Luton Council have announced an enquiry into the DART project around lateness and overspends.

This seems more about political point scoring than a sensible use of time and money.
Similar to the ongoing Edinburgh Tram Inquiry. At least it will allow the Luton council to waste some money on 'fact- finding' trips and report back by 2027 that everything that could go wrong went wrong
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

Haywain

Veteran Member
Joined
3 Feb 2013
Messages
24,866
Luton Council have announced an enquiry into the DART project around lateness and overspends.

This seems more about political point scoring than a sensible use of time and money.
As a matter of interest, who will be point scoring against who?
 

jon0844

Veteran Member
Joined
1 Feb 2009
Messages
31,007
Location
UK
Well, the elections in May will be long gone before any enquiry is completed so any point scoring of that nature will have no impact at all.

Isn't it better if the outcome isn't known, but you can just point out that there is one?
 

Haywain

Veteran Member
Joined
3 Feb 2013
Messages
24,866
Isn't it better if the outcome isn't known, but you can just point out that there is one?
The political landscape in Luton is duch that even with an enquiry taking place it would be a major shock if Labour did not come out of the election as the ruling party.
 

spag23

On Moderation
Joined
4 Nov 2012
Messages
793
Getting this back on track (!), the DART trials restart next Wednesday, 15th, but unfortunately I've had to turn my invite down as I'll be 'oop North'.
Have you got a link to the invitation? Or was it to previous responders only?
 

zwk500

Veteran Member
Joined
20 Jan 2020
Messages
18,681
Location
Northampton
Isn't it better if the outcome isn't known, but you can just point out that there is one?
This is the kind of political point scoring that is likely to put voters off engaging at all, let alone voting for one party over another.

If there are lessons to be learned from the project, by all means have an inquriy to establish what went wrong and how to fix them. But turning it into a political football means that 1. It's outputs will be largely ignored as partisan and 2. It will cost a lot more money as people fight for control of the summary statement.
 

John R

Established Member
Joined
1 Jul 2013
Messages
6,151
This is the kind of political point scoring that is likely to put voters off engaging at all, let alone voting for one party over another.

If there are lessons to be learned from the project, by all means have an inquriy to establish what went wrong and how to fix them. But turning it into a political football means that 1. It's outputs will be largely ignored as partisan and 2. It will cost a lot more money as people fight for control of the summary statement.
To be fair, it was only the poster who originally reported the enquiry who said it would be used for political point scoring. Personally I'd be somewhat upset if a project which had gone so far over budget wasn't the subject of some retrospective scrutiny as to what went wrong.

In Bristol, the cost of refurbishing the Bristol Beacon (prev Colston Hall) has leapt from 52m to 135m, with the City Council's (who own it) contribution rising from an original 10m to 80m. I'm sure council tax payers would welcome understanding at some point what went wrong that has saddled the council with 2.3m per annum of borrowing costs for the next 50 years to pay for it.
 

zwk500

Veteran Member
Joined
20 Jan 2020
Messages
18,681
Location
Northampton
To be fair, it was only the poster who originally reported the enquiry who said it would be used for political point scoring. Personally I'd be somewhat upset if a project which had gone so far over budget wasn't the subject of some retrospective scrutiny as to what went wrong.

In Bristol, the cost of refurbishing the Bristol Beacon (prev Colston Hall) has leapt from 52m to 135m, with the City Council's (who own it) contribution rising from an original 10m to 80m. I'm sure council tax payers would welcome understanding at some point what went wrong that has saddled the council with 2.3m per annum of borrowing costs for the next 50 years to pay for it.
Oh totally understand the desire to learn lessons. However, such an inquiry needs to be clearly independent from the body(ies) who are going to be roundly criticised by it.
 

jon0844

Veteran Member
Joined
1 Feb 2009
Messages
31,007
Location
UK
This is the kind of political point scoring that is likely to put voters off engaging at all, let alone voting for one party over another.
I meant better for the party calling for an inquiry, on the basis that most people will just jump to the conclusion of 'guilty as charged'.
 

TheHSRailFan

Member
Joined
16 Jun 2018
Messages
299
Had a friend who did yesterday's testing. In his own words, he called it "A Mess" as well as pointing out many faults with the system.
 

spag23

On Moderation
Joined
4 Nov 2012
Messages
793
Had a friend who did yesterday's testing. In his own words, he called it "A Mess" as well as pointing out many faults with the system
Disappointing, given it was the second exercise. Can he expand on the issues?
 

Mike395

Forum Staff
Staff Member
Administrator
Joined
23 May 2009
Messages
3,407
Location
Bedford
Disappointing, given it was the second exercise. Can he expand on the issues?
I was also there and I wouldn't say it was a mess - generally I was fairly impressed, and the main problems are easily resolveable.

Biggest single one for me personally was signage, it's lacking in several areas (lots of small niggles I won't detail here, but notably at the airport end, there's a fire exit underneath a big sign with 'Welcome to Luton Airport' or similar wording, and insufficient pointers to where the lifts are, or what the buttons in the lift do - there's also some confusing digital signage which don't map the platform numbers correctly) but that's all easily rectifiable, and in the debrief I had confidence that the feedback was being taken on board.

