Bluebell extension to Haywards Heath via Ardingly

Status
Not open for further replies.

trainmania100

Established Member
Joined
8 Nov 2015
Messages
3,040
Location
Newhaven
Read the thread.... & you will see someone saying there might be a problem with building a heavy 70 door turntable on built up Bluebell land at Horsted Keynes.

Ploughman at post 52 has very sensibly contributed to the discussion by saying it has just been done successfully on similar built up land in a tight location at
So it can be done at Horsted.
Thanks. Would be good for bluebell to have but my blunt reply was due to the fact that I couldn't see what relevance it had for this thread, the horsted to ardingly extension.

I'm guessing they posted in the wrong thread by mistake hence my confusion :lol:
If this is the right thread i wonder why they want a turntable? I thought all their locos faced north by choice . Although I may have heard wrong lol
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

32475

Member
Joined
2 Nov 2019
Messages
815
Location
Sandwich
Thanks. Would be good for bluebell to have but my blunt reply was due to the fact that I couldn't see what relevance it had for this thread, the horsted to ardingly extension.

I'm guessing they posted in the wrong thread by mistake hence my confusion :lol:
If this is the right thread i wonder why they want a turntable? I thought all their locos faced north by choice . Although I may have heard wrong lol
A turntable will allow the ability to turn steam locomotives around which is especially important for visiting tours to exit the Bluebell at East Grinstead facing north towards the London direction.
If you look at a map of the Bluebell and its location relative to the national network then this should become apparent.
 

zwk500

Veteran Member
Joined
20 Jan 2020
Messages
18,645
Location
Northampton
Read the thread.... & you will see someone saying there might be a problem with building a heavy 70 door turntable on built up Bluebell land at Horsted Keynes.

Ploughman at post 52 has very sensibly contributed to the discussion by saying it has just been done successfully on similar built up land in a tight location at
So it can be done at Horsted.
Indeed, it's possible, but if you read the RVR report it's costing them rather a lot of money.
Thanks. Would be good for bluebell to have but my blunt reply was due to the fact that I couldn't see what relevance it had for this thread, the horsted to ardingly extension.
The relevance was that somebody had suggested extending to HHE would permit turning movements, but it doesn't
If this is the right thread i wonder why they want a turntable? I thought all their locos faced north by choice . Although I may have heard wrong lol
The Bluebell does indeed prefer to have it's locos facing North as that's the prevailing gradient. However Steam locos arriving from the mainline will generally be facing south at East Grinstead, and travelling tender-first imposes a 45mph speed restriction on NR so it would be preferable if they can spin the loco. At the moment the train has to be dragged by a loco on the rear between East Grinstead and South Croydon (or very rarely it gets dragged from South Croydon to East Grinstead, so that it's facing north on departure) and turn using a route via Redhill and Guildford.

The Ardingly branch would permit specials to use the Bluebell as a stop-off on a through journey, but trains would need to work a circuit via the coast to turn.
 

Jan Mayen

Established Member
Joined
30 Sep 2020
Messages
1,362
Location
Sussex
Would it be possible for the freight trains to/from Hanson at Ardingly be able to go via Horsted Keynes?
 

trainmania100

Established Member
Joined
8 Nov 2015
Messages
3,040
Location
Newhaven
Would it be possible for the freight trains to/from Hanson at Ardingly be able to go via Horsted Keynes?
We can only wish. Somehow I don't think it's worthwhile going via 15mph to east grinstead, then up to Clapham instead of just reversing at HAyward heath then 60mph up.
 

Jan Mayen

Established Member
Joined
30 Sep 2020
Messages
1,362
Location
Sussex
We can only wish. Somehow I don't think it's worthwhile going via 15mph to east grinstead, then up to Clapham instead of just reversing at HAyward heath then 60mph up.
Indeed. Perhaps the capacity released (with the freight not using the line between Haywards Heath and South Croydon) would be worth the longer journey?
 

zwk500

Veteran Member
Joined
20 Jan 2020
Messages
18,645
Location
Northampton
There are weak bridges on the route between Oxted and East Grinstead that would restrict freight trains. Not sure how badly they'd affect it. Also, there are other freight terminals at Crawley Yard and Salfords that would still be occupying the capacity. Much easier to just line all the paths over the top.
 

