After months of hard work, London Underground (LU) has successfully completed station Trial Operations.
This means we’ve met the requirements of the Sub Surface regulations, safety standards and the Safety Certificate requirements for working with other railway companies in the 400+ exercises we undertook for Trial Operations at LU stations
After each exercise we listened to feedback and worked on resolving all actions raised.
Additionally, we’ve completed all Safety, Health & Environment (SHE) Verification activities.
Alongside MTR-Elizabeth Line and Rail for London Infrastructure (RfLI), LU also took part in 35 joint Trial Operations exercises.
Whitechapel station
66 planned Trial Operations undertaken
Eight joint Trial Operations exercises
64 evacuation scenarios
One full station evacuation