Warm storage enabled by the use of er gas axesNo doubt Mr Needle is rubbing his hands at another contract for the Worksop facility![]()
If the figures quoted ate correct then 155 people standing on a five car train is going to be awful. If the train had that many standing I'm not sure I would be comfortable traveling on it on health grounds
If the figures quoted ate correct then 155 people standing on a five car train is going to be awful. If the train had that many standing I'm not sure I would be comfortable traveling on it on health grounds
DfT has just published the East Midlands 2022 contract
Page 76 has the 810s
33 x 5car
capacity 254 (+155 standing) and 47 First class + 2 wheelchairs
leases phased start between Dec 2023 and March 2025
leases end 22/08/27
3 things to note:If the figures quoted ate correct then 155 people standing on a five car train is going to be awful. If the train had that many standing I'm not sure I would be comfortable traveling on it on health grounds
It'll be a darn sight more comfortable than 155 standing on a 222.
That works out at 31 standees per vehicle which includes the vestibules. Even taking first class out of the standing equation that’s an average of 38.75 per vehicle including the vestibules so hardly crush loaded.If the figures quoted ate correct then 155 people standing on a five car train is going to be awful. If the train had that many standing I'm not sure I would be comfortable traveling on it on health grounds
it is the same as other 5 car class 80x's.3 things to note:
finally - it seems both wheelchair spaces on the 810s will be in 1st class? very odd choice imo.
Good idea unless they have to pay for first class to get a seat. Not many people ride first class anyway, so taking away seats for wheelchair space, leaving standard for the rest of the passengers, is a no brainer.finally - it seems both wheelchair spaces on the 810s will be in 1st class? very odd choice imo.
true - works well unless, as you said, they have to pay extra.Good idea unless they have to pay for first class to get a seat. Not many people ride first class anyway, so taking away seats for wheelchair space, leaving standard for the rest of the passengers, is a no brainer.
With 47 seats, its in line with other 5-carriage 80Xs that have had a driving trailer with First Class and a kitchen and a composite carriage - What comes closest is the Hull Trains Class 802s which have 43 seats.speaking of first class, anyone know how much of the train will be 1st? 1 coach, or 1.5?
Good idea unless they have to pay for first class to get a seat. Not many people ride first class anyway, so taking away seats for wheelchair space, leaving standard for the rest of the passengers, is a no brainer.
Where required:true - works well unless, as you said, they have to pay extra.
speaking of first class, anyone know how much of the train will be 1st? 1 coach, or 1.5?

So the trains will be used for a short while before the lease ends ?. I make that a guaranteed income covering 29 to 45 months for all the units.DfT has just published the East Midlands 2022 contract
Page 76 has the 810s
33 x 5car
capacity 254 (+155 standing) and 47 First class + 2 wheelchairs
leases phased start between Dec 2023 and March 2025
leases end 22/08/27
So the trains will be used for a short while before the lease ends ?. I make that a guaranteed income covering 29 to 45 months for all the units.
Always assuming the successor wants them! Yes I know it's unlikely but crazy world we live in etc...Presumably they can only be leased to EMR for the period of their contract. They would of course* be leased to their successor too.
* OK, 350/2s.
Some TOCs don’t have a choice as a minimum length of time as agreed on order. The actual name of this slips my mind, section something or the otherAlways assuming the successor wants them! Yes I know it's unlikely but crazy world we live in etc...
Section 54 - as explained here - https://www.railforums.co.uk/threads/class-710-lo.145774/page-64#post-4265523Some TOCs don’t have a choice as a minimum length of time as agreed on order. The actual name of this slips my mind, section something or the other
These guarantees are generally known as ‘section 54s’, after the part of the Railway Act 1993 that provides for the Secretary of State to direct train operators to use particular stock.... They reduce the re-leasing risk, and so can provide for lower lease prices at the risk of constraining the market.
No section 54 guarantees have been issued since 2014
Scotrail have a Section 54 on their HSTs until 2030. https://angeltrains.co.uk/wp-content/uploads/2021/02/Investor-Report-01_07_14-to-30_06_15-Final.pdfNo section 54 guarantees have been issued since 2014
The only ones remaining are :
class 800, 801, 802 (27.5 years from first unit accepted)
class 444, 450 (until April 2025)
class 350/1 (until April 2025)
class 700 (until March 2036)
class 395 (until 2025)
![]()
Written questions and answers - Written questions, answers and statements - UK Parliament
Information from UK Parliament on written questions & answers, written statements and daily reports.questions-statements.parliament.uk
Don't know if Scottish of Welsh Governments have issued any s54
As it would probably take at least 2 years to get any new train order in service, effectively it is only the East Coast and GWR IETs, and cross London Thameslink fleet that have ongoing guarantees
I don't think the 802s are part of the 27.5-year Section 54 agreement - that relates just to the DfT's IEP procurement for 800/801 (GWR/LNER).No section 54 guarantees have been issued since 2014
The only ones remaining are :
class 800, 801, 802 (27.5 years from first unit accepted)
class 444, 450 (until April 2025)
class 350/1 (until April 2025)
class 700 (until March 2036)
class 395 (until 2025)
Don't know if Scottish of Welsh Governments have issued any s54
As it would probably take at least 2 years to get any new train order in service, effectively it is only the East Coast and GWR IETs, and cross London Thameslink fleet that have ongoing guarantees
Ah good thanks, so potentially the successor to EMR isn't tied to using the 810s if they have other ideas.No section 54 guarantees have been issued since 2014
The only ones remaining are :
class 800, 801, 802 (27.5 years from first unit accepted)
class 444, 450 (until April 2025)
class 350/1 (until April 2025)
class 700 (until March 2036)
class 395 (until 2025)
Given that the 810s were developed specifically for this route to cope with the shorter platforms at St. P, they would have to have one heck of an other idea!Ah good thanks, so potentially the successor to EMR isn't tied to using the 810s if they have other ideas.
A future operator could use, say, 9-car 80x units (9x26m=234m) as their standard train, in which case the 120m/240m 810s would be redundant.Given that the 810s were developed specifically for this route to cope with the shorter platforms at St. P, they would have to have one heck of an other idea!
They could, but I think that the idea of 9-car units on the services from St Pancras is somewhat wishful thinking.A future operator could use, say, 9-car 80x units (9x26m=234m) as their standard train, in which case the 120m/240m 810s would be redundant.