May I enquire where this information has come from because as far as I am aware TfGM have only updated / informed the public on July 24 as follows:-
”Land movement affecting the Metrolink network near Derker has slowed, enabling detailed ground investigations and temporary repair works to get underway.
To get trams running again, a small section of track has to be moved back into its original position. The overhead line poles also need to be repaired. Due to the complexity of the work, it is expected to take up to five weeks to complete, and we are looking to accelerate repairs.
The detailed ground investigations will establish whether further work to strengthen foundations beneath the track will be needed at a later date”
In this timescale, re-opening of the tram line should (in the worst case), be before the end of August.
No mention there of a closure immediately following the bridge works on the M62 / heavy rail Rochdale - Mcr Vic line.
I’m not doubting your information as it sounds like you may have some insider knowledge.
It will be massively disappointing if the tram line only temporarily re-opens for just a fortnight. It’s been areal PITA for the last 5 weeks.