Hello all,
My first post on RailUK Forums in a long time – I did have an account many years ago, but I cannot remember its details for the life of me... However, having attended the Institute of Mechanical Engineers lecture on the Valley Lines electrification at Cardiff University on Wednesday evening, I thought that I would share my notes covering what Susan Holyoake, Principle Engineering Manager for Amey, discussed in case they are of interest to anyone in this thread.
Essentially, and very much unsurprisingly, the tight budget allocated to the project means that TFW are seeking to avoid more costly and difficult elements of the project wherever possible. Hence, locations such as Caerphilly Tunnel and Merthyr Viaduct will not be wired; whilst Permanently Earthed Sections will be installed where minimum standards surrounding insulation cannot be met. The latter is particularly the case at overbridges, with around 60 sites currently identified. However, it was explained that it is hoped to reduce the number of these if possible, with permanent earthing only an option where the cost of altering a bridge is too much. Also mentioned were challenges surrounding signal sighting distances on several curves, together with various issues surrounding the geology of the glacial valleys.
More specifically, Cardiff Queen Street won’t be wired to avoid having to wire complex junctions. Instead, the wires will begin to the west of Cathays station on the Merthyr/Rhondda lines and south of Crwys Road on the Rhymney/Coryton line. At Cardiff Bay, there will be charging points installed, allowing the Citylinks to recharge whilst turning around. At Pontypridd, it was explained that the decision to forgo electrification is not only attributable to the extra cost of wiring the junctions, but also to both avoid undertaking any alterations to the Grade II listed canopy, and foundation issues on the bridges in the area. On the Rhymney Line, wiring has been had to be extended from Ystrad Mynach to Bargoed because of issues with Western Power supplying enough power off the existing infrastructure at Rhymney. However, the FLIRTs will be recharge by around 7% whilst turning around in the platforms (enough to get them back down to Bargoed) whilst, so far as I remember anyway, the sidings will be supplied at a reduced charge.
More generally, Taffs Well Depot, Cardiff Canton and Treherbert stabling sidings will be equipped with charging points. Switch over from OHLE to battery power will be undertaken automatically via beacons placed at 13 seconds at line speed from the end of wiring. The Stadlers will also be able to recognise where a Permanently Earthed Section begins and ends, with the change over to battery being automatic.
That’s about all the notes I took at the event; a lot of the more technical specifications were too much for my brain. However, hopefully they may be of use to someone!
Best wishes,
Jamie
My first post on RailUK Forums in a long time – I did have an account many years ago, but I cannot remember its details for the life of me... However, having attended the Institute of Mechanical Engineers lecture on the Valley Lines electrification at Cardiff University on Wednesday evening, I thought that I would share my notes covering what Susan Holyoake, Principle Engineering Manager for Amey, discussed in case they are of interest to anyone in this thread.
Essentially, and very much unsurprisingly, the tight budget allocated to the project means that TFW are seeking to avoid more costly and difficult elements of the project wherever possible. Hence, locations such as Caerphilly Tunnel and Merthyr Viaduct will not be wired; whilst Permanently Earthed Sections will be installed where minimum standards surrounding insulation cannot be met. The latter is particularly the case at overbridges, with around 60 sites currently identified. However, it was explained that it is hoped to reduce the number of these if possible, with permanent earthing only an option where the cost of altering a bridge is too much. Also mentioned were challenges surrounding signal sighting distances on several curves, together with various issues surrounding the geology of the glacial valleys.
More specifically, Cardiff Queen Street won’t be wired to avoid having to wire complex junctions. Instead, the wires will begin to the west of Cathays station on the Merthyr/Rhondda lines and south of Crwys Road on the Rhymney/Coryton line. At Cardiff Bay, there will be charging points installed, allowing the Citylinks to recharge whilst turning around. At Pontypridd, it was explained that the decision to forgo electrification is not only attributable to the extra cost of wiring the junctions, but also to both avoid undertaking any alterations to the Grade II listed canopy, and foundation issues on the bridges in the area. On the Rhymney Line, wiring has been had to be extended from Ystrad Mynach to Bargoed because of issues with Western Power supplying enough power off the existing infrastructure at Rhymney. However, the FLIRTs will be recharge by around 7% whilst turning around in the platforms (enough to get them back down to Bargoed) whilst, so far as I remember anyway, the sidings will be supplied at a reduced charge.
More generally, Taffs Well Depot, Cardiff Canton and Treherbert stabling sidings will be equipped with charging points. Switch over from OHLE to battery power will be undertaken automatically via beacons placed at 13 seconds at line speed from the end of wiring. The Stadlers will also be able to recognise where a Permanently Earthed Section begins and ends, with the change over to battery being automatic.
That’s about all the notes I took at the event; a lot of the more technical specifications were too much for my brain. However, hopefully they may be of use to someone!
Best wishes,
Jamie