• Our new ticketing site is now live! Using either this or the original site (both powered by TrainSplit) helps support the running of the forum with every ticket purchase! Find out more and ask any questions/give us feedback in this thread!

East-West Rail (EWR): Consultation updates [not speculation]

Status
Not open for further replies.

12LDA28C

Established Member
Joined
14 Oct 2022
Messages
5,058
8 extra, (4 EWR each way), so 12 per hour with Chiltern Marylebone services?

(But maybe this isn't really a current construction progress matter, as it’s part of the new consultation for the future Bedford and Cambridge services that has its own thread.)

4 EWR trains each way every hour? That frequency of service is many years away yet, if it ever happens.
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

eastdyke

Established Member
Joined
25 Jan 2010
Messages
2,058
Location
East Midlands
I assume that the Written statement to Parliament today by Louise Haigh, in tandem with the Consultation will be a [very]
short summary of some of the main objectives.
As such I will read that first!

I note [my bold]:
By 2050, East West Rail is set to boost the Oxford-Cambridge regional economy by £6.7 billion every year.
 

ABB125

Established Member
Joined
23 Jul 2016
Messages
4,345
Location
University of Birmingham
I'm currently reading though the various documents in order, so apologies if this is mentioned elsewhere.
The consultation brochure states that two westbound passing loops are planned between Bletchley and Oxford. But no eastbound loops?
This seems a bit odd - surely there would need to be at least one eastbound passing loop as well? Or is the plan for freights etc to be looped somewhere adjacent to the WCML between Bletchley and Milton Keynes, before heading north? If so, why not do the same where EWR joins the line towards Oxford?
Also, 2 passing loops seems like a lot, when a less than hourly freight service is expected...
 

swt_passenger

Veteran Member
Joined
7 Apr 2010
Messages
34,294
I'm currently reading though the various documents in order, so apologies if this is mentioned elsewhere.
The consultation brochure states that two westbound passing loops are planned between Bletchley and Oxford. But no eastbound loops?
This seems a bit odd - surely there would need to be at least one eastbound passing loop as well? Or is the plan for freights etc to be looped somewhere adjacent to the WCML between Bletchley and Milton Keynes, before heading north? If so, why not do the same where EWR joins the line towards Oxford?
Also, 2 passing loops seems like a lot, when a less than hourly freight service is expected...
There already is one completed eastbound passing loop on EWR, just after the HS2 crossing.
 

Magdalia

Established Member
Joined
1 Jan 2022
Messages
7,400
Location
The Fens
I assume that the Written statement to Parliament today by Louise Haigh, in tandem with the Consultation will be a [very]
short summary of some of the main objectives.
As such I will read that first!
The penultimate paragraph of the statement says something that I've not found in the consultation documents:

The Department for Transport will also be issuing safeguarding directions for East West Rail today to protect land from conflicting development. I am placing a copy of the safeguarding directions in the Libraries of both Houses.
 

eastdyke

Established Member
Joined
25 Jan 2010
Messages
2,058
Location
East Midlands
The penultimate paragraph of the statement says something that I've not found in the consultation documents:
The Department for Transport will also be issuing safeguarding directions for East West Rail today to protect land from conflicting development. I am placing a copy of the safeguarding directions in the Libraries of both Houses.
No consultation needed on that!
It does of course impose obligations and cost upon The Authorities along the safeguarded route.
 

12LDA28C

Established Member
Joined
14 Oct 2022
Messages
5,058
I'm currently reading though the various documents in order, so apologies if this is mentioned elsewhere.
The consultation brochure states that two westbound passing loops are planned between Bletchley and Oxford. But no eastbound loops?
This seems a bit odd - surely there would need to be at least one eastbound passing loop as well? Or is the plan for freights etc to be looped somewhere adjacent to the WCML between Bletchley and Milton Keynes, before heading north? If so, why not do the same where EWR joins the line towards Oxford?
Also, 2 passing loops seems like a lot, when a less than hourly freight service is expected...

The loops at Claydon are bi-directional, as are the loops at Bicester so in actual fact there are already four loops along the route which can be used by both eastbound and westbound trains.

== Doublepost prevention - post automatically merged: ==

There already is one completed eastbound passing loop on EWR, just after the HS2 crossing.

See above.
 

jfowkes

Established Member
Joined
20 Jul 2017
Messages
1,270
The consultation document proposes dualling the Newmarket line between Coldhams Lane Junction and Cherry Hinton LC to act as a turnback siding, and proposes rebuilding the two footbridges over that section:
We are planning to reconstruct two footbridges at Coldham’s Common and The Tins footpath to allow for electrification of the railway and the addition of a second track.

