What is the current cost of building a new railway in the UK? I'm thinking about the total cost, not just the civil engineering. There's a number of references I can find. Are there any better sources?
- East West Rail Central Section options Central section capital cost estimate (14.08.2019) estimated £60m per route km in 2017.
- The cost of HS2 phase 2a is now suggested at £7bn for 59km over open countryside. That's £120m/route km.
- The HS2 civil engineering contract C1 to design and build the 3.4km Colne Valley Viaduct plus 15.8km of twin-bore 9m diamter Chiltern tunnel was awarded to ALIGN JV in 2017 for £965million. Even after inflation, that implies less than £50m/km to bore a single tunnel.
- HS2 Phase 2bWest was supposed to cost £17bn for the station and 15km tunnel in Manchester, plus (I think) 5km tunnel under Crewe and 35km of open line. Suggests tunnelled city line costs perhaps £500 per route km.
- £50m: Upgrading functional goods line to express passenger standards (e.g. Ditton Freight Line to Warrington Low-Level)
- £100m: 2-track 100mph railway on an old extant alignment (e.g. Warrington to Lymm)
- £100m: New unelectrified 2-track railway over open countryside (e.g. EWR Bedford-Cambridge)
- £120m: New Highspeed line across open country (e.g. HS2 phase 2a)
- £200m: New viaduct over open country (e.g. Colne Valley HS2)
- £200m: Cut and cover tunnel in countryside (e.g. HS2 green tunnels)
- £300m: Bored twin tunnel under open country
- £400m: Bored twin tunnel under city
- £50m: Tunnel Portal
£200m: New halt on mainline (2x260m platforms, like Winslow)£1000m: New station on High Speed Line (4x400m platforms plus through lines, like Airport HS)£2000m: 6 platform HS terminus, (e.g. HS Piccadilly)
- £20M: New halt on mainline (e.g. Camp Hill line)
- £400M: New station of High Speed Line (4x400m platforms plus through lines, like Airport HS)
- £1000M: 6 Platfrom HS terminus (e.g. PHS iccadilly)