Manchester Piccadilly P13 & 14 new platforms

Status
Not open for further replies.

td97

Established Member
Joined
26 Jul 2017
Messages
1,557
The long-neglected Manchester Piccadilly platforms 13 and 14 are to be renewed later this year/early 2023.
There will be mainly accessibility improvements with compliant platform/track offsets, resurfacing and the big win is tactile paving.
There's planned to be a Christmas 2022 block and weekend closures in January (subject to confirmation).
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

The Planner

Veteran Member
Joined
15 Apr 2008
Messages
19,713
The long-neglected Manchester Piccadilly platforms 13 and 14 are to be renewed later this year/early 2023.
There will be mainly accessibility improvements with compliant platform/track offsets, resurfacing and the big win is tactile paving.
There's planned to be a Christmas 2022 block and weekend closures in January (subject to confirmation).
Nothing to be confirmed, blocks are happening. Will be a period with trains running through without stopping.
 

plugwash

Established Member
Joined
29 May 2015
Messages
1,995
Any idea what the arrangements will be for passengers? shuttle bus between picadilly and oxford road?
 

coxxy

Member
Joined
16 Aug 2013
Messages
375
Slightly unrelated... but is the plan for 15 and 16 officially dead again yet?
 

alf

On Moderation
Joined
1 Mar 2021
Messages
426
Location
Bournemouth
Slightly unrelated... but is the plan for 15 and 16 officially dead again yet?
Yes, I wrongly hoped this topic was about the desperately needed, but expensive new 15 & 16 platforms, not about putting in tactile paving in the existing 13 & 14.

Not being a Mancunian I assumed 13 & 14 were the numbers of the new platforms.

What wonderful news if 15 & 16 & associated tracks were to be built. That would be an improvement worth trumpeting.
 

snowball

Established Member
Joined
4 Mar 2013
Messages
8,144
Location
Leeds
Has there ever been an actual plan or just vague wishes and promises?
There was most definitely an actual plan but it's getting to be quite a few years ago now. If was to have followed on from the Ordsall Chord. Network Rail submitted an application for a Transport and Works Order for two extra through platforms at Piccadilly and realignment of the four through platforms at Oxford Road with closure of the bay. It underwent public consultations and a public inquiry. The inspector's report on the inquiry was sent to the then SoS for transport, Chris Grayling, but he never issued a decision for or against it, though he made disparaging remarks about the cost.
 

swt_passenger

Veteran Member
Joined
7 Apr 2010
Messages
34,296
There was most definitely an actual plan but it's getting to be quite a few years ago now. If was to have followed on from the Ordsall Chord. Network Rail submitted an application for a Transport and Works Order for two extra through platforms at Piccadilly and realignment of the four through platforms at Oxford Road with closure of the bay. It underwent public consultations and a public inquiry. The inspector's report on the inquiry was sent to the then SoS for transport, Chris Grayling, but he never issued a decision for or against it, though he made disparaging remarks about the cost.
He probably read a post in these forums that claimed it could all be fixed with smart timetabling, digital signalling, batteries or hydrogen - or some combination… :D
 

py_megapixel

Established Member
Joined
5 Nov 2018
Messages
7,496
Location
Northern England
One of the biggest improvements they could make in my opinion, short of building a new set of platforms, would be to fence off the almost entirely unused rearmost sections of the platform faces (i.e. the western end of P13 and the eastern end of P14). Not sure if there's some kind of modular solution that could be used to allow the fences to be removed in the event of a Pendolino diversion (which appears to be the only circumstance in which passengers need to board/alight in those sections). That way passengers could spread out a lot more without danger of falling onto the track.
 

JD2168

Established Member
Joined
11 Jul 2022
Messages
1,732
Location
Sheffield
Hopefully these improvements at platforms 13 & 14 will include a way of it not feeling you are in the middle of a strong Gale or like in a wind tunnel whilst stood waiting for your train.
 

py_megapixel

Established Member
Joined
5 Nov 2018
Messages
7,496
Location
Northern England
I think reversing the ends used would be sensible. The 13 end is wider.
Presumably that has the disadvantage that you need a load of different stopping points for all the different stock that uses it, whereas the current arrangement means everything just goes all the way along and stops at the front. You could stop everything halfway along, but for shorter trains, that wouldn't line up neatly with where the stairs are. Also, when there is disruption that means that trains "stack up", the rear bit sometimes has another train in it. I can't imagine those trains sitting in the station throat instead would be a good idea.

(this is another reason to fence off the unused sections - so that people don't try to board a train which has stopped but not released the doors because it isn't in the right place)
 

yorkie

Forum Staff
Staff Member
Administrator
Joined
6 Jun 2005
Messages
78,421
Location
Yorkshire
Can we stick to updates regarding what is actually happening in this thread please.

If anyone would like to create a separate thread for changes you'd like to see, feel free to do so!

Thanks :)
 

317 forever

Established Member
Joined
21 Aug 2010
Messages
3,286
Location
North West
The long-neglected Manchester Piccadilly platforms 13 and 14 are to be renewed later this year/early 2023.
There will be mainly accessibility improvements with compliant platform/track offsets, resurfacing and the big win is tactile paving.
There's planned to be a Christmas 2022 block and weekend closures in January (subject to confirmation).
I reckoned on changing to those platforms on the Christmas Bank Holiday. There may be bus replacements between Piccadilly and Oxford Road then.
 