MarkyT

Established Member
Joined
20 May 2012
Messages
7,611
Location
Torbay
I think if the down platform #1 loop entry turnout from the down main was relocated just over 500m further south, station side of Old Wickham Lane overbridge, then a completely independent line for Bluebell services and freight might be created all the way from Copyhold Jn into HHE station using the siding to the north of the station. and a short (circa 100m) platform created on the flat part of the station car park adjacent to the run round line parallel to platform #1, taking a row of spaces. They could call it platfrom #0, or 'B' for Bluebell - shown in green below:
1663618584603.png

The broader track layout might look a little like this:
1663624736961.png
 

LowLevel

Established Member
Joined
26 Oct 2013
Messages
8,928
Why would you want to wreck a perfectly twee heritage railway that does a good job at Horsted Keynes in particular of being a microcosm of the past by running a modern passenger service or even worse, humongous stone trains over it?

Some concessions had to be made to get to East Grinstead but for the most part it's like an ancient country branch of yesteryear, which is of course what it was preserved to be. Trying to be something else is pointless.

If you were to put it back on the national network you will lose what makes it tick.

It'll never happen, but still!
 

MarkyT

Established Member
Joined
20 May 2012
Messages
7,611
Location
Torbay
Won't that require approach control on the signal for the down loop?
Possibly. Consulting the Sectional Appendix...
1663673492424.png
...shows the down loop divergence to be a 70mph turnout today from a 90mph down main through speed, so some form of special junction aspect sequence must be present due to the difference being greater than 10mph. A flashing yellow sequence would be ok, but it might instead be a 'free yellow' sequence not involving any flashing aspects, something popular on the Southern Region in 4-aspect territory. The idea here is that the junction signal is held at single yellow and the double yellow on approach provides sufficient advance warning to slow down to the turnout speed. Even if the driver was misled in this scenario, thinking they were going straight on, the cautionary sequence is sufficient alone to control the speed within safe limits for the divergence. Operationally, the current arrangement allows a stopper to get out of the way of a closely following non-stop very quickly and has sufficient capacity on the loop to hold a second train awaiting platform #1, clear of the main. In retrospect, I'm reluctant to suggest removing all this as I can't see how you could avoid providing a less capacious and flexible arrangement with the loop turnout relocated, and it looks like the high-speed turnouts at Copyhold Jn have been renewed fairly recently anyway. I have thus revised my proposal to leave the down platform loop turnout in the existing position. The independent line into the new platform would now be provided by widening the alignment for around 600m to accommodate a lengthened down siding joining directly onto the branch, reconstructing the Old Wickham Lane overbridge. Some new crossovers between run-round line and down loop are provided north of the station. This work has potential to allow a longer freight than currently possible to accomodate in platfrom #1, running directly in from the north onto the down siding with the loco running round via platfrom #1 instead. Movements between the improved down siding and the branch would also no longer interfere with down loop traffic so this scheme could have direct benefits to BML capacity as well as allowing a Bluebell passenger service from Horsted Keynes to run into Haywards Heath station independently at times when the particular freights weren't running.

