The final trial operation test is this weekend. I wouldn't expect the line to be open before the results of the trial operations (not everything went entirely to plan) are turned into new operational policy. Dates are getting thrown around internally, but I genuinely can't remember which date it was I heard!
One of the posts further up mentioned some time ago that the start of a full timetable was 6th March which would fit with that. Andy Byford has said in the past that there will be 2 weeks of full timetable run prior to opening. That might also allow time at a couple of weekends to rerun the 24tph test and the test across the transitions to GWML and GEML with turn rounds at Acton and Stratford if they wanted. I'm not sure if those tests need to be repeated though.