than for an electric car, which can already do several hundred miles when fully charged? I thought that rail vehicles were much more efficient because of the lower rolling friction.
 

Thirteen

Established Member
Joined
3 Oct 2021
Messages
1,904
Location
London
8 years is plenty of time for battery technology for BEMU to progress to the levels which are needed.
 

QSK19

Member
Joined
29 Dec 2020
Messages
1,149
Location
Leicestershire
8 years is plenty of time for battery technology for BEMU to progress to the levels which are needed.
Presumably it would be more like 6 years seeing as 2033 is the theoretical introduction into service - would have thought the trains would start being built a couple of years beforehand.

But yes, I agree that it’s a good chunk of time for BEMUs to progress towards a decent level of battery range.
 

Nottingham59

Established Member
Joined
10 Dec 2019
Messages
3,350
Location
Nottingham
Got to wonder where these "Battery-Electric" multiple units are going to charge themselves on some of the more 'regional' routes on the network if they don't have a means of self powering.

Feels a lot more like a green-wash than a strategy to me.
The answer is tri-modes on some routes and Static Frequency Converters on others.

A tri-mode BEMU would only need a tiny diesel engine to give it unlimited range, especially on slow lines through a flat landscape like Lincolnshire. With battery boost to get back up to linespeed and on gradients, I would guess that 2 x 100kW engines running on HVO biodiesel would be plenty for a 3-car tri-mode class 170 replacement. That size engine fits under the bonnet of a family car.

Then add OHLE recharging at your leisure. It would only need simple overhead conductor bars at major stations where all trains stop anyway, with SFCs fed from local 33kV electricity supplies. Add battery reinforcment if the local grid were not able to handle the recharging loads.

With OHLE fed from the ECML at Newark Castle and Retford Low Level, I'd expect that SFC recharging at Lincoln, Sleaford and Grimsby stations would probably be enough for the whole of the regional network in the East Midlands.
 

duffield

Established Member
Joined
31 Jul 2013
Messages
3,302
Location
East Midlands
Possibly a silly question, but why is the range of BEMUs so much less than for an electric car, which can already do several hundred miles when fully charged? I thought that rail vehicles were much more efficient because of the lower rolling friction.
I'm not an expert, but I can think of a number of explanations:

  • Different power to weight considerations. A modest two coach BEMU might be carrying around 150 passengers when crush loaded
  • More rigorous safety and certification requirements
  • Smaller market, fewer companies, with less money devoted to R&D
  • All the above adding up to technology a generation or more behind electric cars
 

Zomboid

Established Member
Joined
2 Apr 2025
Messages
2,310
Location
Oxford
Electric car tech is what is pushing the train version along. But they're very different applications - in a train, they'll be subject to many more charge/discharge cycles per day than a typical car, as well as what's already been said.
 

Thirteen

Established Member
Joined
3 Oct 2021
Messages
1,904
Location
London
The upcoming Tri modes like the Class 897 and the Hitachi train for Grand Central are going to be the test bed for Battery powered trains as well as Irish Rail's BEMU Alstom trains.
 

Elecman

Established Member
Joined
31 Dec 2013
Messages
3,583
Location
Lancashire
Then add OHLE recharging at your leisure. It would only need simple overhead conductor bars at major stations where all trains stop anyway, with SFCs fed from local 33kV electricity supplies. Add battery reinforcment if the local grid were not able to handle the recharging loads.
it would be far easier to use a 3 phase 11kV supply as that is much more likely to be available rather than 33kV then via static Convertors to convert to 25kV single phase. You would need a fairly broad contact arrangement rather than just wire to avoid overheating the pantograph carbons/ contact wire as the train wouldn’t be moving.
 

Failed Unit

Established Member
Joined
26 Jan 2009
Messages
9,811
Location
Central Belt
It is also difficult to predict on the EMR network, Infill schemes could fill in some gaps,

Peterborough - Ely I could see (as part of a key freight route)
Doncaster -Cleethorpes could be possible (which of course would mean Barnetby - Cleehorpes is covered) as the may justify that key could getting done.

