Transpennine Route Upgrade and Electrification updates

sjpowermac

Established Member
Joined
26 May 2018
Messages
2,079
All depends on what piles the structures being installed here are for. 'Open Route' ones will probably come more quickly, while those at overlaps & crossovers will likely take longer.
Again, many thanks indeed.
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

59CosG95

Established Member
Joined
18 Aug 2013
Messages
6,861
Location
Beeston (Notts)
This came up on the LinkedIn profile for Adey Steel, who are (I believe) the biggest supplier of OLE steelwork in the UK. 400 structures will be erected between York & Church Fenton.
 

WAO

Established Member
Joined
10 Mar 2019
Messages
1,225
Perhaps an advantage of a modest but economic project; UK producers can compete. I imagine that an order for 50 route miles of the stuff would be beyond any UK's firm's capacity and would go abroad, further impoverishing the Regions that such schemes are meant to help...

WAO
 

Bald Rick

Veteran Member
Joined
28 Sep 2010
Messages
35,817
Perhaps an advantage of a modest but economic project; UK producers can compete. I imagine that an order for 50 route miles of the stuff would be beyond any UK's firm's capacity and would go abroad, further impoverishing the Regions that such schemes are meant to help...

WAO

I doubt it. It’s not like they are all going to be installed at the same time. If they can produce x masts for installation over y months, they can produce 3x masts for installation over 3y months, and so on.
 

LNW-GW Joint

Veteran Member
Joined
22 Feb 2011
Messages
21,920
Location
Mold, Clwyd
Most OLE steelwork contracts seem to go to works based in the UK, but the specialist and fiddly parts are often sourced abroad, often Italy.
All the steel majors are global companies and will source production wherever is best for them.
NR's subcontractors will also have their preferred suppliers when they bid for the electrification work.
 

WAO

Established Member
Joined
10 Mar 2019
Messages
1,225
It's not that simple. Commercial considerations such as access to capital, risk, prolonged exposure to a single large (unstable!) customer etc often mean that the enquiry would be marked "decline to tender".

WAO
 

greyman42

Established Member
Joined
14 Aug 2017
Messages
5,368
This came up on the LinkedIn profile for Adey Steel, who are (I believe) the biggest supplier of OLE steelwork in the UK. 400 structures will be erected between York & Church Fenton.
Should that be between Colton Jc. and Church Fenton?
 

59CosG95

Established Member
Joined
18 Aug 2013
Messages
6,861
Location
Beeston (Notts)
Should that be between Colton Jc. and Church Fenton?
I've looked into it a bit, and your suggestion certainly seems more likely. SICAT (the specific cantilever type earmarked for TPE) has a max. span length of 74m, so I assumed the structures would be more spread out.

Based on the distances between Church F & York (8.77km Church Fenton to Colton Jn; 8.87km Colton Jn to York), the total distance is about 17.64km. Dividing that by 74m gives 238.4 structures over the entire length, assuming all structures are portals; they may well be a mix of portals, TTCs and single track cantilevers so you're probably right.
 

Grumpy

Established Member
Joined
8 Nov 2010
Messages
1,319
I've looked into it a bit, and your suggestion certainly seems more likely. SICAT (the specific cantilever type earmarked for TPE) has a max. span length of 74m, so I assumed the structures would be more spread out.

Based on the distances between Church F & York (8.77km Church Fenton to Colton Jn; 8.87km Colton Jn to York), the total distance is about 17.64km. Dividing that by 74m gives 238.4 structures over the entire length, assuming all structures are portals; they may well be a mix of portals, TTCs and single track cantilevers so you're probably right.
Isn't the point that York to Colton is already electrified?
Are they doing all 4 tracks? Seems a lot of structures for2
 

Bald Rick

Veteran Member
Joined
28 Sep 2010
Messages
35,817
Isn't the point that York to Colton is already electrified?
Are they doing all 4 tracks? Seems a lot of structures for2

It will surely be all 4 to Church Fenton North Jn.

I’m sorry if I haven’t been paying attention upthread, but where exactly is the wiring finishing at Church Fenton?
 

