• Our new ticketing site is now live! Using either this or the original site (both powered by TrainSplit) helps support the running of the forum with every ticket purchase! Find out more and ask any questions/give us feedback in this thread!

Kidsgrove to crewe line

Status
Not open for further replies.

Hppmaar

New Member
Joined
23 Jun 2020
Messages
1
Location
Liverpool
Why have thay not doubled line from radway green to crewe.
Would give direct train liverpool to stoke, not faster by 30 mins by car.
Would give space
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

30907

Veteran Member
Joined
30 Sep 2012
Messages
21,973
Location
Airedale
Why have thay not doubled line from radway green to crewe.
Would give direct train liverpool to stoke, not faster by 30 mins by car.
Would give space
Welcome!
They singled it for economy when Crewe was rebuilt IIRC. As there are only 2 trains per hour each way it's not really a constraint on capacity.
 
Joined
6 Feb 2014
Messages
99
The real problem the single section causes is when the WCML is diverted via Stoke. Has happened to me quite a number of times. The capacity to cope with two way diversions on top of the 2tph each way creates backlogs stretching south of Nuneaton and north to Liverpool and Wigan.
I would like to see the costings for redoubling from Radway Green to Crewe (would still have problems at the throat at Crewe and Stoke/Stone - but surely would make a significant improvement).
Perhaps a lesson for HS2 to consider diversionary routes?
 

A0

On Moderation
Joined
19 Jan 2008
Messages
7,751
Why have thay not doubled line from radway green to crewe.
Would give direct train liverpool to stoke, not faster by 30 mins by car.
Would give space

Comes in the wrong side of Crewe to head for Liverpool so you'd need to find a 2 paths across Crewe - one there, one back.
 

Ianno87

Veteran Member
Joined
3 May 2015
Messages
15,214
The real problem the single section causes is when the WCML is diverted via Stoke. Has happened to me quite a number of times. The capacity to cope with two way diversions on top of the 2tph each way creates backlogs stretching south of Nuneaton and north to Liverpool and Wigan.
I would like to see the costings for redoubling from Radway Green to Crewe (would still have problems at the throat at Crewe and Stoke/Stone - but surely would make a significant improvement).
Perhaps a lesson for HS2 to consider diversionary routes?
HS2 *is* the diversionary route!
 

GRALISTAIR

Established Member
Joined
11 Apr 2012
Messages
10,534
Location
Preston Lancs
As @Bald Rick has pointed out on more occasions than I care to count, diversionary potential does not make for a viable business case.
I am not saying it (Diversionary potentials) does but surely to god for the love of everything logical it must at least help the B in the BCR calculation?
 

A0

On Moderation
Joined
19 Jan 2008
Messages
7,751
I am not saying it (Diversionary potentials) does but surely to god for the love of everything logical it must at least help the B in the BCR calculation?

Not necessarily, if the costs of maintaining the diversion in route knowledge and keeping spare paths exceeds the cost of providing an alternative - a coach perhaps - then there is no "benefit".
 

edwin_m

Veteran Member
Joined
21 Apr 2013
Messages
28,707
Location
Nottingham
At the time it was singled there was only the hourly Derby train using the route and not much freight. Pretty much by definition the train wouldn't be coming back out of Crewe at the same time as it went in, which was probably the reason to single it. One of many elements of the Crewe re-signaling, done at about the lowest point in BR's fortunes and expectations of future traffic, that turned out to be inadequate for the growth in demand that actually happened.
 

The Planner

Veteran Member
Joined
15 Apr 2008
Messages
19,718
Not being touched as part of Crewe re-signalling or HS2 enabling either. It would have a use for the construction period, but after? not so much.
 

LNW-GW Joint

Veteran Member
Joined
22 Feb 2011
Messages
21,935
Location
Mold, Clwyd
As @Bald Rick has pointed out on more occasions than I care to count, diversionary potential does not make for a viable business case.

It did actually have a business case or it wouldn't have been electrified c2000.
This was just so WCML traffic could use it instead of the main line to Stafford for a year while they rebuilt it.
Otherwise the Crewe-Stoke-Stafford service would be a DMU (or not exist, as before).
 

CW2

Established Member
Joined
7 May 2020
Messages
2,227
Location
Crewe
Electrification was necessary to allow for WCML diversions during the West Coast Route Modernisation. There was no business case driven by local demand, it was all about keeping the WCML running. Doubling was considered at that time, and deemed unnecessary. I don't see anything much has changed.
 

jfowkes

Established Member
Joined
20 Jul 2017
Messages
1,271
I'm surprised there isn't a demand-driven business case for an a-bit-more-regular-than-once-an-hour Crewe-Stoke shuttle, especially in the peaks.
 