For the sake of charging maybe Lincoln - Newark, Grantham - Sleaford and Sleaford - Lincoln. (of which non of these can be justified alone, but Edinburgh to Dalmeny is getting done.

Freight could one day maybe drive Peterborough - Doncaster, but can’t see it yet
 

Nottingham59

Established Member
Joined
10 Dec 2019
Messages
3,350
Location
Nottingham
it would be far easier to use a 3 phase 11kV supply as that is much more likely to be available rather than 33kV then via static Convertors to convert to 25kV single phase.
There are lots of options, but luckily Grimsby and Lincoln have 132kV substations right next to the railway, and Sleaford has one just a few hundred metres away. All three places have plenty of 33kV circuits that could be tapped into.

You would need a fairly broad contact arrangement rather than just wire to avoid overheating the pantograph carbons/ contact wire as the train wouldn’t be moving.
Yes, thicker conductor bars and pantograph carbons may well be needed. I hope that someone is looking at what standards will be needed to cope with rapid batterification of the rail network.

EDIT: Given the Stadler EURO9000 takes 9MW (presumably when moving), I'd guess a standard GB pantograph and OHLE should be able to hande 5MW even when stationary. (Is that a fair guess?) 5MW is enough to recharge a 500kWh traction battery in 6 minutes, which strikes me as plenty fast enough for EMR regional BEMUs. But I might be wrong, how much power could a static BEMU draw on standard GB OHLE?


(Or they could just use the sort of robotic pantograph that battery trolleybuses use:
960px-Electric_bus_%282022%29.jpg

Image credit: Marc A. Hermann/MTA via Wikimedia
 
Last edited:

Halish Railway

Established Member
Joined
26 Apr 2017
Messages
2,177
Location
West Yorkshire / Birmingham
On a rather interesting side note, it states BEMUs replacing the Regional fleet from 2033.
Does it necessarily say it’s going to replace the entire fleet?

There’re quite a few routes where battery electric trains are suitable such as Lincoln to Matlock and Leicester, Nottingham to Crewe and maybe Nottingham to Worksop where discontinuous electrification would be a good option, but all other routes look unsuitable for anything but a diesel multiple unit, apart from Liverpool to Norwich which could see 810s displaced onto it once the MML to Nottingham and Sheffield is electrified and if new EMUs are ordered.
 

Zomboid

Established Member
Joined
2 Apr 2025
Messages
2,310
Location
Oxford
There's always the technology along the lines of the West Ealing battery train, that doesn't take a long dwell to get a decent amount of charge into the train.
I don't know a huge amount about the EMT network, but that kind of technology at a few stations (not only termini) ought to allow a battery train to cover fairly large distances without wires.
 

RealTrains07

Established Member
Joined
28 Feb 2019
Messages
1,905
On a rather interesting side note, it states BEMUs replacing the Regional fleet from 2033.
Considering the refurbishment programme will be continuing into 2027. Thats not a long time between finishing the programme and then replacing the fleet if all regional trains are to go??

But then who knows with GBR taking over EMRs contract at some point in the near future things might change?
 

Nym

Established Member
Joined
2 Mar 2007
Messages
9,800
Location
Somewhere, not in London
One might also feel it apt to point out here for those comparing with battery electric cars...

Trains need to meet fire standards.
Cars do not.
 

Russel

Established Member
Joined
30 Jun 2022
Messages
5,571
Location
Lichfield
From following the 810 progress, an EMR BEMU project doesn't fill me with confidence.
 

duffield

Established Member
Joined
31 Jul 2013
Messages
3,302
Location
East Midlands
Considering the refurbishment programme will be continuing into 2027. Thats not a long time between finishing the programme and then replacing the fleet if all regional trains are to go??

But then who knows with GBR taking over EMRs contract at some point in the near future things might change?
The key word in "will see BEMUs introduced from 2033" is "from". No end date or timescale is given! So the replacement programme should start in 2033 but might not be actually completed until - say - 2043 - which would give at least some of the most recently refurbished units 15+ years service after their refurb.
 

dosxuk

Established Member
Joined
2 Jan 2011
Messages
2,443
Liverpool to Norwich which could see 810s displaced onto it once the MML to Nottingham and Sheffield is electrified and if new EMUs are ordered
Not going to happen - for the same reasons the 222's aren't (and never were) going to be cascaded down to that route.
 

