Noticed masts up today at the new Hairmyers Station and towards the Glasgow Southern Orbital overbridge.
Good news and nice steady progress.Noticed masts up today at the new Hairmyers Station and towards the Glasgow Southern Orbital overbridge.
| |
I think those funny looking arm ends are just normal components that have been strapped up with cable ties to keep them out of the way until the catenary wire is installed.Great set of pics and as a former long-time user of this line, it’s remarkable to see the changes. As to the strange OHL “hardware” around Thorntonhall, not my field of expertise, but I don’t recall ever seeing anything like those. They may be “bespoke” for this particular situation.
I think those funny looking arm ends are just normal components that have been strapped up with cable ties to keep them out of the way until the catenary wire is installed.
The "double arm" arrangement for the low clearances at Thorntonhall is for very low clearances.Exactly this.
The part of the arm that the contact wire is fixed to is currently secured up out of the way to prevent any damage to them. The doubled up arms either side of the bridge at Thorntonhall are possibly in place to provide extra rigidity to the wires for under the bridge to maintain clearances.
Quoting just the important sections as the document is quite long:
1. The purpose of this report is to inform Members about the Clarkston Active Travel Bridge and to seek approval to directly appoint Network Rail to design a new active travel bridge across the railway at Clarkston adjacent to the existing B767 road bridge and install the Active Travel Bridge on site.
3. The department is currently leading the development of the Clarkston to Muirend Active Corridor funded via the Sustrans Places for Everyone programme. This project aims to improve active travel infrastructure on the B767, which is identified and approved by Council as Strategic Cycle Corridor 3 in Local Development Plan 2.
4. A key constraint is the existing crossings of the railway at Clarkston. The B767 road bridge has a substandard footway that is too narrow to accommodate separated cycleway, while the nearby footbridge is unsuitable for cycle traffic due to its limited width and indirect route. A feasibility study conducted in 2021 by AECOM concluded that these constraints could be overcome by constructing a new foot/cycle bridge adjacent to the current road bridge.
5. The Council has worked with Network Rail to prepare a ‘Development Services Agreement’, which would see Network Rail lead the project. Funding has been awarded via Transport Scotland’s Active Travel Transformation Fund to support design activity.
6. The report is seeking Cabinet approval for an exemption to standard procurement procedures to allow East Renfrewshire Council to directly award the contract to Network Rail with an estimated cost of £193,500 to carry out a full design package for a new walking, wheeling and cycling bridge across the railway at Clarkston adjacent to the existing B767 road bridge. This will also create a safe link between the Goods Yards car park and the town centre.
7. The project justification to proceed with the direct award is as follows: a. Delivery of the detailed design activity by the Council would depend on obtaining access to the railway to conduct topographical and ground investigation surveys. Network Rail’s approval of any work carried out on-site by a third party (and the signing of an ‘asset protection’ agreement) is a mandatory and lengthy process. This would present a risk that the proposed project would not be achieved within the timeframe of the railway electrification project, leading to future construction constraints, negative effects on the local community and railway users, and possible inability to achieve a crossing in the near future. b. Network Rail electrification of the Glasgow to East Kilbride railway line is a live project and there is a risk that the design process would not take account of the new pedestrian and cycle bridge design. An agreement with Network Rail would allow seamless working between our project and Network Rail and reduce any delays or negative effects. c. Network Rail is required to improve station accessibility and access as a part of their project on the railway, this will include a new footbridge being installed, and a new access from platform two from its northern end into the Clarkston town centre carpark. The agreement between the Council and Network Rail will allow a more appealing and accessible step-free access to the station platform two and stepped access to platform one.
8. It is considered that the criteria for a Regulation 33 exemption and standing order 23 exemption are therefore met for the following reasons: a. The design and construction of the proposed foot/cycle bridge must integrate with the current electrification project by Network Rail, which has already commenced on site from both a technical and timescale perspective. The bridge must be designed to fit with and be completed prior to Network Rail works. b. The key sections of the new bridge would be constructed during closure of the railway for the electrification works in Spring 2025 and so the design and all preliminary tasks would require to be completed by this date to avoid further closure of the railway and to avoid difficulties in providing improved accessible access to the station platforms.