Revised proposal shown below:
1663673728726.png
 

zwk500

Veteran Member
Joined
20 Jan 2020
Messages
18,645
Location
Northampton
I have thus revised my proposal to leave the down platform loop turnout in the existing position. The independent line into the new platform would now be provided by widening the alignment for around 600m to accommodate a lengthened down siding joining directly onto the branch, reconstructing the Old Wickham Lane overbridge. Some new crossovers between run-round line and down loop are provided north of the station.
This sounds awfully expensive. I don't see how the Bluebell could possibly meet even a reasonable proportion of those costs. NR aren't going to be paying for it when the Bluebell has no real need to run to HHE. Can't see funding grants gravitating towards this proposal either. We're looking at a 20- to 30-year fundraising effort by the BRPS, to my mind.
The cutting north of HHE is very deep and very steep, with heavily wooded land on top. Reconstructing the Overbridge will require a full line block. New Crossovers will also require resignalling.
This work has potential to allow a longer freight than currently possible to accomodate in platfrom #1, running directly in from the north onto the down siding with the loco running round via platfrom #1 instead.
The longest length aggregates traffic ordinarily runs to is 450m, how long is the current standage for a runround?
Movements between the improved down siding and the branch would also no longer interfere with down loop traffic so this scheme could have direct benefits to BML capacity as well as allowing a Bluebell passenger service from Horsted Keynes to run into Haywards Heath station independently at times when the particular freights weren't running.
Thing is, you potentially don't actually need that big a gap between trains at Haywards Heath. You can follow a mainline train at minimum headway into the loop, re-occupy the platform at the minimum value (2 minutes) after it's departure, and then the only gap you need is long enough to change direction (10 minutes?), run to Copyhold Jn (2.5/3 minutes) and the Junction margin at Copyhold Jn (2/3 minutes depending on exactly how it would be defined). So all trains are running DML/P2 for about 16 minutes, which isn't actually a massive challenge on this part of the route at certain parts of the hour.
The difficulty is working out whether the gaps at Haywards Heath permit a service that offers a sensible interchange time at Horsted Keynes (it's about 15 mins between the two), such that the Main SP-EG service can still run to interchange with the London service there. It's one thing having the branch, but the BRPS has to be able to operate if effectively to make it worth spending such a vast amount of cash on putting it back.
 

MarkyT

Established Member
Joined
20 May 2012
Messages
7,611
Location
Torbay
Why would you want to wreck a perfectly twee heritage railway that does a good job at Horsted Keynes in particular of being a microcosm of the past by running a modern passenger service or even worse, humongous stone trains over it?

Some concessions had to be made to get to East Grinstead but for the most part it's like an ancient country branch of yesteryear, which is of course what it was preserved to be. Trying to be something else is pointless.

If you were to put it back on the national network you will lose what makes it tick.

It'll never happen, but still!
It would hardly need to be 'on the national network' to host occasional stone trains via East Grinstead instead of Haywards Heath. Horsted Keynes is already a significantly complex layout, rather more than any typical bucolic little branch line, and running a modern freight at low speed through the station is hardly going to spoil it. I believe The Bluebell's S&T Department has a clever scheme under development to only require one signalbox, at Kingscote (with its electric miniature lever frame), to be open to allow both NR interfaces and movements between them at quiet times when no Bluebell passenger or departmental services are running.
This sounds awfully expensive. I don't see how the Bluebell could possibly meet even a reasonable proportion of those costs. NR aren't going to be paying for it when the Bluebell has no real need to run to HHE. Can't see funding grants gravitating towards this proposal either. We're looking at a 20- to 30-year fundraising effort by the BRPS, to my mind.
The cutting north of HHE is very deep and very steep, with heavily wooded land on top. Reconstructing the Overbridge will require a full line block. New Crossovers will also require resignalling.
Signalling alterations rather than wholesale replacement I'd have thought, or the work might have to wait until a broader signalling scheme was scheduled in the area for other reasons. I wonder if the additional line might be pushed through the side span of the existing overbridge if it's still this structure illustrated in this 1949 aerial image:
1663677761717.png
The longest length aggregates traffic ordinarily runs to is 450m, how long is the current standage for a runround?
Looks like around the same as a 12-car, i.e 240m. My scheme could probably accomodate the full 450m, with the wagons offline in the siding during runround, still with a fast divergence from the main.
The difficulty is working out whether the gaps at Haywards Heath permit a service that offers a sensible interchange time at Horsted Keynes (it's about 15 mins between the two), such that the Main SP-EG service can still run to interchange with the London service there. It's one thing having the branch, but the BRPS has to be able to operate if effectively to make it worth spending such a vast amount of cash on putting it back.
Fully agree engineering and operational analyses need to be thorough.
 
