Ex LNER (and Grand Central) Mark 4 sets for TfW

Status
Not open for further replies.

Diedinium

Member
Joined
31 Oct 2021
Messages
185
Location
Shropshire
Very long term absentees 67017 and 67010 should be heading back to TfW in the Next day or two after testing. 010 is planned to be on HD06 whilst it undergoes an exam and 017 should head to Canton to act as recovery loco. In the meantime, 67023 will be hired from Colas and used as the recovery loco and based in the Shrewsbury area to cover both ends of the network.

Set wise, HD05 is now back from Crewe ETD after tyre turning and is undergoing final testing and finishing before heading back out as the final 5 car. HD06 is now in for its heavy exam and should be the final set to have its SV mods with improved ventilation and air con in the kitchen vehicle. As 06 and 05 are now both on exam at Crewe, until 05 is released, HD02 is now temporarily stored at Holyhead.

As HD02 is now stored, 1V91 from Holyhead will be a unit tomorrow with 67014+HD01 planned to pick up the diagram from the 10:52 Cardiff to Manchester
Edit- it will now work the 08:49 from Cardiff replacing 67020+HD04 which failed earlier with low power caused by a faulty traction motor.
Ah I saw 67023 based in the Coleham sidings when driving by it today and wondered what that was doing there, nice to see it explained.
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

mikestone1952

Member
Joined
12 Feb 2011
Messages
299
According to RTT 67015 finished at Holyhead on Friday night, but following this mornings failure appeared to have made its way to Crewe to take over 1W57 - despite which journeycheck is apologising for 1W65 having no first!
 

sd0733

Established Member
Joined
7 Nov 2012
Messages
5,186
According to RTT 67015 finished at Holyhead on Friday night, but following this mornings failure appeared to have made its way to Crewe to take over 1W57 - despite which journeycheck is apologising for 1W65 having no first!
67015 ran light engine back to Crewe on Saturday morning, leaving HD02 in Holyhead. It's now gone onto HD04 replacing 67020 which is the one that had the failure.

== Doublepost prevention - post automatically merged: ==

‐----‐--------------------------------------------------------
Posted 09/07

HD05 is due out on its test run tomorrow which will finally end the 5 car programme, as long as no issues are found it will then be available for service from Thursday (although could be a spare set as 3 will be available at Crewe)

67010 now at Canton will take 67022 to Crewe ETD tomorrow for repairs, 010 will then return light to Canton on Thursday morning.

67020 is now repaired and after a test run is now powering HD06 whilst it undergoes it's heavy exam at Crewe.
 
Last edited:

Lurcheroo

Established Member
Joined
21 Sep 2021
Messages
1,240
Location
Wales
67015 ran light engine back to Crewe on Saturday morning, leaving HD02 in Holyhead. It's now gone onto HD04 replacing 67020 which is the one that had the failure.

== Doublepost prevention - post automatically merged: ==

‐----‐--------------------------------------------------------
Posted 09/07

HD05 is due out on its test run tomorrow which will finally end the 5 car programme, as long as no issues are found it will then be available for service from Thursday (although could be a spare set as 3 will be available at Crewe)

67010 now at Canton will take 67022 to Crewe ETD tomorrow for repairs, 010 will then return light to Canton on Thursday morning.

67020 is now repaired and after a test run is now powering HD06 whilst it undergoes it's heavy exam at Crewe.
Awesome stuff! Is there a plan for the 5th diagram ?
 

sd0733

Established Member
Joined
7 Nov 2012
Messages
5,186
Awesome stuff! Is there a plan for the 5th diagram ?
Believe it's still planned for late August/Early September now but things change so much it's hard to keep up sometimes.

== Doublepost prevention - post automatically merged: ==

HD05 wasn't ready in time so is now planned out for a test run tomorrow. It is then planned to re-enter service in Friday replacing HD01 which will stop for exam.
 
Last edited:

Lurcheroo

Established Member
Joined
21 Sep 2021
Messages
1,240
Location
Wales
Believe it's still planned for late August/Early September now but things change so much it's hard to keep up sometimes.
Ahh ok, once it’s ready and in service, would be nice if they can get it covered sooner but we shall see
 

craigybagel

Established Member
Joined
25 Oct 2012
Messages
5,827
Most of the MU speed differentials were replaced with Passenger/Freight differentials between Shrewsbury and Craven Arms last week - meaning that MKIV operated services are no longer limited to 70mph through this section.

