The Swansea District Line appears to have been closed for several weeks now. I heard somewhere that there's an issue with a tunnel. Does anyone know what the problem is and what's planned to resolve it? Trains are diverted via Landore, involving 2 locos on the Trostre trains due to the double reversal needed at Llandeilo Junction.
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

anthony263

Established Member
Joined
19 Aug 2008
Messages
6,892
Location
South Wales
The Swansea District Line appears to have been closed for several weeks now. I heard somewhere that there's an issue with a tunnel. Does anyone know what the problem is and what's planned to resolve it? Trains are diverted via Landore, involving 2 locos on the Trostre trains due to the double reversal needed at Llandeilo Junction.
It's llangyfelach tunnel that's the problem network rail supposed to be repairing the structure as there's been so e movement or something
 

38Cto15E

Member
Joined
1 Nov 2009
Messages
1,116
Location
15E
I went through it a few weeks ago (11th April) on the lunchtime Fishguard Harbour to Cardiff train.
 

Richard Robson

New Member
Joined
26 Apr 2019
Messages
1
It was closed sometime before 12th June. We were on the Fishguard Harbour to Cardiff and was told by the guard it was going via the Swansea avaoider as there was a tunnel issue. So we got to do that instead. Hopefully it will be repaired and we can go and do the District at some point in the not to distand future
 

Western 52

Established Member
Joined
19 Jun 2020
Messages
1,672
Location
Burry Port
The line remains closed this week with freight traffic still going via Landore. Oil trains are double headed and reduced to around 21 tanks, whilst Trostre trains are top and tailed. This must be extra cost of course, so you'd think getting the District Line open would be a priority. I've noticed the lines at the Briton Ferry end are now quite rusty.
 

John R

Established Member
Joined
1 Jul 2013
Messages
6,117
The line remains closed this week with freight traffic still going via Landore. Oil trains are double headed and reduced to around 21 tanks, whilst Trostre trains are top and tailed. This must be extra cost of course, so you'd think getting the District Line open would be a priority. I've noticed the lines at the Briton Ferry end are now quite rusty.
I’ve often wondered why the line has survived when such an obvious alternative exists, but I think I now have the answer!
 

D6975

Established Member
Joined
26 Nov 2009
Messages
3,052
Location
Bristol
The ability to turn HST power cars was another reason in the not so distant past.
 

The exile

Established Member
Joined
31 Mar 2010
Messages
9,436
Location
Somerset
Ignoramus question here, what is the difference between the district line and the Swansea avoider line?
Both lines in question are strictly speaking “Swansea avoiders”. One is the north side of the triangle at Landore; the other, much longer, links Briton Ferry to Llangennech on the Central Wales Line. The Landore variant is presumably more steeply graded.

== Doublepost prevention - post automatically merged: ==

The ability to turn HST power cars was another reason in the not so distant past.
Surely the Landore curve would have been used for that, rather than the District. Of course, various freight lines fed into the District Lines (Onllwyn, Cwmgwrach, Swansea Docks, so complete closure was not an option while they still had traffic.
 

D6975

Established Member
Joined
26 Nov 2009
Messages
3,052
Location
Bristol
Surely the Landore curve would have been used for that, rather than the District. Of course, various freight lines fed into the District Lines (Onllwyn, Cwmgwrach, Swansea Docks, so complete closure was not an option while they still had traffic.
We were talking about the Landore curve...
 

andythebrave

Member
Joined
8 Oct 2009
Messages
570
Location
England
Both lines in question are strictly speaking “Swansea avoiders”. One is the north side of the triangle at Landore; the other, much longer, links Briton Ferry to Llangennech on the Central Wales Line. The Landore variant is presumably more steeply graded.
Thank you.
 

anthony263

Established Member
Joined
19 Aug 2008
Messages
6,892
Location
South Wales
The Swansea District Line could become part of the Swansea metro Pontardulais to Swansea service
 

GW43125

Established Member
Joined
8 Dec 2014
Messages
2,310
Both lines in question are strictly speaking “Swansea avoiders”. One is the north side of the triangle at Landore; the other, much longer, links Briton Ferry to Llangennech on the Central Wales Line. The Landore variant is presumably more steeply graded.
If memory serves, I think it's a fairly stiff climb out the west end of Swansea towards Llanelli-I remember a single 153 trying its best, with limited success!
 

Western 52

Established Member
Joined
19 Jun 2020
Messages
1,672
Location
Burry Port
If memory serves, I think it's a fairly stiff climb out the west end of Swansea towards Llanelli-I remember a single 153 trying its best, with limited success!
Yes, it's a steep climb to Cockett Tunnel both ways. This limits freight loads.
 

Western 52

Established Member
Joined
19 Jun 2020
Messages
1,672
Location
Burry Port
The line remains closed, but I noticed yesterday 2 August that the up line at the Morlais Junction end shows signs of use. Works movements maybe, anyone have any update on what's happening?
 

sleepinglion

Member
Joined
2 Aug 2024
Messages
9
Location
Wales
Can only speak as a local but bave seen work crews of around 8 people parked up and either starting or finishing work above the cutting at the Morriston end of the tunnel at around 9pm a couple night this week, so can only assume they are working hard there.
We all had letters a month or two before the closure warning of heavy work going on in the tunnel there for a few nights but that finished well over a month before the tunnel closed, so unsure it's connected.

== Doublepost prevention - post automatically merged: ==

Yes, it's a steep climb to Cockett Tunnel both ways. This limits freight loads.
Might be wrong but I believe it's 1 in 52 one side and 1 in 53 the other.
 
Last edited:

Western 52

Established Member
Joined
19 Jun 2020
Messages
1,672
Location
Burry Port
That will be good news for freight operators. Current double heading and top and tail working must be expensive.
 

John R

Established Member
Joined
1 Jul 2013
Messages
6,117
That will be good news for freight operators. Current double heading and top and tail working must be expensive.
Wouldn’t Network Rail pick up the additional costs, if the asset they are contracted to make available isn’t?
 

Western 52

Established Member
Joined
19 Jun 2020
Messages
1,672
Location
Burry Port
Looks like testing trains running on the line today, and according to RTT tomorrow's 6B13 Robeston to Westerleigh oil is going that way.


 