Bertie the bus

Established Member
Joined
15 Aug 2014
Messages
3,216
The long-neglected Manchester Piccadilly platforms 13 and 14 are to be renewed later this year/early 2023.
There will be mainly accessibility improvements with compliant platform/track offsets, resurfacing and the big win is tactile paving.
There's planned to be a Christmas 2022 block and weekend closures in January (subject to confirmation).
So lots of disruption for virtually no gain then. Tactile paving is not a big win. P13/14 are crawling with staff and if you step foot over the red line you are guaranteed to get shouted at so there is absolutely no possibility of visually impaired passengers getting too close to the platform edge.
 

td97

Established Member
Joined
26 Jul 2017
Messages
1,557

Bletchleyite

Veteran Member
Joined
20 Oct 2014
Messages
113,643
Location
"Marston Vale mafia"
Yes it is. Every platform on the network without tactile paving is too a high risk. This incident is a key theme with every platform improvement project.

Tactile paving at Picc is probably low risk, because you get barked at before you get anywhere near the edge!
 

py_megapixel

Established Member
Joined
5 Nov 2018
Messages
7,496
Location
Northern England
So lots of disruption for virtually no gain then. Tactile paving is not a big win. P13/14 are crawling with staff and if you step foot over the red line you are guaranteed to get shouted at so there is absolutely no possibility of visually impaired passengers getting too close to the platform edge.
Anything that reduces platform dwell times is a good thing in such a busy corridor, and if this work involves reducing the somewhat large platform gap - which is what "compliant platform/track offsets" sounds like - then it will allow people to board and alight faster.

Of course, the aim should really be true level boarding - but the idea that will get anywhere near Castlefield in the foreseeable future is but a pipe-dream. (Unless TfW sticks a FLIRT onto a random North Wales Coast diagram at some point in the future, as they have a habit of doing with Sprinters at the moment)
 

Bertie the bus

Established Member
Joined
15 Aug 2014
Messages
3,216
Yes it is. Every platform on the network without tactile paving is too a high risk. This incident is a key theme with every platform improvement project.
Just selectively partially quoting a post and then posting a link to a completely irrelevant story adds nothing.
 

Jozhua

Established Member
Joined
6 Jan 2019
Messages
1,891
Picc 13/14 could absolutely handle more passengers...if they were on a metro line. However, without PSDs, level boarding and trains designed with frequent, wide doors, it's just not going to happen.

Honestly, I worry about the safety of 13/14 - far too busy to handle the volumes of passengers on there. Tactile paving is a welcome improvement, but they are not going to be safe until new capacity is added.
 

Mollman

Established Member
Joined
21 Sep 2016
Messages
1,718
Location
Preston
So lots of disruption for virtually no gain then. Tactile paving is not a big win. P13/14 are crawling with staff and if you step foot over the red line you are guaranteed to get shouted at so there is absolutely no possibility of visually impaired passengers getting too close to the platform edge.
It will get rid of the announcement they play every minute now to warn people that some platforms do not have tactile paving!
 

GoneSouth

Established Member
Joined
17 Dec 2018
Messages
1,491
Tactile paving at Picc is probably low risk, because you get barked at before you get anywhere near the edge!
Barking at someone without sight to step back behind the red line is less than helpful. They probably don’t know they’ve stepped over it so why should they think someone is barking at them! By the time the barking person has made it clear who they are barking at it might be too late.

The platform width, overcrowding and relatively high frequency of trains I would have thought made it a higher risk than many.

Tactile paving on every platform is absolutely the right thing to do.
 

The Snap

Established Member
Joined
10 Jun 2005
Messages
3,156
Works now well underway on platforms 13 and 14. Platform closed on a Christmas Eve and will remain so until 3rd Jan
 

Cantab26

Established Member
Joined
9 Jun 2016
Messages
1,948
What are the arrangements in terms of replacement bus services?
Today it looked like a half hourly loop: Piccadilly, Oxford Road, Deansgate, Piccadilly.

Plenty of confusion on trains and platforms to be observed
 

Bletchleyite

Veteran Member
Joined
20 Oct 2014
Messages
113,643
Location
"Marston Vale mafia"
Today it looked like a half hourly loop: Piccadilly, Oxford Road, Deansgate, Piccadilly.

Plenty of confusion on trains and platforms to be observed

Could they not have done half at a time rather than closing it? It would have required special crowd control measures (i.e. physically preventing people going down until their train was next) but with reduced numbers of passengers over the "interval" period it would surely have been workable.
 

The Planner

Veteran Member
Joined
15 Apr 2008
Messages
19,713
Could they not have done half at a time rather than closing it? It would have required special crowd control measures (i.e. physically preventing people going down until their train was next) but with reduced numbers of passengers over the "interval" period it would surely have been workable.
Its more to do with equipment, materials and where you store it as well as the buffer zone you would need. Having the whole thing shut makes the job quicker.
 

Llandudno

Established Member
Joined
25 Dec 2014
Messages
2,748
Location
Matlock
Could they not have done half at a time rather than closing it? It would have required special crowd control measures (i.e. physically preventing people going down until their train was next) but with reduced numbers of passengers over the "interval" period it would surely have been workable.
The platform gestapo at Piccadilly would have relished the challenge….!
 