Trainfan2019

Member
Joined
9 Aug 2019
Messages
530
I'm surprised there isn't a demand-driven business case for an a-bit-more-regular-than-once-an-hour Crewe-Stoke shuttle, especially in the peaks.

There are 2 trains an hour between Crewe and Stoke (London Northwestern and East Midlands Railway) but badly timed leaving Crewe at 1 minute past and 7 minutes past each hour. Even worse on Sundays as EMR don't start operating until mid-afternoon.
 

ForTheLoveOf

Established Member
Joined
7 Oct 2017
Messages
6,416
Not being touched as part of Crewe re-signalling or HS2 enabling either. It would have a use for the construction period, but after? not so much.
It wouldn't be the first time an improvement was made to cater for other long-running engineering/improvement works. HS2 will no doubt disrupt the southern end of Crewe for quite a number of years to come. Going via Shrewsbury is hardly a viable alternative to via Kidsgrove, and it's not electrified anyway.

Refusing to redouble a once double-track and already electrified diversionary route epitomises the penny wise, pound foolish thinking that pervades today's rail industry (and this is by no means a criticism levelled solely at Network Rail itself).

There's no single track bridges to contend with (a double track one was provided at considerable expense when the A5020 was built). There's only a couple of passenger trains an hour to bustitute (or divert via Norton Bridge) whilst the work is done.

Not many schemes are this simple. And yet it's seemingly impossible to just get on and do it, in a reasonable time and at a reasonable cost. For as long as the rail industry is unable to grasp the nettle of efficiency, even the smallest improvements will continue to take forever to be approved.
 

Bald Rick

Veteran Member
Joined
28 Sep 2010
Messages
35,910
Electrification was necessary to allow for WCML diversions during the West Coast Route Modernisation. There was no business case driven by local demand, it was all about keeping the WCML running. Doubling was considered at that time, and deemed unnecessary. I don't see anything much has changed.

It was indeed considered for redoubling. I remember it well.

The choice was redoubling, or electrification. Not both. The right answer was chosen.
 

The Chimaera

Member
Joined
15 Jun 2018
Messages
96
There's no single track bridges to contend with (a double track one was provided at considerable expense when the A5020 was built). There's only a couple of passenger trains an hour to bustitute (or divert via Norton Bridge) whilst the work is done.

Not many schemes are this simple. And yet it's seemingly impossible to just get on and do it, in a reasonable time and at a reasonable cost. For as long as the rail industry is unable to grasp the nettle of efficiency, even the smallest improvements will continue to take forever to be approved.



No single track bridges to remove correct but one overbridge to heighten because the single line was slewed to the centre of formation to pass under the middle of a low arched bridge to get clearance of the OLE. Not a biggy really though. Should be a easy, locally led project but we don't live in that world anymore unfortunately.
 
Last edited by a moderator:

ForTheLoveOf

Established Member
Joined
7 Oct 2017
Messages
6,416
No single track bridges to remove correct but one overbridge to heighten because the single line was slewed to the centre of formation to pass under the middle of a low arched bridge to get clearance of the OLE. Not a biggy really though. Should be a easy, locally led project but we don't live in that world anymore unfortunately.
Precisely. It's frankly sad to think about the contemporary state of the industry by comparison to the attitude shown by videos such as this:
Electrifying Euston in one night. Utterly unthinkable nowadays :(
 

InOban

On Moderation
Joined
12 Mar 2017
Messages
4,537
Raising a bridge can be simple or complicated depending on the number of services which run under the surface, requiring each to be diverted across a temporary footbridge while the old bridge is dismantled and rebuilt.
 

A0

On Moderation
Joined
19 Jan 2008
Messages
7,751
Precisely. It's frankly sad to think about the contemporary state of the industry by comparison to the attitude shown by videos such as this:

Electrifying Euston in one night. Utterly unthinkable nowadays
:(

Naturally you're qualified to make such assessments and assertions?
 

CW2

Established Member
Joined
7 May 2020
Messages
2,227
Location
Crewe
The traditional way of working is no longer possible. The Working at Height Regulations mean practices like leaning a ladder at a 45 degree angle then climbing half way up to reach up to clip up a cable are (rightly) prohibited. I don't claim we have the most efficient electrification methodology, but at least we aren't killing and maiming as many people as we used to.
 