Last edited:

zwk500

Veteran Member
Joined
20 Jan 2020
Messages
18,645
Location
Northampton
Stone trains running via East Grinstead can be pretty firmly ruled out. You'd need competent Signalling staff, driver knowledge, ground frame operators, a person to return the token, route clearance from Ardingly to Oxted (many weak bridges north of East Grinstead) and paths available to run in.
There's no commercial arrangement that would make sense to both parties.

== Doublepost prevention - post automatically merged: ==

It would hardly need to be 'on the national network' to host occasional stone trains via East Grinstead instead of Haywards Heath. Horsted Keynes is already a significantly complex layout, rather more than any typical bucolic little branch line, and running a modern freight at low speed through the station is hardly going to spoil it.
Agree, it would rarely be more than 1 train a week anyway so 99% of visitors will be utterly unaware.
I believe The Bluebell's S&T Department has a clever scheme under development to only require one signalbox, at Kingscote (with its electric miniature lever frame), to be open to allow both NR interfaces and movements between them at quiet times when no Bluebell passenger or departmental services are running.
My understanding was that the plan involved Kingscote being able to control the East Grinstead area (and interchange with NR) using TCB and removing the need for tokens. AIUI Kingscote has no ability, planned or theoretical, to control any part of Horsted Keynes. Separately, there is the ability for Sheffield Park and Kingscote to use 'Long Section' working and switch out Horsted Keynes box. If this is being used, then there is no access to the Ardingly Branch as the junction cannot be changed with HK Box switched out. Provision was made for Ardingly in the HK Resignalling, but I'm not sure if that was just for a Section & Home signal and a Key Token instrument, or if the branch can be run without a token. If it needs a token instrument at Ardingly, that's yet more faff.
There's also the signalling of the existing Ardingly branch to consider, which is One Train no Staff. Simplest option is to put a 'Stop and Telephone' board at the network boundary, but regular passenger moves may need a bit more safety buffer than that.
More importantly, discussion of how through trains would operate is probably veering into the Speculative section, so I'll try to focus on the actual proposal from now on!
Signalling alterations rather than wholesale replacement I'd have thought, or the work might have to wait until a broader signalling scheme was scheduled in the area for other reasons. I wonder if the additional line might be pushed through the side span of the existing overbridge if it's still this structure illustrated in this 1949 aerial image:
As I've been told, there's no such thing as a small signalling change. Pushing through the existing bridge may be possible but it'll need a retaining wall and getting access for that wouldn't come cheap.
Looks like around the same as a 12-car, i.e 240m. My scheme could probably accomodate the full 450m, with the wagons offline in the siding during runround, still with a fast divergence from the main.
I make it 460m from the clearance point of the Shunt Neck/Runround (the platform signal is cleared towards the shunt neck and the train drawn forward, btw) to the foot crossing at the north end of the platform. Seems like limited value to NR making it longer.
 
Last edited:

MarkyT

Established Member
Joined
20 May 2012
Messages
7,611
Location
Torbay
As I've been told, there's no such thing as a small signalling change.
I can't disagree! This may still be a geographical interlocking area if that element hasn't been renewed more recently. If you can get sufficient refurbished 'sets', the design and changeover can be a little more swift than with other relay based tech. They were planning to do this for the preliminary stages of CARS I believe.
I make it 460m from the clearance point of the Shunt Neck/Runround (the platform signal is cleared towards the shunt neck and the train drawn forward, btw) to the foot crossing at the north end of the platform. Seems like limited value to NR making it longer.
Ok that makes sense. In which case my new right hand x-over isn't required at all and the existing one nearer the platform would suffice. The benefit of being able to run straight into and out of the siding via a new left-hand crossover might still be worth looking into however so the wagons can be left there while the loco runs round between trains via platform #1. That work might be pursued in advance with the widening to create the independant connection to the branch, carried out later when stakeholders can build a case and raise the finance.

