adamedwards
Member
- Joined
- 4 Apr 2016
- Messages
- 796
"Build 6 tracks" is not so easy along the WCML until you get beyond Tring. That's why HS2 is in tunnel out of London. At which point you might as well go direct to the north west and not via Rugby.
Moving block doesnt exist on a major railway yet. Cab signalling on the WCML is a marginal gain, it has 3 minute headways now, in cab might get you 2 in places, 2.5 in others and doesnt give you anywhere near the uplift in capacity.Moving block, cab signalling, grade separation, modified timetables (trains stopping in more regular patterns) new rolling stock, double-heading on freight services etc. It is also possible to build 6 tracks
Moving block, cab signalling, grade separation, modified timetables (trains stopping in more regular patterns) new rolling stock, double-heading on freight services etc. It is also possible to build 6 tracks
Incorrect, it will allow (although some other things will still be required for this) 140mph operation.Cab signalling - gives you nothing (without shorter, or moving blocks)
Incorrect, it will allow (although some other things will still be required for this) 140mph operation.
Which in turn allows you to catch up the train in front that has stopped that bit quicker.Incorrect, it will allow (although some other things will still be required for this) 140mph operation.
Railtrack had already done a lot of work on the WCML for this, until they went bust.‘Some other things’ being an upgrade of the OLE, upgrade and recanting of the track, upgrade of many (if not all) underbridges, closure of all platforms to passengers where trains at that speed may pass, a complete change to all maintenance requirements, removal of all level crossings, etc.etc. All for 3 seconds a mile.
However, it still doesn’t do anything for capacity.
Railtrack had already done a lot of work on the WCML for this, until they went bust.
Ex-Beeching lines serve places where there is previously no fixed public transport link (a bus running on a public road with a sign for a bus stop is not a real 'fixed and permanent' link). HS2 serves a place that is already served by a 4-track line. Considering that the 4-track line can be optimised, then do that first
But should this be the case? No. If a £2b project doubles, it gets to £4b. If a £10b project doubles, it's an extra £10b to fork out. Thus the value for money may be different. It's not just proportions.
The suggestion that the WCML should be six tracked is comical. For those who remember the four tracking of 15 miles of the Trent Valley line from Tamworth to not-quite-Rugeley, the line was shut almost every weekend for 3 years, and was shut for a couple of big blockades in that time as well. That was in generally easy terrain in open country. It also took 10 years of planning before work started. It reasonable to assume that for, say, 80 miles of 6 tracking to get from just Euston to Rugby the line would have to be shut somewhere on that stretch every weekend for 15 years. At a push, you could start work in 2030. Even then that does nothing for the Midlands and north. Doesn’t sound attractive to me.
And the upgrade fifteen/twenty years ago was the "low hanging fruit" - it took three years of costly disruption to deliver the "quick wins" (and even those were scaled back somewhat) - imagine how much harder it'd be now to have the same kind of boost to capacity, given that any obvious/ simple/ cheap upgrades have already been done.
And don't forget they gave up and didn't do the full job. South of Rugby, journeys were sped up and an extra path created mostly by removing stops at Watford or MK rather than completing the proposed works.
They weren't going to do work to allow more stops at Watford or MK. They were going to do work elsewhere (and maybe there) that meant that they didn't need to remove stops at those stations to eke out the limited extra capacity and couple of minutes saving that the scheme was meant to deliver.What work were they going to do to allow more stops at Watford or Milton Keynes? It would have required a significant rebuild of both stations to add a full set of island platforms on the fast lines.
I don’t like to correct you, but feel the need to set the record straight on the level of disruption.
It took 10 years of costly disruption, not 3. The first disruptive access was in 1998 for the early stages of Euston remodelling, the last was in 2008. (And that doesn’t include some work that was delivered later, such as parts of Watford and Bletchley resignalling, Norton Bridge etc.)
In those 10 years we had major blockades, in no particular order: on the approaches to Birmingham (nearly 3 weeks), the Stoke line (months), Crewe- Cheadle Hulme (months), Euston - Hemel week long blocks (at least a couple in summer), Trent Valley (as mentioned above), Euston (reduced service for 6 months, no DC line into Euston for over a year), Willesden (a week, which overran several days), durations I can’t remember for Tring, Ledburn & MK, Rugby (a week, overran badly, with severe restrictions there for almost a year beforehand). Oh and there were more big blocks for Wolverhampton, Coventry, Birmingham International, Stockport, and on the main line all the way down to Scotland.
But other than that ...
They weren't going to do work to allow more stops at Watford or MK. They were going to do work elsewhere (and maybe there) that meant that they didn't need to remove stops at those stations to eke out the limited extra capacity and couple of minutes saving that the scheme was meant to deliver.
Rugby went down in folklore, some of the stories you hear about that one![]()
That's a pretty sobering list - one that should be read by anyone who thinks that we could replace HS2 plans by "simply" upgrading existing routes!
I can't imagine today's passengers putting up with that level of disruption - it must have been even worse than I remembered (thanks for clarifying).
I can't remember. Maybe it was the plan all along to reduce Home Counties->North service to get small gains in London->North service. Which isn't a good plan at all - at least for the small gains eked out (bigger gains, maybe).But what work was it? I don’t remember that.
Didn't Ledburn go in as swing nose crossings, or was it Bourne End?It was actually worse than that (time passes - nightmares are forgotten) , - Ledburn was (I think) 16 weekends + another 16 weekends as they had installed the wrong equipment first time around. Then there was a hefty TSR for a long time over all 4 lines - 60 mph or less.
Didn't Ledburn go in as swing nose crossings, or was it Bourne End?
I can't remember. Maybe it was the plan all along to reduce Home Counties->North service to get small gains in London->North service. Which isn't a good plan at all - at least for the small gains eked out (bigger gains, maybe).
Didn't Ledburn go in as swing nose crossings, or was it Bourne End?
Moving block, cab signalling, grade separation, modified timetables (trains stopping in more regular patterns) new rolling stock, double-heading on freight services etc. It is also possible to build 6 tracks
This compares to an expected 1,100 seats on a HS2 train.
An HS2 train is considerably longer. With some work, we could also extend WCML trains.
An HS2 train is considerably longer. With some work, we could also extend WCML trains.
Rugby went down in folklore, some of the stories you hear about that one![]()
I don't suppose there's anywhere us proles can read about those stories of old?Oh it was quite something.
An HS2 train is considerably longer. With some work, we could also extend WCML trains.