"Due to a short-notice change to the timetable"

Status
Not open for further replies.

XAM2175

Established Member
Joined
8 Jun 2016
Messages
3,471
Location
Glasgow
Wonderful. I bet that goes down well. Fortunately I never bother with advances. Presumably one can still ask for a refund if the pre booked train vanishes?
Yes, the right to fee-free abandonment of journey is unchanged.

I'm not sure how never bothering with advances is any relevance though?
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

Watershed

Veteran Member
Associate Staff
Senior Fares Advisor
Joined
26 Sep 2020
Messages
16,804
Location
UK
The DfT claims, in this FoI response, not to have sent any instructions or guidance to train operators regarding the use of cancellation reasons.

It seems to me that they may have missed some documents, particularly since @800001 has stated that this instruction has come from the DfT.

I hope that Mr Walker, the person who made the request, raises an appeal. It would be interesting to see whether that perhaps leads to the DfT confirming what @800001 says TOCs were told.
 

800001

Established Member
Joined
24 Oct 2015
Messages
7,401
O
The DfT claims, in this FoI response, not to have sent any instructions or guidance to train operators regarding the use of cancellation reasons.

It seems to me that they may have missed some documents, particularly since @800001 has stated that this instruction has come from the DfT.

I hope that Mr Walker, the person who made the request, raises an appeal. It would be interesting to see whether that perhaps leads to the DfT confirming what @800001 says TOCs were told.
only going by what I was told!!!! No need to tag me twice in the post
 

Watershed

Veteran Member
Associate Staff
Senior Fares Advisor
Joined
26 Sep 2020
Messages
16,804
Location
UK
O

only going by what I was told!!!! No need to tag me twice in the post
Of course. I don't doubt that what you were told is accurate, but at the moment there isn't anything in the public domain about it.
 

kkong

Member
Joined
8 Sep 2008
Messages
1,180
LNER website is now stating amended / cancelled services are "due to a shortage of train crew", which is an improvement.
 

Bertie the bus

Established Member
Joined
15 Aug 2014
Messages
3,216
The DfT claims, in this FoI response, not to have sent any instructions or guidance to train operators regarding the use of cancellation reasons.

It seems to me that they may have missed some documents, particularly since @800001 has stated that this instruction has come from the DfT.

I hope that Mr Walker, the person who made the request, raises an appeal. It would be interesting to see whether that perhaps leads to the DfT confirming what @800001 says TOCs were told.
It seems to me as though it is yet another thing that people try to blame on the DfT when it is the rail industry they should be complaining about.
 

Bertie the bus

Established Member
Joined
15 Aug 2014
Messages
3,216
No, it is the DfT
Of course it is. Everything is. The fact it is an announcement that had been used for years for pre-planned cancellations and on the day cancellations still refer to a shortage of train crew is irrelevant. It’s the government’s fault.
 

Watershed

Veteran Member
Associate Staff
Senior Fares Advisor
Joined
26 Sep 2020
Messages
16,804
Location
UK
Of course it is. Everything is. The fact it is an announcement that had been used for years for pre-planned cancellations and on the day cancellations still refer to a shortage of train crew is irrelevant. It’s the government’s fault.
It has never been used in a widespread and misleading manner like this before. He who pays the piper...

You wouldn't believe some of the stuff that's going on behind the scenes.
 

Bertie the bus

Established Member
Joined
15 Aug 2014
Messages
3,216
The reason it hasn't been so widespread is because pre-planned cancellations weren't so widespread. There used to be far more on the day cancellations instead.
 

Mitchell Hurd

On Moderation
Joined
28 Oct 2017
Messages
1,763
Today's Highland Chieftain from Inverness were cancelled and tomorrow's too Both started from Edinburgh.

So was the 09:52 Aberdeen to London service yesterday morning which started from Edinburgh. Why ScotRail couldn't accept passengers tickets I don't know because the passengers had to have a rail replacement coach which a coach wasn't suitable for a passenger.

Apparently it was they could implement. R website is now stating amended / cancelled services are "due to a shortage of train crew", which is an improvement.
 

IanXC

Emeritus Moderator
Joined
18 Dec 2009
Messages
6,615
The reason it hasn't been so widespread is because pre-planned cancellations weren't so widespread. There used to be far more on the day cancellations instead.

Also because "Due to a short-notice change to the timetable" was only added to the list of Darwin cancellation reasons in around August 2021.
 
Joined
14 Jun 2022
Messages
45
Location
Yorkshire
Actually, I stand corrected. The DfT have NOT communicated to the TOC I work for to use a particular phrase. If it was their idea, it didn't go directly to us. It went via something else like Darwin.
 

Frontera2

Member
Joined
11 Dec 2007
Messages
268
T

Really? Ok. Thank you for your input.

== Doublepost prevention - post automatically merged: ==

The DfT had absolutely nothing to do with this. How do I know? Well for I start I was heavily involved in the discussions that led to this (and a couple of other additional reasons) being added to Darwin (and other systems)

This reason was born out of the issues around the 2018 timetable change where timetables were indeed being changed at very short notice..
 

800001

Established Member
Joined
24 Oct 2015
Messages
7,401

== Doublepost prevention - post automatically merged: ==

The DfT had absolutely nothing to do with this. How do I know? Well for I start I was heavily involved in the discussions that led to this (and a couple of other additional reasons) being added to Darwin (and other systems)

This reason was born out of the issues around the 2018 timetable change where timetables were indeed being changed at very short notice..
Well maybe the people from the dft who told the TOC I work for to use that reason code then need to make it clear that they as dft did not tell the toc to use it
 

Starmill

Veteran Member
Joined
18 May 2012
Messages
27,351
Location
Bolton
I think that as originally intended this reason was for a short notice change to a timetable for no reason other than that the timetable simply had to be changed to allow it to work, or because of another reason regarding the timetable itself.

There have been a number of cases more recently where a short notice change to the timetable is an accurate description for the cancellation, but the underlying cause is either more trains than usual needing repairs at the same time, or more commonly a shortage of train drivers, train guards, or both.
 

ABB125

Established Member
Joined
23 Jul 2016
Messages
4,354
Location
University of Birmingham
I'm not a fan of this particular explanation. If only because the train isn't delayed/cancelled due to a short notice change to the timetable; it is the short notice change
 

Watershed

Veteran Member
Associate Staff
Senior Fares Advisor
Joined
26 Sep 2020
Messages
16,804
Location
UK
LNER and Northern have both responded to the FOI, seems that Mr Walker was wrong
Indeed, interesting. I wonder if Mr Walker was perhaps taking the wibble on this thread a little too seriously?

The LNER response is nevertheless interesting as it suggests that the DfT actually made a contrary instruction, namely not to use the unhelpful "short notice change to the timetable" reason.
 