Try following this one. Sorry it's not totally in sequence but shows how one little problem reverberates around the network.
I was at Dore & Totley station this morning where passengers were waiting for the 10.53 into Sheffield, 2S78, the Northern 9.42 from Piccadilly. At 10.51 it was announced and showing on the CIS as on time, a fact that was attracting positive comments as Dore has an unhappy reputation for consistently featuring in the worst 100 stations in the country for timely trains. It's not whether the train will be late, but by how much - and if TPE whether it will run at all.
However EMR's westbound IR62, their 6.51 4 car 158 from Norwich to Liverpool, came into the station about 10.52, and slowly stopped. (158858 and another.) No stop booked and no signal to stop at. Driver alighted, walked to the other end, awaited a signal, and returned to Sheffield. See; https://www.realtimetrains.co.uk/service/gb-nr:P53259/2022-11-29/detailed
It was 39 minutes late by the time it got back into Sheffield at 11.16 and cancelled due to a problem with the on-board safety systems (M0).Not much help for those wanting to get to Manchester and Liverpool, but what followed?
Northern's 2 car delayed 2S78 was due into Sheffield at 10.59 but arrived at 11.19. It set off back to Manchester as 2S79 (due out at 11.14) at 11.22, only 8 minutes down. Excellent platform work there, but was seemingly held before Dore Station Junction arriving at Dore 11 minutes late at 11.31 and at Piccadilly 11 minutes late.
It was waiting for TPE 5B73 Nova 3 from Cleethorpes to Piccadilly to overtake (ECS to wind people up more) and that growled through Dore at 11.28, it too having been held up both arriving at Sheffield and again at Dore Station Junction.
Following Northern's eastbound 2S78 was 6G65 from Earles Sidings to Walsall Freight Terminal. It should have left Earles at 9.19 but departed 72 minutes down at 10.31 to follow the Northern service. It then had to wait at Grindleford before entering Totley Tunnel, to be held again at Dore West Junction for a path to go south, finally clearing Dore South Junction at 11.24, 95 minutes late. It crawled up into Bradway tunnel but reached its final destination on time.
This, of course delayed services on the Midland mainline, both north and south, but in the queue eastbound along the Hope Valley was TPE's 10.18, 1B72, Manchester - Cleethorpes which was running close to time at Bamford but passed Dore West 23 minutes down and Dore Station Junction at 11.26. (It maintained about that until Scunthorpe where it was terminated due to signal failure.)
Meanwhile Cross Country Edinburgh - Plymouth 1V52 that was on time at Sheffield was 14 minutes late at 11.09 at Dore Station Junction, arriving at Penzance 23 minutes late.
East Midlands 1C41 Sheffield - St Pancras left Sheffield at 11.01 on time but passed Dore Station Junction 11 minutes late at 11.15, finally arriving at St Pancras 31 minutes late.
I'll leave others to follow this further but the TPE, Northern, Cross Country and EMR London services delayed by this mishap in the Sheffield suburbs will have delayed others across the country, on top of other reasons for delays. Follow all the rippling minutes lost across the network starting from this hour around Dore Station Junction; https://www.realtimetrains.co.uk/se...2022-11-29/1104?stp=WVS&show=all&order=actual
Now if the double track had been restored and Dore & Totley station's second 6 car platform been operational this situation would have been less serious, and if the longer Dore chord were complete even less so. If one of the Dore platforms were made bi-directional there would be yet more flexibility. But the track work and station platforms due originally to be complete in 2018 may not now be ready until late 2023 or early 2024 - but won't be bi-directional.
This is why we need more investment around choke points before reopening most of the long closed lines. We have to make what's still open work a lot, lot better as a priority.
I was at Dore & Totley station this morning where passengers were waiting for the 10.53 into Sheffield, 2S78, the Northern 9.42 from Piccadilly. At 10.51 it was announced and showing on the CIS as on time, a fact that was attracting positive comments as Dore has an unhappy reputation for consistently featuring in the worst 100 stations in the country for timely trains. It's not whether the train will be late, but by how much - and if TPE whether it will run at all.
However EMR's westbound IR62, their 6.51 4 car 158 from Norwich to Liverpool, came into the station about 10.52, and slowly stopped. (158858 and another.) No stop booked and no signal to stop at. Driver alighted, walked to the other end, awaited a signal, and returned to Sheffield. See; https://www.realtimetrains.co.uk/service/gb-nr:P53259/2022-11-29/detailed
It was 39 minutes late by the time it got back into Sheffield at 11.16 and cancelled due to a problem with the on-board safety systems (M0).Not much help for those wanting to get to Manchester and Liverpool, but what followed?
Northern's 2 car delayed 2S78 was due into Sheffield at 10.59 but arrived at 11.19. It set off back to Manchester as 2S79 (due out at 11.14) at 11.22, only 8 minutes down. Excellent platform work there, but was seemingly held before Dore Station Junction arriving at Dore 11 minutes late at 11.31 and at Piccadilly 11 minutes late.
It was waiting for TPE 5B73 Nova 3 from Cleethorpes to Piccadilly to overtake (ECS to wind people up more) and that growled through Dore at 11.28, it too having been held up both arriving at Sheffield and again at Dore Station Junction.
Following Northern's eastbound 2S78 was 6G65 from Earles Sidings to Walsall Freight Terminal. It should have left Earles at 9.19 but departed 72 minutes down at 10.31 to follow the Northern service. It then had to wait at Grindleford before entering Totley Tunnel, to be held again at Dore West Junction for a path to go south, finally clearing Dore South Junction at 11.24, 95 minutes late. It crawled up into Bradway tunnel but reached its final destination on time.
This, of course delayed services on the Midland mainline, both north and south, but in the queue eastbound along the Hope Valley was TPE's 10.18, 1B72, Manchester - Cleethorpes which was running close to time at Bamford but passed Dore West 23 minutes down and Dore Station Junction at 11.26. (It maintained about that until Scunthorpe where it was terminated due to signal failure.)
Meanwhile Cross Country Edinburgh - Plymouth 1V52 that was on time at Sheffield was 14 minutes late at 11.09 at Dore Station Junction, arriving at Penzance 23 minutes late.
East Midlands 1C41 Sheffield - St Pancras left Sheffield at 11.01 on time but passed Dore Station Junction 11 minutes late at 11.15, finally arriving at St Pancras 31 minutes late.
I'll leave others to follow this further but the TPE, Northern, Cross Country and EMR London services delayed by this mishap in the Sheffield suburbs will have delayed others across the country, on top of other reasons for delays. Follow all the rippling minutes lost across the network starting from this hour around Dore Station Junction; https://www.realtimetrains.co.uk/se...2022-11-29/1104?stp=WVS&show=all&order=actual
Now if the double track had been restored and Dore & Totley station's second 6 car platform been operational this situation would have been less serious, and if the longer Dore chord were complete even less so. If one of the Dore platforms were made bi-directional there would be yet more flexibility. But the track work and station platforms due originally to be complete in 2018 may not now be ready until late 2023 or early 2024 - but won't be bi-directional.
This is why we need more investment around choke points before reopening most of the long closed lines. We have to make what's still open work a lot, lot better as a priority.