701s were getting in the way of the timetabled rolling stock plan.Thanks. So from Eastleigh.
Rock rail had raised charges middle of last year for eight 701s and 701019 was one of them. Now does that mean the units going for store are ones that are already accepted (to a certain extent) as opposed to units merely off the production line with no where to go ?.
Looks ominous unless SWR just want more room to do FFR (Fault Free Running) on some more 701s.
I believe they were due to be moved out of the way before the December timetable change but due to strikes and various other issues that never happened. They were cluttering up sidings where berth stocked was due to go.
701s are still being built and sent from Derby but with no immediate sign of introduction they have to be put somewhere, Marchwood seems an easy and local option so it’s not too surprising it was selected by SWR.