Sadly the 90MU/40 restriction over a small bridge just North of Craven Arms remains, as does a short section of 90MU/75 on the approach to Craven Arms from Onibury, but overall this should still save a few minutes on MKIV operated services.
 
Joined
21 Aug 2019
Messages
154
Location
Newport
Most of the MU speed differentials were replaced with Passenger/Freight differentials between Shrewsbury and Craven Arms last week - meaning that MKIV operated services are no longer limited to 70mph through this section.

Sadly the 90MU/40 restriction over a small bridge just North of Craven Arms remains, as does a short section of 90MU/75 on the approach to Craven Arms from Onibury, but overall this should still save a few minutes on MKIV operated services.
Great to hear. Are those remaining sections likely to ever get done?
 

craigybagel

Established Member
Joined
25 Oct 2012
Messages
5,827
Great to hear. Are those remaining sections likely to ever get done?
From what I've heard, the bridge needs a lot of work or maybe even complete replacement to allow higher speeds. No idea if there's any plans for that or not.

If the bridge doesn't get fixed, there's no point doing anything about the other section either, as the section before it is 75 for everything, and then it's uphill so a MKIV rake isn't likely to accelerate to a much higher speed before it needs to start braking for the 40 over the bridge. It looks like it's tied in with braking distances for the signals so Craven Arms, which are pretty tight.
 

SuperLuke2334

Established Member
Joined
23 Oct 2021
Messages
1,898
Location
Welsh Marches
Most of the MU speed differentials were replaced with Passenger/Freight differentials between Shrewsbury and Craven Arms last week - meaning that MKIV operated services are no longer limited to 70mph through this section.

Sadly the 90MU/40 restriction over a small bridge just North of Craven Arms remains, as does a short section of 90MU/75 on the approach to Craven Arms from Onibury, but overall this should still save a few minutes on MKIV operated services.
I did wonder why we were do quick on Saturday morning! That's excellent progress. Hopefully timekeeping is on the up!
 

BillStampy

Established Member
Joined
6 Jan 2024
Messages
1,598
Location
Llanharan
HD05 wasn't ready in time so is now planned out for a test run tomorrow. It is then planned to re-enter service in Friday replacing HD01 which will stop for exam.
Excellent, what 67 is on it and what diagram will it do when it returns on Friday? Going to try take a look at it as soon as possible.
 

sd0733

Established Member
Joined
7 Nov 2012
Messages
5,186
Excellent, what 67 is on it and what diagram will it do when it returns on Friday? Going to try take a look at it as soon as possible.
It's got 67012 on it. It more than likely will be put onto the 04:54 from Crewe diagram, they're normally kept 'captive' on that for a couple of days starting and finishing in Crewe but can't be 100% at this point.

== Doublepost prevention - post automatically merged: ==

HD05 completed its test and Is now back at Crewe, effectively ending the 5 car programme, it's planned out of Crewe as expected on the 04:54 tomorrow morning.

Tomorrow evening, the 17:14 Cardiff to Holyhead is a planned substitution to a unit, this will allow 67017+HD02 to re-enter service on Monday morning on the 05:30 from Holyhead.
 
Last edited:

BillStampy

Established Member
Joined
6 Jan 2024
Messages
1,598
Location
Llanharan
Certainly has been a long time coming! But we shall reap the rewards of it at least!
Indeed! Set reliability has certainly increased now and way less are being swapped off for issues. Same with the 67s, which do seem to be working for the most part well, especially with the return of two more 67s.
 

sd0733

Established Member
Joined
7 Nov 2012
Messages
5,186
Certainly has been a long time coming! But we shall reap the rewards of it at least!
It was around 14 weeks later than originally planned for the last set to enter service, some of that was caused by the condition of the TOs after several years out of use, others was different tasks/mods being added to the scope whilst sets were long term stopped.

== Doublepost prevention - post automatically merged: ==

Indeed! Set reliability has certainly increased now and way less are being swapped off for issues. Same with the 67s, which do seem to be working for the most part well, especially with the return of two more 67s.
The mods that have been undertaken certainly seem to be paying off. Availability is a far cry from where it once was, both loco and rakes. Timekeeping is also much much better recently especially since the speed limits were increased. Now the exams are pretty much caught up and better balanced too, there shouldn't be a need to store/exam sets in Holyhead anymore which will reduce swaps as there won't be a need to balance those sets in/out of diagrams.
 

