The Railway Magazine has reported that these two units have had large sections of their bodysides removed for analysis following the cracking issues. It suggests that repairs to these vehicles may well be unviable necessitating new vehicles.
Which vehicles in each set are affected? And what has been cut away?
Where are the two trains currently?
Thanks.
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

JonathanH

Veteran Member
Joined
29 May 2011
Messages
23,406
The Railway Magazine has reported that these two units have had large sections of their bodysides removed for analysis following the cracking issues. It suggests that repairs to these vehicles may well be unviable necessitating new vehicles.
Which vehicles in each set are affected? And what has been cut away?
Where are the two trains currently?
Thanks.
802005 is back in service.

800026 isn't.
 

JN114

Established Member
Joined
28 Jun 2005
Messages
3,530
It shouldn’t be in service if it’s had large sections removed from the bodywork...

Only if one presumes the “reports” in the magazines were accurate.

It is out in traffic.
 

DanNCL

Established Member
Joined
17 Jul 2017
Messages
5,123
Location
County Durham
I should add that two LNER units that had also been reported as too badly cracked to return to service with the bulk of the fleet back in May, 800104 and 800105, have also made appearances in service in the last few weeks. In the case of 800105, this unit was dumped in Tyne Yard for the majority of June as a result. As there is no fix for these cracks, what has changed that these units have all of a sudden gone from being "too badly cracked" to being fit for service without any remedial work done whatsoever?
 

pdeaves

Established Member
Joined
14 Sep 2014
Messages
5,932
Location
Gateway to the South West
As there is no fix for these cracks
Is there no fix? Like plastering a cracked house wall, they dig out material and replace it, I understand. The issue is more how to prevent cracks from propagating. Until that's understood, there is a super regular checking process.
 

DanNCL

Established Member
Joined
17 Jul 2017
Messages
5,123
Location
County Durham
Is there no fix? Like plastering a cracked house wall, they dig out material and replace it, I understand. The issue is more how to prevent cracks from propagating. Until that's understood, there is a super regular checking process.
Not at present, a fix is yet to be developed.
 

JN114

Established Member
Joined
28 Jun 2005
Messages
3,530
I should add that two LNER units that had also been reported as too badly cracked to return to service with the bulk of the fleet back in May, 800104 and 800105, have also made appearances in service in the last few weeks. In the case of 800105, this unit was dumped in Tyne Yard for the majority of June as a result. As there is no fix for these cracks, what has changed that these units have all of a sudden gone from being "too badly cracked" to being fit for service without any remedial work done whatsoever?

Exactly the same answer as my previous - this presumes the reports that they were “too badly cracked” were accurate. That they’re back in service would suggest that those reports were over-exaggerated.
 

19Gnasher69

Member
Joined
1 Jul 2021
Messages
172
Location
Aire Valley
From this correspondence it looks as though all GWR and LNER units are serviceable (subject to inspections) except for 800026. Presumably sections weren’t cut out of 800205 or, as suggested above, the degree of parts removal wasn’t particularly significant.
I understood that sections from both units had gone for testing to UK and Japanese laboratories.
Has 800205 been reassembled or is 800026 the sole guinea pig?
 

JonathanH

Veteran Member
Joined
29 May 2011
Messages
23,406
From this correspondence it looks as though all GWR and LNER units are serviceable (subject to inspections) except for 800026
800013 also seemingly not in action since April (based on gen group postings). There are some others stopped for a shorter time.
 

Peter Mugridge

Veteran Member
Joined
8 Apr 2010
Messages
17,856
Location
Oakham
Not at present, a fix is yet to be developed.
Are we talking about the yaw damper cracks or the lifting point cracks here? I'm starting to lose track!

There's a report in Rail 935 stating that the fix for the lifting point cracks is that they will be removing and replacing the affected area; it should only take 24 hours for each unit as the vast majority of the fleet only have a single cracked lifting point.

My guess is they'll do those units with only one cracked area first and leave the ones with multiple areas needing changing until later in order to maximise fleet availability?
 