I'll think about further detailed signalling implications on the heritage line later, but I concur the current one train without train staff method over any part of the branch won't be acceptable, especially considering the section would become double ended with a mix of freight and passenger, and the possibility of crippled wagons being left at the quarry end. Converting it to a form of tokenless block with a traincrew confirmation of clearance at the other end and some locked trapping of the sidings might be an option. A new token section from Horstead Keynes to Copyhold would be my suggestion with remote instrument(s) at HHE that release the approriate NR signals towards the branch. A GF could then be provided at the quarry entrance, released by the section token. An additional remote token instrument at the quarry could allow lock-in while other trains use the single line (power and communications implications). A remote token arrangement at HHE might be arranged such that a token might be available to crew even if the Bluebell SB wasn't open, for a trip to the quarry.
 

zwk500

Veteran Member
Joined
20 Jan 2020
Messages
18,645
Location
Northampton
I can't disagree! This may still be a geographical interlocking area if that element hasn't been renewed more recently. If you can get sufficient refurbished 'sets', the design and changeover can be a little more swift than with other relay based tech. They were planning to do this for the preliminary stages of CARS I believe.
I think there's a plan to move it into the ROC in the near future, not sure how firm it is. (I heard talk about Bi-Di on all 4 tracks, etc but never a date).
Ok that makes sense. In which case my new right hand x-over isn't required at all and the existing one nearer the platform would suffice. The benefit of being able to run straight into and out of the siding via a new left-hand crossover might still be worth looking into however so the wagons can be left there while the loco runs round between trains via platform #1. That work might be pursued in advance with the widening to create the independant connection to the branch, carried out later when stakeholders can build a case and raise the finance.
Agreed. Being able to stable the wagons in the runround loop would be a massive boost to the flexibility of the freight paths. However for less than 3 trains a week it's difficult to make the case for even a comparatively small signalling intervention.
I'll think about further detailed signalling implications on the heritage line later, but I concur the current one train without train staff method over any part of the branch won't be acceptable, especially considering the section would become double ended with a mix of freight and passenger, and the possibility of crippled wagons being left at the quarry end. Converting it to a form of tokenless block with a traincrew confirmation of clearance at the other end and some locked trapping of the sidings might be an option. A new token section from Horstead Keynes to Copyhold would be my suggestion with remote instrument(s) at HHE that release the approriate NR signals towards the branch. A GF could then be provided at the quarry entrance, released by the section token. An additional remote token instrument at the quarry could allow lock-in while other trains use the single line (power and communications implications). A remote token arrangement at HHE might be arranged such that a token might be available to crew even if the Bluebell SB wasn't open, for a trip to the quarry.
It all depends on what the Bluebell think they need to run. If they're going to use it for a couple of trains a day a few days a year, then a Ground frame at the yard and Stop board at the NR/BRPS boundary may be enough. If, however, they want to run a regular shuttle all through the day every summer weekend then it'd need something a bit more. It also depends on whether the Bluebell plan to put anything in at Ardingly to allow self-contained operations for any reason.
 

MarkyT

Established Member
Joined
20 May 2012
Messages
7,611
Location
Torbay
I think there's a plan to move it into the ROC in the near future, not sure how firm it is. (I heard talk about Bi-Di on all 4 tracks, etc but never a date).
Could be a control transfer to ROC workstations, with existing interlockings and trackside equipment retained, at least initially.
Agreed. Being able to stable the wagons in the runround loop would be a massive boost to the flexibility of the freight paths. However for less than 3 trains a week it's difficult to make the case for even a comparatively small signalling intervention.
I wonder if an easier task planning the freight here might lead to an increase in traffic.

Here's my layout diagram again, with more detail and suggesting a staged approach. Shows a route set for a down freight arrival:
1663781021442.png
 

zwk500

Veteran Member
Joined
20 Jan 2020
Messages
18,645
Location
Northampton
I'll think about further detailed signalling implications on the heritage line later
Having just poked around the Bluebell's website: https://www.bluebell-railway.com/brps/signals/ it appears that they are intending to use Electric Train Staff working between Horsted Keynes and Ardingly. If they were intending to run only sporadic trains through to HHE, then it could be made to work with Stop boards and 'Stop and Telephone' instructions to confirm Train Arrived Complete and track clear to the relevant signallers at each end. You'd need only minimal intervention at Ardingly sidings to fit the turnout (and possibly a pair of trap points), maybe not even an FPL (if they clip and scotch each time). This would even work for an all-day service, although they'd probably need to make sure there's no freight using the sidings that day.
Could be a control transfer to ROC workstations, with existing interlockings and trackside equipment retained, at least initially.
Almost certainly that's the first step
I wonder if an easier task planning the freight here might lead to an increase in traffic.
No, the bottlenecks elsewhere wouldn't be helped. The total number of paths wouldn't change, but it would make what does run more flexible to avoid delay.
 