59CosG95

Established Member
Joined
18 Aug 2013
Messages
6,861
Location
Beeston (Notts)
It will surely be all 4 to Church Fenton North Jn.

I’m sorry if I haven’t been paying attention upthread, but where exactly is the wiring finishing at Church Fenton?
At a guess, the Church Fenton South Jn area. That seems to be where the new TSC is going so would make sense to get the sectioning arrangement up now to save modification later.
 

Chris NS

Member
Joined
19 Apr 2020
Messages
62
Location
Durham
I'm also guessing you'd want to get Church Fenton junction out of the way the same time as you do the work to Colton. Colton - Church Fenton is going to be a pain no matter what, with diversions difficult or impossible. But finish work at the junction, and when the time comes for the rest pg the route to Leeds (which will presumably need more work), you can send trains on the relatively easy Castleford route.
 

59CosG95

Established Member
Joined
18 Aug 2013
Messages
6,861
Location
Beeston (Notts)
I'm also guessing you'd want to get Church Fenton junction out of the way the same time as you do the work to Colton. Colton - Church Fenton is going to be a pain no matter what, with diversions difficult or impossible. But finish work at the junction, and when the time comes for the rest pg the route to Leeds (which will presumably need more work), you can send trains on the relatively easy Castleford route.
Like in South Wales, Colton - Church F has the advantage of quadruple track, so if NR & the Transpire Alliance (Siemens/Volker Rail/Murphy IIRC) decide to work ALO, it could be possible to have one pair of lines closed (e.g. the Normanton Lines) while the other pair is open. This would probably only happen at weekends to minimise disruption.
I only raise this as the Mains/Reliefs on the South Wales ML were done in a similar way last year.
 

unslet

Member
Joined
5 Apr 2013
Messages
76
Location
Leeds
It would appear the electrification is stopping short of Church Fenton station.

From the Church Fenton Parish Council after having met with Network Rail.

"The electrification does not go through Church Fenton, again it appears to stop on the track roughly opposite the airbase. This suggests bi-mode trains".
 

Halish Railway

Established Member
Joined
26 Apr 2017
Messages
2,176
Location
West Yorkshire / Birmingham
It would appear the electrification is stopping short of Church Fenton station.

From the Church Fenton Parish Council after having met with Network Rail.

"The electrification does not go through Church Fenton, again it appears to stop on the track roughly opposite the airbase. This suggests bi-mode trains".
This is probably due to the quagmire of having low wires underneath the Common Lane bridge being shortly followed by high wires at the Rose Lane level crossing.

Better to kick the problem into the long grass.
 

WAO

Established Member
Joined
10 Mar 2019
Messages
1,225
It may also be avoiding the pointwork of the ladder North of the station, depending on which airbase track they mean.

WAO
 

Philip Phlopp

Established Member
Joined
31 May 2015
Messages
3,003
It would appear the electrification is stopping short of Church Fenton station.

From the Church Fenton Parish Council after having met with Network Rail.

"The electrification does not go through Church Fenton, again it appears to stop on the track roughly opposite the airbase. This suggests bi-mode trains".

It was always going to stop there - there is (or was, or will be, or might be, or could be) the issue of the HS2 connection to contend with.

As Bald Rick says, it was never going to be electric trains just to Church Fenton - it is, at present, a nice little project to allow all bi-mode stock to arrive or depart from York on electric power, improving air quality in the area, and it deals with one of the major problems on the TRU - connecting the whole lot into the ECML.
 

Bald Rick

Veteran Member
Joined
28 Sep 2010
Messages
35,817
How big will the gap be between Neville Hill and Church Fenton?
Will the wires be extended from NH any distance at all? Maybe to Micklefield?

About 15 miles.

Wiring the gap may depend on options chosen for Northern Powerhouse Rail, as this section could well be one of the first parts of that project to be delivered.
 

WAO

Established Member
Joined
10 Mar 2019
Messages
1,225
I think that the "gap" is a bigger issue than just wires. The two-track railway East of Leeds has to host XC, TPE, serious stopping services and freight. There is a four track formation from just East of Marsh Lane in Leeds to beyond Cross Gates but the prospect of trying to widen a busy route even if the existing bridges are wide is daunting. The HS2/3 route basically eases the Church Fenton - Micklefield curve then heads straight West until it follows the M1. Extra tracks on this route with a curve over the M1 into the Cross Gates line mostly in open country, may be a consideration.