Two things I note:
  • Neither the proposal nor the technical report mention the foot/cyclepath underpass at the far west of this section, which as far as I can tell from google maps would also need a rebuild. This is a very well used path and the narrow underpass is a chokepoint on it. Dualling the line would be an excellent opportunity to improve this path. I will be bringing this up at a consultation meeting - hopefully this omission is just an oversight by EWR.
  • It's not entirely clear to me why they need to go all the way to Cherry Hinton just for a turnback siding?
 

Magdalia

Established Member
Joined
1 Jan 2022
Messages
7,400
Location
The Fens
The consultation document proposes dualling the Newmarket line between Coldhams Lane Junction and Cherry Hinton LC to act as a turnback siding, and proposes rebuilding the two footbridges over that section:


Two things I note:
  • Neither the proposal nor the technical report mention the foot/cyclepath underpass at the far west of this section, which as far as I can tell from google maps would also need a rebuild. This is a very well used path and the narrow underpass is a chokepoint on it. Dualling the line would be an excellent opportunity to improve this path. I will be bringing this up at a consultation meeting - hopefully this omission is just an oversight by EWR.
  • It's not entirely clear to me why they need to go all the way to Cherry Hinton just for a turnback siding?
Have you read section 13.4.1 of the Technical Report?

I'm presuming that the underpass (now part of the Chisholm Trail) is covered as part of this:

Realignment of the existing track at several locations to accommodate the new parallel track within the same track formation. Remedial and extension works to the existing track formation would be required to accommodate the additional tracks.

And this in the same section may be a clue about Cherry Hinton:

EWR Co has identified the potential for a new station to the east of Cambridge on the line to Newmarket, which would enable services to turn around and would also provide additional connectivity for this part of Cambridge. A station at Cambridge East is not within the current scope of EWR, but it is recognised this could deliver benefits including supporting wider growth and opportunities for local people in this area of Cambridge. Third-party funding would be required to take forward a scheme in this area.
 

ABB125

Established Member
Joined
23 Jul 2016
Messages
4,345
Location
University of Birmingham
Something else I've noticed - there seem to be an awfully large number of proposed power line diversions throughout the scheme, including existing sections and Oxford-Bletchley (which is currently being rebuilt has now finished being rebuilt). These diversions are presumably due to proposed electrification? Which would imply full electrification across the entire line.
Alternatively, if these diversions are not due to electrification, what are they for? For example, the 4 high-voltage transmission lines heading north from East Claydon substation (3x132kV, 1x400kV) are all listed as being proposed for diversion. Yet they weren't diverted for the current rebuilding works, so the only reasonable explanation is electrical clearances if the line is electrified.
However, have diversions of every electricity grid power line along an electrification scheme been required previously, such as the MML? If not, why are they required for EWR? Are they just being overly pessimistic?
Taking the 400kV transmission line north of East Claydon, there is a pylon immediately south of EWR (which, remember, has just been rebuilt and didn't need diversion for that). Therefore, the wires will be at their highest point; there is a huge amount of vertical clearance, compared to the (newly-constructed) bridge next to it (as shown here).

Transmission line diversions are not cheap. Is there an element of gold-plating going on here?
 
Last edited:
Joined
26 Aug 2022
Messages
28
Location
Buckingham
Something else I've noticed - there seem to be an awfully large number of proposed power line diversions throughout the scheme, including existing sections and Oxford-Bletchley (which is currently being rebuilt). These diversions are presumably due to proposed electrification? Which would imply full electrification across the entire line.
Alternatively, if these diversions are not due to electrification, what are they for? For example, the 4 high-voltage transmission lines heading north from East Claydon substation (3x132kV, 1x400kV) are all listed as being proposed for diversion. Yet they weren't diverted for the current rebuilding works, so the only reasonable explanation is electrical clearances if the line is electrified.
However, have diversions of every electricity grid power line along an electrification scheme been required previously, such as the MML? If not, why are they required for EWR? Are they just being overly pessimistic?
Taking the 400kV transmission line north of East Claydon, there is a pylon immediately south of EWR (which, remember, has just been rebuilt and didn't need diversion for that). Therefore, the wires will be at their highest point; there is a huge amount of vertical clearance, compared to the (newly-constructed) bridge next to it (as shown here).

Transmission line diversions are not cheap. Is there an element of gold-plating going on here?
The plan AIUI for Claydon is a complete rebuild/resiting of the current 1960s substation. As part of that there are some planned OHL diversions to connect to the new substation site. There's some local info here
 

12LDA28C

Established Member
Joined
14 Oct 2022
Messages
5,058
Something else I've noticed - there seem to be an awfully large number of proposed power line diversions throughout the scheme, including existing sections and Oxford-Bletchley (which is currently being rebuilt). These diversions are presumably due to proposed electrification? Which would imply full electrification across the entire line.
Alternatively, if these diversions are not due to electrification, what are they for? For example, the 4 high-voltage transmission lines heading north from East Claydon substation (3x132kV, 1x400kV) are all listed as being proposed for diversion. Yet they weren't diverted for the current rebuilding works, so the only reasonable explanation is electrical clearances if the line is electrified.