GRALISTAIR

Established Member
Joined
11 Apr 2012
Messages
10,534
Location
Preston Lancs
The traditional way of working is no longer possible. The Working at Height Regulations mean practices like leaning a ladder at a 45 degree angle then climbing half way up to reach up to clip up a cable are (rightly) prohibited. I don't claim we have the most efficient electrification methodology, but at least we aren't killing and maiming as many people as we used to.
Hear hear. I get frustrated too but Health and Safety has to be quite rightly paramount. I want people going home to their families etc at night not in the casualty department of the local hospital.
 

ForTheLoveOf

Established Member
Joined
7 Oct 2017
Messages
6,416
The traditional way of working is no longer possible. The Working at Height Regulations mean practices like leaning a ladder at a 45 degree angle then climbing half way up to reach up to clip up a cable are (rightly) prohibited. I don't claim we have the most efficient electrification methodology, but at least we aren't killing and maiming as many people as we used to.
How many people are killed and maimed in RTCs each year that wouldn't have happened if there were a viable train alternative? What about serious health conditions and deaths from air pollution from our congested roads?

As morbid as might seem, the deaths and injuries of track workers needs to be put into the context of what happens if you focus purely on improving that issue (to the detriment of enabling more public transport improvements to happen, and thus improving society as a whole, with the money that's available).

You have to look at the bigger picture. Unfortunately that's something this country struggles at.
 

Bevan Price

Established Member
Joined
22 Apr 2010
Messages
8,341
Not necessarily, if the costs of maintaining the diversion in route knowledge and keeping spare paths exceeds the cost of providing an alternative - a coach perhaps - then there is no "benefit".
Maybe - but rail replacement coaches are a big negative benefit. I don't have numerical figures, but trains are always a lot emptier than normal when pre-advertised rail replacement services occur.
 

A0

On Moderation
Joined
19 Jan 2008
Messages
7,751
How many people are killed and maimed in RTCs each year that wouldn't have happened if there were a viable train alternative? What about serious health conditions and deaths from air pollution from our congested roads?

As morbid as might seem, the deaths and injuries of track workers needs to be put into the context of what happens if you focus purely on improving that issue (to the detriment of enabling more public transport improvements to happen, and thus improving society as a whole, with the money that's available).

You have to look at the bigger picture. Unfortunately that's something this country struggles at.

According to government figures in 2018 there were about 5 deaths for every BILLION miles travelled on the roads.

So to remove just one road death - assuming a straight correlation you would need to replace 200,000 miles worth of road journey. The average motorist drives about 12,000 miles a year - so you would need 16 "average mileage" motorists to change all of their journeys to rail to achieve that 1 reduction in death.

If you think that's going to happen, I think you have a tenuous grasp on reality.
 

A0

On Moderation
Joined
19 Jan 2008
Messages
7,751
Maybe - but rail replacement coaches are a big negative benefit. I don't have numerical figures, but trains are always a lot emptier than normal when pre-advertised rail replacement services occur.

But rail replacement coaches are exceptional and usually people are advised to consider if their journey is essential. If anything it highlights the number of "non essential" journeys people make.

It's not a "big negative benefit'" except in your opinion because you don't like rail replacement coaches.
 

ForTheLoveOf

Established Member
Joined
7 Oct 2017
Messages
6,416
According to government figures in 2018 there were about 5 deaths for every BILLION miles travelled on the roads.

So to remove just one road death - assuming a straight correlation you would need to replace 200,000 miles worth of road journey. The average motorist drives about 12,000 miles a year - so you would need 16 "average mileage" motorists to change all of their journeys to rail to achieve that 1 reduction in death.

If you think that's going to happen, I think you have a tenuous grasp on reality.
Reduced RTC deaths are just part of the benefits. It may well be that the decrease in injuries and deaths is not sufficient to justify risking additional rail workers' lives, but at the moment no attempt seems to be made to even try and work this out.
 

CW2

Established Member
Joined
7 May 2020
Messages
2,227
Location
Crewe
Reduced RTC deaths are just part of the benefits. It may well be that the decrease in injuries and deaths is not sufficient to justify risking additional rail workers' lives, but at the moment no attempt seems to be made to even try and work this out.
In sheer economic terms the benefits you are seeking to count only produce small numbers - regardless of how obviously good the idea seems to be. So they get lumped together as "Wider Economic Bemefits" in the business case. Sometimes these benefits can help to swing a marginal case, but you'll never manage to justify a project based solely on such benefits.
 
Status
Not open for further replies.

Top