Lurcheroo

Established Member
Joined
21 Sep 2021
Messages
1,240
Location
Wales
It was around 14 weeks later than originally planned for the last set to enter service, some of that was caused by the condition of the TOs after several years out of use, others was different tasks/mods being added to the scope whilst sets were long term stopped.
Oh that’s not so bad to be fair!

Indeed! Set reliability has certainly increased now and way less are being swapped off for issues. Same with the 67s, which do seem to be working for the most part well, especially with the return of two more 67s.

The mods that have been undertaken certainly seem to be paying off. Availability is a far cry from where it once was, both loco and rakes. Timekeeping is also much much better recently especially since the speed limits were increased. Now the exams are pretty much caught up and better balanced too, there shouldn't be a need to store/exam sets in Holyhead anymore which will reduce swaps as there won't be a need to balance those sets in/out of diagrams.
Well it’s certainly an improvement and hopefully the general public are noticing the better consistency.
 

Caaardiff

Established Member
Joined
9 Jun 2019
Messages
1,383
That's excellent news. With the 5 cars done, hopefully it'll mean good availability before the 5th diagram starts, alongside the increases in capacity of 197s on the Marches TFW are finally starting to see good progress.
 

sd0733

Established Member
Joined
7 Nov 2012
Messages
5,186
That's excellent news. With the 5 cars done, hopefully it'll mean good availability before the 5th diagram starts, alongside the increases in capacity of 197s on the Marches TFW are finally starting to see good progress.
Certainly looks as If everything is planned out, and spare rakes every day into next week with 6 sets available most days.
 

BillStampy

Established Member
Joined
6 Jan 2024
Messages
1,598
Location
Llanharan
Certainly looks as If everything is planned out, and spare rakes every day into next week with 6 sets available most days.
Brilliant! A lot better compared to the past and when they were introduced to Manchester originally (:s), hopefully we can get that 5th diagram in soon!

Any news regarding HD08, supposing Transport for Wales now turn to see what condition it's in, would be excellent.
 

craigybagel

Established Member
Joined
25 Oct 2012
Messages
5,827
Quite a nice sight on the depot at Crewe in the wee hours this morning - all 4 of the roads regularly used to stable the MKIVs had full rakes occupying them. It would have been nice if they were all facing the same way but you can't have everything!
 

SuperLuke2334

Established Member
Joined
23 Oct 2021
Messages
1,898
Location
Welsh Marches
Quite a nice sight on the depot at Crewe in the wee hours this morning - all 4 of the roads regularly used to stable the MKIVs had full rakes occupying them. It would have been nice if they were all facing the same way but you can't have everything!
Hopefully in the future they will be managed well enough to keep them the same way, like the Mk3 sets. It would make it a lot easier for passengers!
 

BillStampy

Established Member
Joined
6 Jan 2024
Messages
1,598
Location
Llanharan
Quite a nice sight on the depot at Crewe in the wee hours this morning - all 4 of the roads regularly used to stable the MKIVs had full rakes occupying them. It would have been nice if they were all facing the same way but you can't have everything!
Believe TfW prefer the locomotive in the shed at Manchester, in the future it could end up simply being made to be that way as much as possible. Not entirely sure, but that's what I heard before. Hopefully they will be though!
 

craigybagel

Established Member
Joined
25 Oct 2012
Messages
5,827
Hopefully in the future they will be managed well enough to keep them the same way, like the Mk3 sets. It would make it a lot easier for passengers!
Indeed. Work has been going on behind the scenes to make sure the ECS services booked to run via Warrington actually run that way the vast majority of the time, so sets should be getting turned less often - but at the moment even if the sets never turn there's still a mix until someone goes to the effort of getting the sets the wrong way round turned.
Believe TfW prefer the locomotive in the shed at Manchester, in the future it could end up simply being made to be that way as much as possible. Not entirely sure, but that's what I heard before. Hopefully they will be though!
Correct. I believe it makes it easier at Canton if the loco is at that end.
 

