Is Central station Northern line closed only on weekends ?
There's a three (and a bit) day blockade coming up, late 26 Feb to end of service 1 March inclusive. Details here

[Quote from website link]

Liverpool Central station will be closed to Northern line passengers and there will be no services on the Hunts Cross line for three days, as further preparations are made for the continued roll-out of the new fleet of Class 777 trains.

The works will see track alterations made to accommodate eight-car trains at the city centre station, which are due to operate as the roll out continues.

For the work to be completed quickly and safely, Liverpool Central station will close to Northern line services from 22:00 on Sunday 26 February until the end of service on Wednesday 1 March.
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

LPJOHN

Member
Joined
13 May 2019
Messages
80
The 13:35 Liverpool Central was delayed arriving at Kirkby. The 13:58 left Kirkby at 14:05 and did not stop until arriving at Liverpool central.
 

karlbbb

Member
Joined
26 Jul 2009
Messages
460
They aren't at the moment, there's a problem depending on where the units were built of them basically not talking to each other.
Are there any proposed solutions to this, do you (or anyone) know? Seems like rather a large oversight! o_O
 

Liverpool 507

Member
Joined
17 Jan 2018
Messages
642
Location
Merseyside
777018 is operating Kirkby line services today with 777049 operating on Kirkby crew training runs. 777013 is operating crew training/testing runs up to Hillside. 777001 and 777003 were out testing overnight as an eight car set.
 

jamesst

Established Member
Joined
4 May 2011
Messages
1,370
Location
Merseyside
Are there any proposed solutions to this, do you (or anyone) know? Seems like rather a large oversight! o_O
It'll be sorted in good time, just need some work on the software. Some can operate together, just depends where they were built!!
 

315801

Member
Joined
12 Jul 2022
Messages
201
It would certainly solve the problem running like that as there wouldn't or shouldn't be any tech issues
 

AlexNL

Established Member
Joined
19 Dec 2014
Messages
1,716
It'll be sorted in good time, just need some work on the software. Some can operate together, just depends where they were built!!
That sounds like the issues NS found in the mid-2000s when the back then new SLT trains were tested.

If memory serves me right the ones built by Bombardier couldn't talk to the ones built by Siemens and vice versa, despite being built by a Siemens-Bombardier consortium. Those issues were resolved though.
 

Wezz

Member
Joined
7 Aug 2019
Messages
174
Location
Liverpool, UK
All Kirkby services (Mon - Sat) except for the 23:55 service will be formed of Class 777's from Monday 20th February, announced on the Mersey Railways 2.0 Facebook group by a staff member who works on the Class 777 programme.
 
Last edited:

Sam 76

Member
Joined
10 Nov 2021
Messages
499
Location
Southport.
All Kirkby services (Mon - Sat) except for the 23:55 service will be formed of Class 777's from Monday 20th February, announced on the Mersey Railways 2.0 Facebook group by a staff member who works on the Class 777 program.
Seems like a really significant moment for the programme. I wonder if it will lead to more withdrawals of the 507/508 ?
 

Vespa

Established Member
Joined
20 Dec 2019
Messages
1,733
Location
Merseyside
Seems like a really significant moment for the programme. I wonder if it will lead to more withdrawals of the 507/508 ?

Undoubtedly as more 777 arrives spaces will need to made for them, the loco shed at Birkenhead Central would have been a useful storage facility, as it is the old trains will have to leave the system for scrapping to make room.


Soon the focus will shift from incoming 777s to chasing the few 507/8 still in service right up to the inevitable farewell tour.
 

Liverpool 507

Member
Joined
17 Jan 2018
Messages
642
Location
Merseyside
Undoubtedly as more 777 arrives spaces will need to made for them, the loco shed at Birkenhead Central would have been a useful storage facility, as it is the old trains will have to leave the system for scrapping to make room.


Soon the focus will shift from incoming 777s to chasing the few 507/8 still in service right up to the inevitable farewell tour.

Southport sidings are seeing more units being stored in the same way New Brighton Wall Siding is used for those in the queue for Birkenhead North.

507004 (recently moved) and 507032 have been at Southport for a number of weeks.
 

61653 HTAFC

Veteran Member
Joined
18 Dec 2012
Messages
19,352
Location
Yorkshire
Undoubtedly as more 777 arrives spaces will need to made for them, the loco shed at Birkenhead Central would have been a useful storage facility, as it is the old trains will have to leave the system for scrapping to make room.


Soon the focus will shift from incoming 777s to chasing the few 507/8 still in service right up to the inevitable farewell tour.
Hasn't there been at least two "farewell" tours already? How many do they need?
 

