BBC Breakfast reporting a three week signalling project on Norwich-Yarmouth line

Status
Not open for further replies.
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

scottie

Member
Joined
21 Feb 2012
Messages
83
Location
south yorkshire
Transferring from old fashioned signals to the new colour light signals probably as the new ones were bagged over last week while I was Acle on the Yarmouth line.
 

dk1

Veteran Member
Joined
2 Oct 2009
Messages
19,910
Location
East Anglia
BBC Breakfast reporting a three week signalling project on Norwich-Yarmouth (is that the Wherry Lines?) in Feb with replacement buses. I wonder if it is related to he signalling problems.
Nothing to do with it. Was planned to be done last year but delayed. Track renewals and a bridge replacement being done at the same time. Its the reason Berney Arms hasn't seen a train for 18 months.
 

LAX54

Established Member
Joined
15 Jan 2008
Messages
3,908
BBC Breakfast reporting a three week signalling project on Norwich-Yarmouth (is that the Wherry Lines?) in Feb with replacement buses. I wonder if it is related to he signalling problems.

No, just the final stage of the resig project, with the final alterations and commissioning of the lines into Colchester ASC.... :) all being well
 