Electrification is not just about wires but about a better all round railway; hence the difficulties with TRU.

Greetings

WAO
 

quantinghome

Established Member
Joined
1 Jun 2013
Messages
2,887
Isn't the point of electrifying to Church Fenton to keep the pipeline of work going, sorting out a section unlikely to be affected by major upgrades/ realignments?
 

fgwrich

Established Member
Joined
15 Apr 2009
Messages
10,639
Location
Hampshire
This is probably due to the quagmire of having low wires underneath the Common Lane bridge being shortly followed by high wires at the Rose Lane level crossing.

Better to kick the problem into the long grass.
Can't be too much of an issue given that similar exists at Steventon on the GWML, albeit admittedly without the complexity of a junction fairly close by.
 

edwin_m

Veteran Member
Joined
21 Apr 2013
Messages
28,668
Location
Nottingham
I think that the "gap" is a bigger issue than just wires. The two-track railway East of Leeds has to host XC, TPE, serious stopping services and freight. There is a four track formation from just East of Marsh Lane in Leeds to beyond Cross Gates but the prospect of trying to widen a busy route even if the existing bridges are wide is daunting. The HS2/3 route basically eases the Church Fenton - Micklefield curve then heads straight West until it follows the M1. Extra tracks on this route with a curve over the M1 into the Cross Gates line mostly in open country, may be a consideration.

Electrification is not just about wires but about a better all round railway; hence the difficulties with TRU.

Greetings

WAO
In fact the proposed junction of HS2 is north of Church Fenton and appears to extend nearly to Ulleskelf (according to the HS Interactive Map). This presumably involves some kind of grade separation - but won't that render a big chunk of this scheme abortive?
 

59CosG95

Established Member
Joined
18 Aug 2013
Messages
6,861
Location
Beeston (Notts)
In fact the proposed junction of HS2 is north of Church Fenton and appears to extend nearly to Ulleskelf (according to the HS Interactive Map). This presumably involves some kind of grade separation - but won't that render a big chunk of this scheme abortive?
There is an indicative layout of the Phase 2b connection here: https://assets.publishing.service.g...ta/file/629106/C321-MMD-RT-DPP-130-591706.pdf
This is sadly about as much detail as we currently have on the connection - if it even goes ahead according to the latest doom-monger mill.
 

WAO

Established Member
Joined
10 Mar 2019
Messages
1,225
- but won't that render a big chunk of this scheme abortive?
Not if it ends North of Church Fenton as indicated. Pan up/down has to be North of the ladder. It must surely now be a NR "no regrets" scheme!

A new track layout may also indicate thinking towards capacity increases.

Greetings

WAO
 

BantamMenace

Member
Joined
2 Dec 2013
Messages
573
Do we know if the two road bridges and two footbridges (one at each station) in Garforth are ready for wires or do they require rebuilding?
 

YorksLad12

Established Member
Joined
5 Feb 2020
Messages
2,713
Location
Leeds
In fact the proposed junction of HS2 is north of Church Fenton and appears to extend nearly to Ulleskelf (according to the HS Interactive Map). This presumably involves some kind of grade separation - but won't that render a big chunk of this scheme abortive?

Not for another 20 years (at current rate of progress), no!
 

IanXC

Emeritus Moderator
Joined
18 Dec 2009
Messages
6,614
Do we know if the two road bridges and two footbridges (one at each station) in Garforth are ready for wires or do they require rebuilding?

Garforth footbridge in particular seems highly unlikely, the road bridge I'd say probably not ready. East Garforth bridges might just be modification rather than replacement.
 

Class 170101

On Moderation
Joined
1 Mar 2014
Messages
8,661
Can we be sure where HS2 2B will actually join the existing line there and in that way anyway? A document released by the NIC and being discussed elsewhere on this board has various options within it how can we be sure that these options will link at Church Fenton like that if at all? (Some say its 20 years away).
 