MarkyT

Established Member
Joined
20 May 2012
Messages
7,611
Location
Torbay
Having just poked around the Bluebell's website: https://www.bluebell-railway.com/brps/signals/ it appears that they are intending to use Electric Train Staff working between Horsted Keynes and Ardingly. If they were intending to run only sporadic trains through to HHE, then it could be made to work with Stop boards and 'Stop and Telephone' instructions to confirm Train Arrived Complete and track clear to the relevant signallers at each end. You'd need only minimal intervention at Ardingly sidings to fit the turnout (and possibly a pair of trap points), maybe not even an FPL (if they clip and scotch each time). This would even work for an all-day service, although they'd probably need to make sure there's no freight using the sidings that day.
I wouldn't like to see a permanent installation relying on clipping and padlocking for passenger operation. I'd put in a small mechanical ground frame at the entrance to the quarry, released by the train staff. For freight to the quarry, the staff instrument at HHE could operate as a remote, without release by the signaller at Horsted Keynes, so as long as the section was left clear a staff might be withdrawn for an out ad back trip without a Bluebell signaller being on duty at Horsted Keynes. Alternatively, a separate 'short section staff' might be provided at HHE, that requires the normal staff system to be in phase, and once withdrawn from its own instrument (a simple Annetts key release device) at HHE would lock out the normal staff system until the short section staff is returned to its instrument.
 

zwk500

Veteran Member
Joined
20 Jan 2020
Messages
18,645
Location
Northampton
I wouldn't like to see a permanent installation relying on clipping and padlocking for passenger operation. I'd put in a small mechanical ground frame at the entrance to the quarry, released by the train staff. For freight to the quarry, the staff instrument at HHE could operate as a remote, without release by the signaller at Horsted Keynes, so as long as the section was left clear a staff might be withdrawn for an out ad back trip without a Bluebell signaller being on duty at Horsted Keynes. Alternatively, a separate 'short section staff' might be provided at HHE, that requires the normal staff system to be in phase, and once withdrawn from its own instrument (a simple Annetts key release device) at HHE would lock out the normal staff system until the short section staff is returned to its instrument.
I don't see why you'd go back to staff operation at HHE, instead of just fitting axle counters if you were that concerned. However I think a GF or Switch panel with staff to advise Train Arrived Complete to Three Bridges or HK would be sufficient. The switching in/out arrangements and potential failure of the staff instrument trapping a freight at HHE would be quite complicated problems to resolve.

A plunger/phone at Ardingly for staff to give TAC, Request the GF Release and advise TRTS to Three Bridges would be enough considering the potential usage. The BRPS staff would only cover up to the Boundary Gate. I might try and knock up a diagram if I have time this evening.
 

STEVIEBOY1

Established Member
Joined
31 Jul 2010
Messages
4,001
Could be a control transfer to ROC workstations, with existing interlockings and trackside equipment retained, at least initially.

I wonder if an easier task planning the freight here might lead to an increase in traffic.

Here's my layout diagram again, with more detail and suggesting a staged approach. Shows a route set for a down freight arrival:
View attachment 121050
That is an interesting diagram. Thank you.
 

MarkyT

Established Member
Joined
20 May 2012
Messages
7,611
Location
Torbay
I don't see why you'd go back to staff operation at HHE, instead of just fitting axle counters if you were that concerned. However I think a GF or Switch panel with staff to advise Train Arrived Complete to Three Bridges or HK would be sufficient. The switching in/out arrangements and potential failure of the staff instrument trapping a freight at HHE would be quite complicated problems to resolve.