Bikeman78

Established Member
Joined
26 Apr 2018
Messages
6,181
Indeed. Work has been going on behind the scenes to make sure the ECS services booked to run via Warrington actually run that way the vast majority of the time, so sets should be getting turned less often - but at the moment even if the sets never turn there's still a mix until someone goes to the effort of getting the sets the wrong way round turned.
I don't see how that could work because one set runs via Eccles each morning and evening. So, if they are all the same way round during the day, one of them will be the other way round when it arrives at Crewe. It's then 50/50 which diagram it will work the next day. At the moment, it is further complicated by the fact that 5V33 runs via Eccles but both sets run from Manchester to Crewe via Wilmslow in the evening.
 

sd0733

Established Member
Joined
7 Nov 2012
Messages
5,186
I don't see how that could work because one set runs via Eccles each morning and evening. So, if they are all the same way round during the day, one of them will be the other way round when it arrives at Crewe. It's then 50/50 which diagram it will work the next day. At the moment, it is further complicated by the fact that 5V33 runs via Eccles but both sets run from Manchester to Crewe via Wilmslow in the evening.
There does lie some of the problem with keeping things the same way round as if the set which runs via Warrington in the evening is always sent back out on the via Warrington in the morning, it means the other set is stuck on the same Crewe-Crewe diagram for several days at a time.
There's also the diversions via Chester vice Nantwich or the Holyheads diverting via Crewe from time to time which ends up turning sets, also the first Cardiff to Manchester is semi-regularly booked via the East Usk chord, again turning it round.
It's certainly an aim to have things consistent but in practice is proving difficult.

== Doublepost prevention - post automatically merged: ==

Any news regarding HD08, supposing Transport for Wales now turn to see what condition it's in, would be exexcellent.
Now the 5 car programme is over, attention can turn to assessing that set. It won't be a quick process though so any return wouldn't be particularly imminent. It's heavily stripped so just putting back the missing bits is quite a long process.
 

craigybagel

Established Member
Joined
25 Oct 2012
Messages
5,827
I don't see how that could work because one set runs via Eccles each morning and evening. So, if they are all the same way round during the day, one of them will be the other way round when it arrives at Crewe. It's then 50/50 which diagram it will work the next day. At the moment, it is further complicated by the fact that 5V33 runs via Eccles but both sets run from Manchester to Crewe via Wilmslow in the evening.
It's booked to be the same set via Warrington both in the evening and the following morning, and in practice it needs to be; there isn't enough time to service the sets at Crewe if you swap them. The evening situation is just a temporary one, in the LTP it's meant to run both ways.
There does lie some of the problem with keeping things the same way round as if the set which runs via Warrington in the evening is always sent back out on the via Warrington in the morning, it means the other set is stuck on the same Crewe-Crewe diagram for several days at a time.
There's also the diversions via Chester vice Nantwich or the Holyheads diverting via Crewe from time to time which ends up turning sets, also the first Cardiff to Manchester is semi-regularly booked via the East Usk chord, again turning it round.
It's certainly an aim to have things consistent but in practice is proving difficult.

== Doublepost prevention - post automatically merged: ==
Does the East Usk move actually happen? I'd be surprised given the difficulties of changing ends there, unless they're double manning it.
 

SuperLuke2334

Established Member
Joined
23 Oct 2021
Messages
1,898
Location
Welsh Marches
There does lie some of the problem with keeping things the same way round as if the set which runs via Warrington in the evening is always sent back out on the via Warrington in the morning, it means the other set is stuck on the same Crewe-Crewe diagram for several days at a time.
There's also the diversions via Chester vice Nantwich or the Holyheads diverting via Crewe from time to time which ends up turning sets, also the first Cardiff to Manchester is semi-regularly booked via the East Usk chord, again turning it round.
It's certainly an aim to have things consistent but in practice is proving difficult.

== Doublepost prevention - post automatically merged: ==


Now the 5 car programme is over, attention can turn to assessing that set. It won't be a quick process though so any return wouldn't be particularly imminent. It's heavily stripped so just putting back the missing bits is quite a long process.
It's booked to be the same set via Warrington both in the evening and the following morning, and in practice it needs to be; there isn't enough time to service the sets at Crewe if you swap them. The evening situation is just a temporary one, in the LTP it's meant to run both ways.

Does the East Usk move actually happen? I'd be surprised given the difficulties of changing ends there, unless they're double manning it.