RAIB are investingating a near-miss at Forestry UWC, on the Breckland line.


Edited to remove separate incident in Scotland.


At about 06:05 hrs on 18 September 2021, a near miss occurred between a passenger train and two cars at Forestry user worked crossing, between Thetford and Brandon. No injuries or damage resulted from the incident.
 
Last edited by a moderator:
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

John Webb

Established Member
Joined
5 Jun 2010
Messages
3,787
Location
St Albans
RAIB Safety Digest issued on 13th December 2021 - see this link.
Important safety messages
This incident highlights:
• the importance of Network Rail continuing to focus management attention on reducing the risks associated with signallers’ decisions about granting permission for users to cross at user worked crossings with telephones, particularly in ensuring that signallers are provided with, and make use of, suitable information on which to base these decisions
• how signallers’ awareness of the position of trains can be influenced by distractions, with potential effects on their safety critical decisions
 

John Webb

Established Member
Joined
5 Jun 2010
Messages
3,787
Location
St Albans
I don't know the line at all, but the RAIB speak of a 'Track Circuit' with a length of 5.64 miles. Is this actually a TC (albeit made up of several shorter ones) or is this based on Axle Counters?
 

TheEdge

Established Member
Joined
29 Nov 2012
Messages
4,498
Location
Norwich
It is actually axle counters signalling but I know around Anglia NR have been adding overlay track circuits for crossing detection. Its definitely been done on the East Suffolk, not sure about the Breckland line.
 

w0033944

Member
Joined
23 Jul 2011
Messages
555
Location
Norfolk
BBC report:
https://www.bbc.co.uk/news/uk-engla...OIlCvWgZN1SaKN4DbCRD9QsCyvz_eXDamE7RDrvI61oDI

Norwich to Stansted train in 75mph 'near miss' with two cars​

Published
22 hours ago


Two cars crossing the rail line
Image source, Greater Anglia
Image caption,
CCTV footage shows two cars either side of the level crossing between Thetford and Brandon at the time of the near miss
A train travelling at nearly 75mph (121km/h) almost hit two cars at a level crossing, a safety report said.
The passenger train was involved in the "near miss" between Thetford and Brandon, on the Norfolk-Suffolk border.
The motorists called on the phone at the forestry user level crossing asking to cross.
The Rail Accident Investigation Branch (RAIB) said a signaller "granted permission... without realising [a train] was approaching".
The train "came close to striking two cars", that were inside the rail boundary but clear of the line, according to the RAIB report.
The Greater Anglia service had been travelling between Norwich and Stansted Airport, Essex.
Inspectors said the motorists had told the signaller that, once gates were opened and closed, it would take them two minutes to cross at about 06:05 BST on 18 September.
The signaller checked his Thetford workstation of five screens, which gave a "schematic layout" of the rail lines and gave permission, the RAIB said.
However, "the lengths of the sections on the screens are not representative of their actual length in the real world," it said.

Not enough information​

The signaller thought the train had only just left Thetford station.
But investigators found the train was actually at the other end of the circuit and it reached the level crossing just 44 seconds after the motorists had called.
The signaller had reported for duty well before his 06:00 start and was given a handover before his shift.
The RAIB said his "continuing focus on understanding the wider situation on the workstation may have affected his perception of the train's position".
"In addition, the long track circuit section between Thetford station and forestry user worked crossing did not... lead to the signaller having enough information about the train's position to allow him to make an informed decision," it added.
The report noted similar cases, including a tractor crash near Thetford in 2016 had led to Network Rail installing two extra screens for the Thetford circuit.
Network Rail is also to introduce a new policy to improve signallers' information, but this will not happen until next year.
It had also been ordered to improve safety measures at level crossings, but Network Rail had said these did not apply to forestry user crossings.
Network Rail said it welcomed the report's findings.
Ellie Burrows, its route director for Anglia, said: "Safety is our top priority and we have already begun work to improve safety at this crossing, including additional training and better processes to help signallers make safe decisions when allowing someone to cross.
"We are also looking at how technology can be used to further improve safety at this location."
 