The timescales involved just make this year seem unlikely. A fair number of staff are going to need to be trained before the units are introduced, unless it is just a very limited introduction.
Yes, I'd have thought a very limited introduction would be the most likely one, say a few trips on 2-3 days a week. That's been the pattern with previous new stock introductions.
Yes, I'd have thought a very limited introduction would be the most likely one, say a few trips on 2-3 days a week. That's been the pattern with previous new stock introductions.
My guess would be that it's been such a long build-up for these units that they probably just want at least some of them in service as soon as possible, just to say that they have entered service (plus it would help to fill the 707 gap). So I'd say they might want to get a few of them ready and in service for the short-term and then focus on the proper introduction of the units and replacement of older ones.
Realtime Trains is an independent source of live realtime running information for the Great British railway network.
www.realtimetrains.co.uk
All the doors had a big 'do not board' thing behind them. So seems quite a lot running around, hopefully their fault free mileage will soon be reached.
I passed Feltham depot twice yesterday and 006 was there as usual, with headlights, interior and destination display lit up. Presumably ongoing staff familiarisation?
== Doublepost prevention - post automatically merged: ==
My guess would be that it's been such a long build-up for these units that they probably just want at least some of them in service as soon as possible, just to say that they have entered service (plus it would help to fill the 707 gap). So I'd say they might want to get a few of them ready and in service for the short-term and then focus on the proper introduction of the units and replacement of older ones.
It was certainly the case with the 458s, Desiros and 707s. Get a unit in service ASAP on very limited workings, with full introduction following later.
I passed Feltham depot twice yesterday and 006 was there as usual, with headlights, interior and destination display lit up. Presumably ongoing staff familiarisation?
== Doublepost prevention - post automatically merged: ==
It was certainly the case with the 458s, Desiros and 707s. Get a unit in service ASAP on very limited workings, with full introduction following later.
There are issues with cab etc. modifications, software and fault free mileage...
Recent stock introductions have shown that a (surprisingly) large number of units are needed initial just to get a few in service - effectively the base layer of a large pyramid (e.g. a large pool is needed for a continuous driver training programme).
Enough to cover for 707, 458 and the worst 455/456 would be ~50% of the 701 fleet. But half level (~20-25%) that would be minimum initial target to remove the pressures.
Probably not much point aiming for in passenger service till the cab mods are complete on most units as this enlarges the pool of units to find that could potentially obtain for fault free mileage quickest.
There are issues with cab etc. modifications, software and fault free mileage...
Recent stock introductions have shown that a (surprisingly) large number of units are needed initial just to get a few in service - effectively the base layer of a large pyramid (e.g. a large pool is needed for a continuous driver training programme).
Enough to cover for 707, 458 and the worst 455/456 would be ~50% of the 701 fleet. But half level (~20-25%) that would be minimum initial target to remove the pressures.
Probably not much point aiming for in passenger service till the cab mods are complete on most units as this enlarges the pool of units to find that could potentially obtain for fault free mileage quickest.
Realtime Trains is an independent source of live realtime running information for the Great British railway network.
www.realtimetrains.co.uk
All the doors had a big 'do not board' thing behind them. So seems quite a lot running around, hopefully their fault free mileage will soon be reached.
I saw 031 at Waterloo on 17th August with Weymouth displayed as destination. I saw the same train a bit later (at 1034) pass Surbiton. As someone who hasn't been following the 701 saga I actually thought it was in service.
There have been 701 ramps at most stations if not all that the 701s will potentially call at for many months, possibly close to a year. I'd be surprised if those had only just appeared. Most have been marked with do not use, especially at Waterloo/very busy stations.
I saw 031 at Waterloo on 17th August with Weymouth displayed as destination. I saw the same train a bit later (at 1034) pass Surbiton. As someone who hasn't been following the 701 saga I actually thought it was in service.
Weymouth? That's a massive clue that it wasn't in service. I strongly suspect that 701s (10car) won't be allowed to go there due to excessive current draw when they pass a 444 going the other way. (or worse still another 701 (10)
Weymouth? That's a massive clue that it wasn't in service. I strongly suspect that 701s (10car) won't be allowed to go there due to excessive current draw when they pass a 444 going the other way. (or worse still another 701 (10)
Quite the contrary, in fact. A 701 (10 car) was tested on several occasions in a possession between Wareham and Weymouth, and with a 444 going the other way past it.
So it's not so much that the 701s won't be able to go down there in service, more that they just aren't intended to.
Quite the contrary, in fact. A 701 (10 car) was tested on several occasions in a possession between Wareham and Weymouth, and with a 444 going the other way past it.
So it's not so much that the 701s won't be able to go down there in service, more that they just aren't intended to.
No, in the series of Press releases in March 2017 when franchise was awarded, the new trains were due to enter service from Autumn 2018 and be all in service by end of 2019.
So all should have been in service, and everyone should have been fully trained pre Covid, the first trains are currently over 1000 days late in starting to enter service.
Providing a link to DfT Press Release, which rather demonstrates that SWR haven’t delivered on list of improvements that were promised.