Wezz

Member
Joined
7 Aug 2019
Messages
174
Location
Liverpool, UK
Undoubtedly as more 777 arrives spaces will need to made for them, the loco shed at Birkenhead Central would have been a useful storage facility, as it is the old trains will have to leave the system for scrapping to make room.


Soon the focus will shift from incoming 777s to chasing the few 507/8 still in service right up to the inevitable farewell tour.
508122 and 508138 are due to be the next units to leave us, no date yet but it won't be long.
 

M28361M

Member
Joined
15 May 2014
Messages
681
Location
Liverpool
There will be a second 777 diagram on the Kirkby line from 20th February, according to a reliable source on “Mersey Railways 2.0” (new Facebook group)
 

Bletchleyite

Veteran Member
Joined
20 Oct 2014
Messages
113,379
Location
"Marston Vale mafia"
So I have now been on one and...it was OK. Better than a 507/508, but then it wouldn't be hard to be better than rolling stock that is so poorly designed that you'd think the designer hated passengers with a passion.

Seats in particular absolutely awful. Legroom poor. Lighting grossly excessive and too direct. Step up from the moving ramp noticeably higher than other Stadlers and may be difficult for some wheelchair users (I've heard a complaint about this already). Ride average with a nasty sway on jointed track. Build quality and panel fit poor (where were these built?), and some bizarrely bad design quirks e.g. the heating conduit.

I'll post a decent review in trip reports when I get back tomorrow or Sunday, but overall for all the shouting this was a massive anticlimax. Overall markedly inferior to the London Underground S8 which I would normally hold as the benchmark for this sort of train - I find the S8s superb and very, very difficult to fault in any way. They will do, but they really are not good. And that's from a "paid up" member of the Stadler fan club.
 

MattRat

On Moderation
Joined
26 May 2021
Messages
2,128
Location
Liverpool
I reckon late March/early April.

I'm not on the 777 programme though so can't confirm.
Personally I'd wait till after the Grand National. Guarantee 6 cars instead of hoping to have the 8 cars ready. But with the way they introduced them on the Kirby line, I doubt they'll do that.
 

Bletchleyite

Veteran Member
Joined
20 Oct 2014
Messages
113,379
Location
"Marston Vale mafia"
Maybe there are different seat spacings. I had about four inches between my knees and the seat in front. I'm about six foot two.

I tried a couple. Normal seat was too tight. Priority was only just OK. Facing seemed good. Similar deal to a 350/2 though very slightly more space than that.

Very narrow though, about the same as the 700 but much, much less comfortable due to the backrest shape.

They'll do. They aren't good. Perhaps overhyped?
 
Last edited:

Grumpy Git

On Moderation
Joined
13 Oct 2019
Messages
2,254
Location
Liverpool
Overall markedly inferior to the London Underground S8 which I would normally hold as the benchmark for this sort of train - I find the S8s superb and very, very difficult to fault in any way.

I happen to know someone high-up on the management team at Merseytravel, who was involved in the procurement of these trains. I can't remember his actual quote to me personally regarding the Bombardier offer at the time, but it was along the lines of 'too bl**dy expensive'.

You pays your money and takes your choice.
 

61653 HTAFC

Veteran Member
Joined
18 Dec 2012
Messages
19,352
Location
Yorkshire
So I have now been on one and...it was OK. Better than a 507/508, but then it wouldn't be hard to be better than rolling stock that is so poorly designed that you'd think the designer hated passengers with a passion.
That's a bit hyperbolic, don't you think? Sure the old trains are getting on a bit now and due for replacement, but the refurb done in the 2000s had many not realising they were the same trains as before.
 

Bletchleyite

Veteran Member
Joined
20 Oct 2014
Messages
113,379
Location
"Marston Vale mafia"
That's a bit hyperbolic, don't you think? Sure the old trains are getting on a bit now and due for replacement, but the refurb done in the 2000s had many not realising they were the same trains as before.

A train that has not one single seat with a good window view is designed by someone whose first thought isn't passengers (see also the 20m Mk3 derived DMUs and EMUs). Though I was indeed referring to as built, as they had rubbish seats then to boot. The refurb did add good seats, something the 777 has gone back on - they are very hard and an extremely odd shape which pushes a tall passenger into leaning forward, forcing a rounded back which is the total opposite of good posture.

Window alignment is certainly something the 777s aren't terrible at - there are a few misaligned seats but not many.

It appears the protruding headrest issue was "fixed" by thickening the cushion at the top. These mock ups really should be done before any procurements are finalised so you can genuinely correct problems rather than just bodging them.
 