Stephen42

Member
Joined
6 Aug 2020
Messages
810
Location
London
The key word in "will see BEMUs introduced from 2033" is "from". No end date or timescale is given! So the replacement programme should start in 2033 but might not be actually completed until - say - 2043 - which would give at least some of the most recently refurbished units 15+ years service after their refurb.
The estimated completion date for the "fleet strategy" item is 2035, though I wouldn't read too much into that. Documents like this are often wildly ambitious, with scope and dates changing significantly before any implementation.

2033 seems a date where the 158s would be considered end of life and it's unlikely they'd be replaced with diesels without any battery or electrical capability. With those timelines EMR can wait to see how the trains from the Northern procurement perform and latest battery advancements before deciding whether to go with BEMUs or a trimode mix to reduce emissions without having to rely solely on the battery off the wires. The extent of the wires in 2033 is probably not confirmed (or maybe even known) yet either.
 

Russel

Established Member
Joined
30 Jun 2022
Messages
5,571
Location
Lichfield
The estimated completion date for the "fleet strategy" item is 2035, though I wouldn't read too much into that. Documents like this are often wildly ambitious, with scope and dates changing significantly before any implementation.

2033 seems a date where the 158s would be considered end of life and it's unlikely they'd be replaced with diesels without any battery or electrical capability. With those timelines EMR can wait to see how the trains from the Northern procurement perform and latest battery advancements before deciding whether to go with BEMUs or a trimode mix to reduce emissions without having to rely solely on the battery off the wires. The extent of the wires in 2033 is probably not confirmed (or maybe even known) yet either.

2033 Is only 8 years away, to get a new fleet into service by then, if we look at how the recent fleet introductions have gone, SWR 710s, LNWR 730s, ERM 810s, the order would have to be placed rather quickly.
 

QSK19

Member
Joined
29 Dec 2020
Messages
1,149
Location
Leicestershire
Does it necessarily say it’s going to replace the entire fleet?

There’re quite a few routes where battery electric trains are suitable such as Lincoln to Matlock and Leicester, Nottingham to Crewe and maybe Nottingham to Worksop where discontinuous electrification would be a good option, but all other routes look unsuitable for anything but a diesel multiple unit, apart from Liverpool to Norwich which could see 810s displaced onto it once the MML to Nottingham and Sheffield is electrified and if new EMUs are ordered.
I would have thought 158s - the 170s have plenty of life left in them.

Having said that, three things spring to mind.
- Firstly, given the £650m figure includes the £400m outlay for the 810s, would £250m cover replacing all the 158s and 170s?
- Secondly, the document puts heavy emphasis on getting rid of diesel trains, so that presumably means all of them?
- Thirdly, the ROI for allocating new build stock to the Regional operation would presumably be practically non-existent? Prior to seeing this, I’d have assumed that the 170 replacements would be 19x once Northern and/or WMR have moved onto other trains.

== Doublepost prevention - post automatically merged: ==

Considering the refurbishment programme will be continuing into 2027. Thats not a long time between finishing the programme and then replacing the fleet if all regional trains are to go??

But then who knows with GBR taking over EMRs contract at some point in the near future things might change?
See above for my thoughts. But as you say, who is to know once GBR is up and running.
 
Last edited:

Energy

Established Member
Joined
29 Dec 2018
Messages
5,135
- Thirdly, the ROI for allocating new build stock to the Regional operation would presumably be practically non-existent? Prior to seeing this, I’d have assumed that the 170 replacements would be 19x once Northern and/or WMR have moved onto other trains.
This comment here (thanks @bunnahabhain ) has the revenue breakdown as:
  • 80% Intercity & Connect
  • 5% Regional
  • 15% Liverpool - Norwich
So the ROI on regional is almost certainly terrible, but BEMUs on Liverpool - Norwich should be financially possible.

Any BEMU order for this route is going to be small (e.g. 26 x 3 car) so ordering from the same framework as Northern would save money and allow for more fleet flexibility should the route change operator.
 