But yeah, the system itself is actually quite impressive, I love the large windows on the shuttles themselves and the team there seem to have thought through how to deal with passenger comms when issues occur like needing to temporarily go to single-shuttle operations.
 

jon0844

Veteran Member
Joined
1 Feb 2009
Messages
31,007
Location
UK
Signage at St Pancras was awful when I did the testing for Eurostar. I recall Heathrow T5 being awful from day one too.

Amazing that these things can't be worked out from the outset. You surely don't need hundreds of people testing a service to identify things anyone could do on their own either on the floor during construction or on a computer.

And yet it seems to happen over and over.
 

DDB

Member
Joined
11 Sep 2011
Messages
733
Signage at St Pancras was awful when I did the testing for Eurostar. I recall Heathrow T5 being awful from day one too.

Amazing that these things can't be worked out from the outset. You surely don't need hundreds of people testing a service to identify things anyone could do on their own either on the floor during construction or on a computer.

And yet it seems to happen over and over.
Probably the benefit of outsiders looking at it. If you have spent weeks/years designing/building a system you know it so well it is hard to forget everything and work out what isn't obvious for someone new.
 

Basil Jet

On Moderation
Joined
23 Apr 2022
Messages
1,090
Location
London
Probably the benefit of outsiders looking at it. If you have spent weeks/years designing/building a system you know it so well it is hard to forget everything and work out what isn't obvious for someone new.
But if you've spent years looking at previous systems, seen how the signage was implemented, seen how it failed and seen how it had to be changed, you should have learnt from that.
 

jon0844

Veteran Member
Joined
1 Feb 2009
Messages
31,007
Location
UK
Probably the benefit of outsiders looking at it. If you have spent weeks/years designing/building a system you know it so well it is hard to forget everything and work out what isn't obvious for someone new.

I was once a software playtester and agree that sometimes you need another set of eyes (just as when writing, you usually need someone else to read what you wrote to look for typos you're blind to), but the issues seem so obvious that I am surprised it always seems to be overlooked by loads of people before the official testing.

It feels like the usability aspects are simply not designed properly from the outset.
 

MML

Member
Joined
25 Oct 2015
Messages
592
The large external Luton Dart Parkway sign on the railway side of the building still has failed illumination. In the dark anybody arriving by rail is greated by the words 'Luton Dart kway'.
I really hope after spending £290m on this project, it isn't signed off without someone insisting the light bulbs are replaced.
 

stuu

Established Member
Joined
2 Sep 2011
Messages
3,774
I was once a software playtester and agree that sometimes you need another set of eyes (just as when writing, you usually need someone else to read what you wrote to look for typos you're blind to), but the issues seem so obvious that I am surprised it always seems to be overlooked by loads of people before the official testing.

It feels like the usability aspects are simply not designed properly from the outset.
One part of the company I work for does customer experience testing, for companies and organisations. Some of the problems they find are so blatantly obvious you wonder how they can have been missed. See also Oyster validators at Farringdon for transfers
 

jon0844

Veteran Member
Joined
1 Feb 2009
Messages
31,007
Location
UK
Ah, yes, Farringdon is a great example. I mean, let's all walk up to the exit to touch in or out as required. Thankfully now sorted.

Still, I guess they only had 4 or 5 years to notice...
 

Kite159

Veteran Member
Joined
27 Jan 2014
Messages
22,883
Location
West of Andover
Email received from Thameslink gives a date of the 10th March for a soft launch for 4 hours a day;

A soft-launch of the DART is scheduled for the 10th March when it will operate for four hours per day. It will gradually increase its operating hours on the run-up to its full launch, currently scheduled to take place before Easter.

 

InOban

On Moderation
Joined
12 Mar 2017
Messages
4,538
That seems unlikely when there are test events after the 10th, up to the 18th.

During the trials, volunteers will be asked to take part in a series of trial situations including fire evacuation, station evacuation and a series of customer service scenarios.

Volunteers are required to detail their availability for each date, volunteers will be chosen based on a first come first serve basis.
  • Wednesday 8th March 2023, 9am – 1pm
  • Monday 13th March 2023, 2pm – 5pm
  • Wednesday 15th March 2023, 9am – 1pm
  • Saturday 18th March 2023, 9am – 1pm
 
Last edited by a moderator:

43066

Veteran Member
Joined
24 Nov 2019
Messages
12,089
Location
London
The large external Luton Dart Parkway sign on the railway side of the building still has failed illumination. In the dark anybody arriving by rail is greated by the words 'Luton Dart kway'.
I really hope after spending £290m on this project, it isn't signed off without someone insisting the light bulbs are replaced.

I’ve also noticed this. Its been like it for ages, and does look very sloppy. I assume replacing them is a difficult/expensive exercise given the size/how high up they are. Hopefully it’ll be sorted by the launch.
 

Meerkat

Established Member
Joined
14 Jul 2018
Messages
9,276
Perfect for anyone flying on the 11th ;)
Maybe on the way home but don't think I would risk missing a flight until they have it working reliably for a while. At least you can get off a bus and walk!
 