No progress?25/11/14
A $US11.97 billion assignment to build Nigeria's new 'coastal railway' is said to be China's largest single overseas contract project to date. China Railway Construction Corporation Limited (CRCC), a large state-owned entity, is to build the entirely new west-east railway from Lagos to Calabar, about 1,402km.
Still unfinished?19/11/15
The China Civil Engineering Construction Corporation (CCECC) began work on phase 1 of the $US2.5 billion Lagos light rail project in 2010. Running from Marina to Okokomaiko, with 13 stations, it was hoped initially to have the 27.5km “Blue Line” working in 2014, but by the end of 2015 it is still unfinished.
But they have bought two long disused Talgo trainsets for the Red Line. Not ideal for commuter services some have suggested.The governor of Lagos State, Nigeria is visiting Wisconsin this week to buy two trainsets that were originally built for the state of Wisconsin.
"They'll actually be in service -- serving people and providing a new transit option in another community," said Acting Mayor Cavalier Johnson during a news conference on Tuesday, Jan. 18.
The Spanish company Talgo, which has a plant at 27th and Townsend in Milwaukee's Century City business park, manufactured the trains 11 years ago.
Abandoned.30/5/17
NIGERIA: A consortium led by GE of the USA has been confirmed by the government as preferred bidder for a concession to rehabilitate, finance and operate the 3 505 km Nigeria Railway Corp network, GE announced on May 25.
What on earth is that loco!? Looks like a Finnish Pendolino.
April 2019
China Civil Engineering Construction Corp has awarded CRRC Qishuyan a contract to supply:
The first batch of 10 of the 1,435 mm gauge diesel locomotives is scheduled to be delivered in October for Abuja – Kaduna and Lagos and Ibadan lines.
- four NDJ3N diesel multiple-units (2 power cars and 7 intermediate vehicles each),
- two DF7GN shunting locomotives,
- six DF11GN passenger locomotives and
- nine DF8BN freight locomotives.
Egypt / Sudan are proposing a link between their systems. That would just leave Wau in South Sudan to Uganda, probably near Gulu. Plus the re-instatement of some other long out of use lines.Will China gradually build a Cape to Cairo railway?
Nigeria theoretically has railways covering 9 states with a total mileage of 3,505 kilometers, but due to disrepair and chaotic management, the only ones that can really carry out commercial operations have long been only from the economic capital Lagos to the neighboring Ijoko City, Ogun State, a section of railway with a length of about 30 kilometers. The Lagos-Kano railway passes through the two major ethnic groups of Yoruba and Hausa and many conflicting federal subjects. Not only is the project complicated and non-technical factors Many, coupled with the rampant corruption in Nigeria, so although the project has been proposed for nearly 10 years, it has been delayed. This can't help but remind me last year that the new government suspended the contract signed two years ago with CCECC (China Civil Engineering Corporation) for the reconstruction of the railway, worth about 8.5 billion US dollars. The economic capital of Lagos is directly connected to the northern commercial town of Kano. CCECC is responsible for "design, construction and maintenance", and CCECC has won a special loan of 1 billion US dollars from the Chinese government for the Nigeria side. However, the new government believes that former President Obasanjo has "greatly engaged in construction" and "has a lot of joy", and the contract signed by him needs to be "reconsidered". In fact, in the past two years, the project has received about 250 million US dollars, much less than the contract. In this African country with poor materials, reliance on imported raw materials, widespread corruption, lack of funds, and lax management, the difficulty can be imagined. In an interview with the media, a spokesperson for CCECC said that "it has done its best and achieved something." , did not directly give a reasonable explanation of the progress. What happened to the contract after that, I don't know. The only thing that can be imagined is that it is not easy for our Chinese compatriots to be abroad, can imagine the difficulties in carrying out engineering construction in this country. Posted on 2020-02-24 15:01
I found an interesting post by a Chinese businessman in 2020, the original text is in Chinese, Google translate was used to convert to English.
Understatement of the year!The only thing that can be imagined is that it is not easy for our Chinese compatriots to be abroad, can imagine the difficulties in carrying out engineering construction in this country.
Acknowledgements
FMoT [Federal Ministry of Transportation] wishes to thank GOD ALMIGHTY and then the regulators at the Federal Ministry of Environment, (FMEnv), Rivers, Abia, Enugu, Ebonyi, Benue, Nasarawa, Kaduna, Plateau, Bauchi, Gombe, Yobe, and Borno Ministries of Environment and all the 65 affected Local Government Areas and various other institutional stakeholders for their various supports for the ESIA of this project.
We are also grateful to the Traditional rulers, Council of chiefs, women, Youth, and all who were of assistance to the success of this study.