Annetts key
Established Member
I would expect a speed restriction to be used until the engineers are happy that the embankment is stable and the new ballast formation is stable.
Yes they are the best.Great progress and puts the doomsters firmly in the long grass that the date would be achieved.
Nothing like a crisis to bring out the best in our industry.
Still plenty of 'liners booked to run via London on that date:Hope this is not speculation, and 4E91 (for example) is likely to run as planned on 9 June!
I'd have though a Tamper would be the first across.Surely the Network Rail test train will cross it first?
My mistake. You of course, are absolutely correct.I'd have though a Tamper would be the first across.
Well, a 66 on the ballast train might yet prove me wrong. But a test train won't actually need to check the bridge for a while as it being newly laid means it should all be in tolerance. However it may pay a visit quite quickly as Didcot-Oxford may well need a check soon enough.My mistake. You of course, are absolutely correct.
Yes it's incredibly impressive. I'd be interested to know the reaction when Peter Hendy gets the bill.Proves that "it" really can be done - "it" being engineering on a grand scale in response to an urgent need - if the situation demands it.
And there's the crux of it! The familiar triangle of delivery - Low Cost / Short time / High quality. Pick two for your project. Clearly cost is the one that was sacrificed here.Yes it's incredibly impressive. I'd be interested to know the reaction when Peter Hendy gets the bill.
Yes, it is great. But it reminds me of something I heard years ago from an experienced rail engineer, that the rail industry really likes responding to a crisis but is not so good at the 'boring' day to day stuff. Amid the great engineering we're seeing, let's not forget that this is ultimately responding to a long term failure. I will be very interested to read the report on the technical and managerial aspects of the failure.Great progress and puts the doomsters firmly in the long grass that the date would be achieved.
Nothing like a crisis to bring out the best in our industry.
Won't Network Rail be having to pay operators huge sums for paths they contracted to provide, but currently cannot ? And therefore strongly driven to provide paths again from the target date of 10 June, at almost any cost ? What worries me, is the diversion to Nuneham of a substantial part of Network Rail's limited budget, at the expense of lots of other no doubt highly desirable schemes.
And there's the crux of it! The familiar triangle of delivery - Low Cost / Short time / High quality. Pick two for your project. Clearly cost is the one that was sacrificed here.
There's also the access etc of course. As an emergency the stuff just gets done as there's huge pressure and urgency, but as a planned works this would take ages to agree and get consents for etc etc.
Would the job have been able to have been done (so relatively quickly) had the River Thames that flows underneath been flooding / in spate? Possibly not?And there's the crux of it! The familiar triangle of delivery - Low Cost / Short time / High quality. Pick two for your project. Clearly cost is the one that was sacrificed here.
There's also the access etc of course. As an emergency the stuff just gets done as there's huge pressure and urgency, but as a planned works this would take ages to agree and get consents for etc etc.
The reality is, the extra cost of unplanned works is counteracted by the huge savings of not doing the endless GRIP process, consultation etc so overall a massive cost saving.And there's the crux of it! The familiar triangle of delivery - Low Cost / Short time / High quality. Pick two for your project. Clearly cost is the one that was sacrificed here.
There's also the access etc of course. As an emergency the stuff just gets done as there's huge pressure and urgency, but as a planned works this would take ages to agree and get consents for etc etc.
Unless it was pre CPPP (confirmed period possession plan) at 26 weeks you are paying the full whack to operators.The reality is, the extra cost of unplanned works is counteracted by the huge savings of not doing the endless GRIP process, consultation etc so overall a massive cost saving.
Against that, unplanned track closure costs dwarf those planned 12+ weeks out with full consultation.
Against that, unplanned track closure costs dwarf those planned 12+ weeks out with full consultation.
Yes, I find some possession take years to book, sometimes over 5 years costing big bucks! At the other end short notice access / possessions are cheap & done as a temporary block for just the cost of supervision.in some places. But on much of the network an unplanned closure costs little.
2 June: embankment rebuilt. Things on top of the new abutment in place.
Fantastic effort by the team to get that done.Realtime trains is now showing freight to be back on 9th June, and passenger on 10th June. Great news!
Well, sending a very heavy engine over it would be one way to test the formation. Is there anything mainline registered at Didcot? If there were to be a celebratory steam special I'd have thought Tyseley the more likely origin, but then again given how much passengers have been stuffed about by this blockage the best way you could celebrate reopening the bridge would have been to run a full timetable, not immediately send a Steam through to get in everybody's way.Was hoping there might be a celebratory working of some steam from Didcot but alas not.
I was hoping that instead of planning "celebratory specials" the full timetable can be reinstated, so I don't have to take a 2 hour bus through Wallingford to get to Oxford.Was hoping there might be a celebratory working of some steam from Didcot but alas not.
Thanks for the regular updates.Photo around 4 pm on Sunday 4 June. Much activity at end of renewed embankment. Span appears to be resting on tray on plate on grey Thing on top of new abutment. One of each group of hydraulic jacks appears also to be in contact with the underside of the span.
Our teams successfully lowered Nuneham viaduct onto the new abutment this weekend!
The embankment has now been built back up & we'll begin the reinstatement of the ballast & tracks in preparation for the line reopening on 10 June