A plunger/phone at Ardingly for staff to give TAC, Request the GF Release and advise TRTS to Three Bridges would be enough considering the potential usage. The BRPS staff would only cover up to the Boundary Gate. I might try and knock up a diagram if I have time this evening.
It would be less trouble if the trapped freight was able to sit on the runround loop instead of in platform 1!

There are examples of staff/token release of NR signals by heritage rail block systems. A fairly recent installation at the West Somerset Railway interface incorporates this. There are signal release instruments (presumably Annetts key type) at Silk Mill relay room and at Taunton station for this. They are activated by inserting and turning a key attached to a token from the WSR's NSTR installation. Another recent example is at Wareham for the Swanage Railway, where two remote key token instrument are housed on the NR platforms and the action of withdrawing a token releases a route towards the branch. An older installation is at Totnes for the South Devon Railway, where a special staff release instrument is housed in a locked cabinet at the NR station. This just predates the modern colour light signalling, being installed in the 1980s, when the steam railway first started operating regularly into the BR station. The system was retained and incorporated into the new signalling when Exeter PSB took over. The single line staff, with an Annetts key attached to one end, is inserted and turned to give a 'one shot' signal release towards the branch. At one time the staff applied to the entire branch to Buckfastleigh, but now it just applies to the short transfer line as far as the more recently commissioned signalbox at Ashburton Junction (AJ), where electric key token working commences. The staff is kept normally in a release instrument in AJ Signalbox and for a transfer movement its withdrawal releases the SDR signal reading towards NR. When an incoming movement is expected a member of SDR staff goes to meet the train at the mainline station and runs the transfer line staff key through the instrument to release the NR signal.
 

JohnElliott

Member
Joined
15 Sep 2014
Messages
275
Nope, Though it can provide ETH (as any ETH fitted diesel can), you would need the services of a 33/1 to provide Push Pull Working.
Since all 33/1s started out as 33/0s, it would suggest that the Bluebell could do the same conversion to theirs if it became necessary.
 

fgwrich

Established Member
Joined
15 Apr 2009
Messages
10,654
Location
Hampshire
Since all 33/1s started out as 33/0s, it would suggest that the Bluebell could do the same conversion to theirs if it became necessary.
They could, but is it really time / cost effective? For example, we are talking about a fairly complex conversion carried out around 1965. Are the components still readily available? Would the Bluebell loco owners want to heavily modify a loco they are already working their way through the restoration of, only to hack it around again? You’d be simpler off speaking to either Nemesis and re-hiring 33103 or any of the other 33/1 owners. Heck, the NRM owned one at the GC could do with a new home or some considerable TLC!
 

paul1609

Established Member
Joined
28 Jan 2006
Messages
7,992
Location
K
They could, but is it really time / cost effective? For example, we are talking about a fairly complex conversion carried out around 1965. Are the components still readily available? Would the Bluebell loco owners want to heavily modify a loco they are already working their way through the restoration of, only to hack it around again? You’d be simpler off speaking to either Nemesis and re-hiring 33103 or any of the other 33/1 owners. Heck, the NRM owned one at the GC could do with a new home or some considerable TLC!
Theres no way regular operation of an EMU would attract other than a very niche band of enthusiasts numbered on one hand Id suggest. The whole operation isnt going to cover its costs.
95%+ of visitors to heritage railways are familys arriving by car. The <5% balance are amply provided for by the station at East Grinstead and the bus from Haywards Heath anything else is pure fantasy.
 

Ashley Hill

Established Member
Joined
8 Dec 2019
Messages
5,680
Location
The West Country
Theres no way regular operation of an EMU would attract other than a very niche band of enthusiasts
Then what’s the point in preserving them? Yes they get dragged around occasionally but some sit quietly in sidings slowly deteriorating. To present an operational one in an authentic setting on high days and holidays must surely be an attraction?
 