Oxford - Bletchley is complete and has been handed over to Network Rail.
 

Starmill

Veteran Member
Joined
18 May 2012
Messages
27,298
Location
Bolton
I'm sure there were consultations on plenty of infrastructure projects that didn't materialise within their envisaged timescale.
No project of any kind can ever be 100% certain of timescales though, can it? So your argument is what? That the level crossing doesn't need to be considered at all, because a delay is a possibility? That would apply to any enhancement you could mention.

The scale of the works isn't exactly ground-breaking. Can you comment on why six years isn't adequate time to close a level crossing?
 

Andyjs247

Member
Joined
1 Jan 2011
Messages
734
Location
North Oxfordshire
The loops at Claydon are bi-directional, as are the loops at Bicester so in actual fact there are already four loops along the route which can be used by both eastbound and westbound trains.

== Doublepost prevention - post automatically merged: ==



See above.
There is one loop at Claydon on the Down side and a loop at Bicester on the up side. So only 2 loops which could be used in either direction if needed. It would require crossing moves if they were to be used in the opposite direction. The bi-directional capability of both loops will be more useful for reversals - to access the MOD site at Bicester or at Claydon to access the future HS2 infrastructure depot or perhaps towards Calvert and Aylesbury.
 

The Planner

Veteran Member
Joined
15 Apr 2008
Messages
19,710
The loops at Claydon are bi-directional, as are the loops at Bicester so in actual fact there are already four loops along the route which can be used by both eastbound and westbound trains.

== Doublepost prevention - post automatically merged: ==



See above.
There was a planned loop at Newton Longville that got canned in the Bletchley direction. Got left as passive provision.
 

mr_jrt

Established Member
Joined
30 May 2011
Messages
1,575
Location
Brighton
I can't recall offhand - are any loops planned on the Bletchley to Bedford section? I do however note some are planned near Cambourne, if I read the literature correctly.
 

GRALISTAIR

Established Member
Joined
11 Apr 2012
Messages
10,520
Location
Preston Lancs
The plan AIUI for Claydon is a complete rebuild/resiting of the current 1960s substation. As part of that there are some planned OHL diversions to connect to the new substation site. There's some local info here
Wow - thanks for that. I did not realise there were plans in the works for this. East-West rail will factor in of course and I assume HS2?
 

Magdalia

Established Member
Joined
1 Jan 2022
Messages
7,400
Location
The Fens
I can't recall offhand - are any loops planned on the Bletchley to Bedford section? I do however note some are planned near Cambourne, if I read the literature correctly.
Yes, see section 7.9.5 in the Technical Report:

Six options have been identified for the location of passing loops which would be constructed in the Ridgmont and Stewartby area as shown in Figure 63. There are three westbound loop options and three eastbound options, with only one loop required in each direction.
I do however note some are planned near Cambourne, if I read the literature correctly.
Yes see section 11.2.2 in the Technical Report.

A track maintenance access point directly to the east of the St Neots Road overbridge would be accessed from St Neots Road to the north of the railway, and St Neots Road/Cambourne Road roundabout to the south. 250m further east, passing loops both sides of the railway would be constructed approximately 1.3km (0.8 miles) in length to allow faster passenger trains to overtake slower trains.

Passing loops are also proposed at Hauxton junction in section 12.3.2.2 of the Technical Report.

During design development, the operational analysis for the railway identified a requirement for passing loops to be constructed at certain locations along the route. Hauxton Junction was one of the identified locations for these loops, therefore, the options were revised to include provision for this.
 

12LDA28C

Established Member
Joined
14 Oct 2022
Messages
5,058
There is one loop at Claydon on the Down side and a loop at Bicester on the up side. So only 2 loops which could be used in either direction if needed. It would require crossing moves if they were to be used in the opposite direction. The bi-directional capability of both loops will be more useful for reversals - to access the MOD site at Bicester or at Claydon to access the future HS2 infrastructure depot or perhaps towards Calvert and Aylesbury.

As stated above, there are two loops at Claydon and two at Bicester. So, four loops.
 

12LDA28C

Established Member
Joined
14 Oct 2022
Messages
5,058
There is not capacity to loop two trains in opposite directions at the same time at either location.

Why not? Surely the signalling allows it? As long as neither train is overlength for the loop of course.
 

TheHSRailFan

Member
Joined
16 Jun 2018
Messages
297
Finished reading the document an hour ago.
I read both this and the 2021 consultation document and this one feels more refined (as expected) compared to the document in 2021. It does seem like they are willing to get their hands on the Marston Vale as soon as possible, getting straight to the point with many things. I really don't get however why they really split the Marston Vale part into 2 when the "Consolidated stations" option feels like the best choice. Also, EWR Ltd's favouring of discontinuous electrification than full electrification is a weird choice, even with their "reasons".
 