9. The contract award to Network Rail to carry out the design package for the bridge is £193,500.
10. Full funding (£240,000) has been awarded by Transport Scotland via the Active Travel Transformation Fund (ATTF), to progress the concept and detailed designs for this new crossing. The ATTF award includes allowance for Council officer time to oversee this work and contingencies. There is no additional financial burden on the Council to progress this design work.
They’ve left that a bit late, Network Rail’s planning will have been well advanced by then. The council should have engaged at the outset to replace the 150 year old, dog leg bridge which is unsuitable for existing traffic never mind the active travel concept. They have history, having bickered over replacing the metal footbridge a number of years ago. I suspect they were hoping someone else would pay for it.I've found a 28 March 2024 East Renfrewshire council document detailing a possible active travel bridge crossing parallel to the existing B767/Stamperland Crescent bridge. It also confirms that the new entrance to Clarkston station will be from the north end of Platform 2, connecting to the car park, as most of us expected. Notably it also mentions a possible new stepped access to the westbound platform 1.
Great stuff.First masts have sprouted between Haimyres and East Kilbride,.
Great update as always. Question: is the loop being extended at the EK end as well? I was of the impression that it was only being extended at the Hairmyres end.East Kilbride To New Hairmyres Station Friday 29/11/2024 Piles Masts & Groundworks Update. Station Office base progress is well advanced and Services Conduits can be seen popping up through the floor. Give a feel of shape and size. Next Looking back from Strathfillan Rd, OB EKE/015A1 towards EK Station. Piles all seem to be in situ. Other side of bridge towards Kirktonholme Rd OB no masts bar 1 at the very end but some evidence of some piles and possibly all of them. Must apologise for the quality of the photos in this area from the day. Kirktonholme OB EK side has all the piles in with 3 masts up. At the other side of the bridge looking over the end of the Loop all piles are in and 8 masts fitted.
Next stop was the footbridge which runs between Eaglesham Rd and Tennant Ave. This is where the loop will be extended from to past the new Hairmyres Station end. There are and will be much ground works in the area. There are plenty of piles already in and I have no doubt there will be more to be installed. No masts fitted on the Hairmyres side but the Queensway side has a few installed close to The Queensway. So a lot of work completed before the 16 week Blockade.
It is only the Hairmyres end. The existing end ends just between Kirktonholme OB and the Queenaway so goes from there to the other side of the New Hairmyres StationGreat update as always. Question: is the loop being extended at the EK end as well? I was of the impression that it was only being extended at the Hairmyres end.
Just had another look at Picture 6, I’m with you now.It is only the Hairmyres end. The existing end ends just between Kirktonholme OB and the Queenaway so goes from there to the other side of the New Hairmyres Station
Great update thank you.It is only the Hairmyres end. The existing end ends just between Kirktonholme OB and the Queenaway so goes from there to the other side of the New Hairmyres Station
Parking suspension on Station Road 24/01 - 07/02 same reason as aboveTemporary road restriction – The Paddock, Glenville Terrace & Westerton Avenue, Busby
A Temporary Restriction Notice has been raised authorising the prohibition of parking on a section of The Paddock, Glenville Terrace & Westerton Avenue, Busby, in order to facilitate the safe operation of Network Rail Bridge works on or near the road.
The restriction will be in effect from Thursday 23rd January to Monday 3rd March 2025.
Temporary road restriction – Station Road, Busby
A Temporary Restriction Notice has been raised authorising the prohibition of parking on Station Road, Busby, in order to facilitate the safe operation of Network Rail Bridge works on or near the road.
The restriction will be in effect from Friday 24th January to Friday 7th February 2025.
One thing of note from the images is that the plans for lift access at this station appear to have been dropped.2024/0617/PAR Demolition of existing footbridge and installation of new footbridge (prior approval)
Clarkston Railway Station 35 Busby Road Clarkston Glasgow East Renfrewshire G76 7BN
Is it possible it's just not drawn accurately or has the work genuinely been descoped?New planning application submitted for the new bridge at Clarkston https://ercbuildingstandards.eastre...ils.do?activeTab=summary&keyVal=SODOQQGP08600
One thing of note from the images is that the plans for lift access at this station appear to have been dropped.
The new Hairmyres station is set to open in May 2025, coinciding with the completion of the 16-week works.