Sm5

Member
Joined
21 Oct 2016
Messages
1,013
The relevance was that somebody had suggested extending to HHE would permit turning movements, but it doesn't

The Bluebell does indeed prefer to have it's locos facing North as that's the prevailing gradient. However Steam locos arriving from the mainline will generally be facing south at East Grinstead, and travelling tender-first imposes a 45mph speed restriction on NR so it would be preferable if they can spin the loco. At the moment the train has to be dragged by a loco on the rear between East Grinstead and South Croydon (or very rarely it gets dragged from South Croydon to East Grinstead, so that it's facing north on departure) and turn using a route via Redhill and Guildford.
when was the last steam hauled railtour into the Bluebell ?

i’m not sure the value of a turntable is there, not even for lets say some fanciful turning of NR tamping machines.. they can use Selhurst, which is where stuff would be coming from anyway.

The line itself is mostly straight, so I doubt even the stock needs turning.

Extending to Haywards Heath has merit from South coast holiday makers on a day trip. But lets face it, this is about extending a railway to increase its attractiveness… its not about money.. none of these railways are about money, thats why Beeching closed them.
 

zwk500

Veteran Member
Joined
20 Jan 2020
Messages
18,645
Location
Northampton
when was the last steam hauled railtour into the Bluebell ?
No idea post-covid, but there used to be 2 or 3 a year, plus loco moves when I used to plan them.
i’m not sure the value of a turntable is there, not even for lets say some fanciful turning of NR tamping machines.. they can use Selhurst, which is where stuff would be coming from anyway.
You wouldn't turn a tamper, and Selhurst is a pain in the neck to use as the third side of the triangle is part of the depot. The value of turning it would be to enable a departure directly back north to increase the range of potential destinations for tours. A steam loco runnning tender-first is limited to 45mph, running chimney first it can go to 60 or 75mph (varies between locos). At the moment to get the loco facing North involves reversing at South Croydon and running via Redhill and Guildford, which takes a long time.
Extending to Haywards Heath has merit from South coast holiday makers on a day trip. But lets face it, this is about extending a railway to increase its attractiveness… its not about money.. none of these railways are about money, thats why Beeching closed them.
The lines are absolutely about money now. They're tourist attractions, and if they don't make money they shut down.
 

Sm5

Member
Joined
21 Oct 2016
Messages
1,013
No idea post-covid, but there used to be 2 or 3 a year, plus loco moves when I used to plan them.

You wouldn't turn a tamper, and Selhurst is a pain in the neck to use as the third side of the triangle is part of the depot. The value of turning it would be to enable a departure directly back north to increase the range of potential destinations for tours. A steam loco runnning tender-first is limited to 45mph, running chimney first it can go to 60 or 75mph (varies between locos). At the moment to get the loco facing North involves reversing at South Croydon and running via Redhill and Guildford, which takes a long time.

so no justification for a turntable at all really, reverse moves can run out of hours easily enough, 2 or 3 times a year.
The lines are absolutely about money now. They're tourist attractions, and if they don't make money they shut down.
Show me one without volunteers to make it happen ?

But yes, as I said they are tourist attractions, and tourists goto the seaside.. but rightnow a visit to Bluebell means a trek uo to South London and back south.. perhaps 4 hours end to end travel just to reach it…. or a taking the car… or do a day trip to some other tourist place. Haywards Heath puts it in day trip from the seaside territory… and a Steam loco in the platform as the Brighton crowd roll past is the best free advertising.
 
Last edited:

steamybrian

Established Member
Joined
26 Nov 2010
Messages
2,003
Location
Kent
Show me one without volunteers to make it happen ?

But yes, as I said they are tourist attractions, and tourists goto the seaside.. but rightnow a visit to Bluebell means a trek uo to South London and back south.. perhaps 4 hours end to end travel just to reach it…. or a taking the car… or do a day trip to some other tourist place. Haywards Heath puts it in day trip from the seaside territory… and a Steam loco in the platform as the Brighton crowd roll past is the best free advertising.
I believe there are several heritage railways without volunteers possibly (I stand to be corrected..!)- Snowdon Mountain Railway, Paignton and Kingswear Railway, Vale of Rheidol.

From Brighton to the Bluebell Railway by public transport I recommend.... Brighton - Three Bridges by rail then by frequent bus (from outside the station ) to East Grinstead station (journey time about 25 minutes). Far quicker then rail via East Croydon..
 