As mentioned, a bit late given when the petition expires but a great idea that should have been done when it got greenlit! A QR code would also have been a good idea...people are lazy, and probably in a rush at a TVM. *shrugs*
As mentioned, a bit late given when the petition expires but a great idea that should have been done when it got greenlit! A QR code would also have been a good idea...people are lazy, and probably in a rush at a TVM. *shrugs*
From 20 May, the only trains terminating/originating in Piccadilly 13/14 will be a few TfW Chester/N Wales services in the peaks (off peak they continue to the Airport). These mostly reverse in the Mayfield Loop. They could not terminate at Oxford Road instead because Platform 5 is occupied by Northern trains at those times (the TfW loco hauled set is too long for that platform anyway).I'd say for now, any trains that terminate/begin at 13/14 should terminate at Platform 5 at Oxford Road as there is no point taking up valuable time on the platform if no through service is provided. Oxford Road and Piccadilly are well connected and a transfer if needed is easy enough to make.
Even removing 1 train per hour would help give a little bit more reliability, especially because the trains which terminate need to be thoroughly checked by staff to ensure no-one is still on-board, adding to the dwell times significantly.
If more services from the Chat Moss line went to Victoria, while services from the Bolton line continued to go to Piccadilly via the Windsor Link, the performance risk of conflicts at Ordsall Lane Junction would increase. In any case the Victoria through platforms have no spare capacity for additional services.I agree, but the only such trains should be the local stopping services (2/hour) from the CLC Warrington line, which have nowhere else to terminate. In particular, as there are other trains from Chester and Warrington to Piccadilly, all services from Chester & Warrington BQ should go to Victoria.
Not the most elegant (or well known) but both work on any Android:Given that Android, bizarrely, doesn't include a QR reader as standard, that might actually be less use than you think.
Someone needs to tell the powers that be to start off by not sending 2 car pacers through the UK's second biggest city...
I genuinely think the terminating platform at Oxford Road is underutilised. Personally I love Oxford Road compared to using Piccadilly when given the choice, it's usually quieter and there are more places to sit.
I've also noticed trains that terminate at 13/14 have much longer dwell times than those that don't as staff have to ensure everyone is off the train. I think if trains are to use 13/14 they MUST have an onward connection to a destination either side as it both reduces dwell times and ensures that the best use is being made of the platforms.
Furthermore, I would also truncate the Liverpool Lime Street - Piccadilly - Crewe via Airport local all stations (or magical mystery tour) to run Crewe - Airport and Liverpool Lime Street - Victoria.
This, remember that an Intermodal takes up the best part of two paths due to the length of them.Freight?
When I’m waiting at Oxford Road at 16:15 each night the hourly container trains seem to cause chaos each time they run. They are so long the front end must be in Oxford Road and the rear still in Picadilly... With those and TPEs late running and over crowded services getting in the way of the commuter trains nothing runs on time...
It’s a complete mess.
They can’t, not with the current infrastructure. The container terminal faces east, straight into the Castlefield corridor. Even if trains could arrive and depart to/from the west, there’s no easy route for them to ultimately head south, where they need to go. It’d surely be possible to rebuild (or relocate?) the terminal to allow access from the west, and to construct a chord line to connect the CLC to the WCML around Warrington - but at what cost?Could they reroute these container trains away from Castlefield? Surely if they can they should and must
Could they reroute these container trains away from Castlefield? Surely if they can they should and must
They can’t, not with the current infrastructure. The container terminal faces east, straight into the Castlefield corridor. Even if trains could arrive and depart to/from the west, there’s no easy route for them to ultimately head south, where they need to go. It’d surely be possible to rebuild (or relocate?) the terminal to allow access from the west, and to construct a chord line to connect the CLC to the WCML around Warrington - but at what cost?
As a cheaper alternative would it be possible to have all freight on the Castlefield route to only operate in the late evenings and early mornings and overnight, which would mean it would run either before or after most passenger services operate?
I doubt that'd work with finite capacity in the terminal (so you can't just squash the whole day's intermodal service into less than half a day) nor with the tight timescales involved.As a cheaper alternative would it be possible to have all freight on the Castlefield route to only operate in the late evenings and early mornings and overnight, which would mean it would run either before or after most passenger services operate?
Where do you hide a delayed inbound freight train, though? Admittedly you could probably recess late runners in Basford Hall, but it'll just compound the problems with traincrew running out of hours, subsequent freight trains being knocked too, and just makes it more likely that the traffic will move to the roads instead. The same applies to a departing freight - it's all well and good until you run out of space to accept a subsequent arrival. I'd imagine that most of the delays are down to passenger operators or Network Rail anyway, so penalising the FOC won't help in that case.Or just refuse it its path if it's late, which would concentrate minds on it not being. Traditionally passenger would always win over freight. Now it's who pays?
Where do you hide a delayed inbound freight train, though? Admittedly you could probably recess late runners in Basford Hall, but it'll just compound the problems with traincrew running out of hours, subsequent freight trains being knocked too, and just makes it more likely that the traffic will move to the roads instead. The same applies to a departing freight - it's all well and good until you run out of space to accept a subsequent arrival. I'd imagine that most of the delays are down to passenger operators or Network Rail anyway, so penalising the FOC won't help in that case.
IIRC the Piccadilly/Oxford Road package was supposed to increase the corridor capacity to 20tph (3 minutes planning headway). 16tph of passenger services then allows for 2tph freight, per the original Northern Hub requirements (each freight occupying two paths).This, remember that an Intermodal takes up the best part of two paths due to the length of them.
IIRC the Piccadilly/Oxford Road package was supposed to increase the corridor capacity to 20tph (3 minutes planning headway). 16tph of passenger services then allows for 2tph freight, per the original Northern Hub requirements (each freight occupying two paths).
With four through platforms at both Oxford Road and Piccadilly, 3 minutes headway would mean 6 minutes reoccupancy time for each platform. That should be achievable even with end door stock.3 minutes headway will not work unless they go Thameslink style. This is idiocy.
What is it about the UK that means we won't spend money simply to make the existing service, with longer trains, reliable as clockwork?
It's totally counter to the highly successful Dutch and Swiss models.
So Wales/Chester/Warrington gets a train to Stalybridge, whilst every shack from Yorkshire gets a service to the airport.
I can't see any holes in that plan, no sir.
3 car trains shouldn't be running through P13/14 - and demand should be spread a bit more. The North Wales services are definitely appropriate to run to Victoria.Warrington would get CLC services to the Airport. Llandudno services diverting to Stalybridge would provide 2tph between Chester and Victoria. It was an option provided to bidders for the new franchise. While its understandable that it was not chosen it is a reasonable option. The longest units on Llandudno-Manchester services in the long term will be 3 coaches.
Are you quite sure of that? The longest configuration of the new CAF stock will be 3 coaches long, but they'll have end-gangways for working in multiple, like the 158s.The longest units on Llandudno-Manchester services in the long term will be 3 coaches.
Are you quite sure of that? The longest configuration of the new CAF stock will be 3 coaches long, but they'll have end-gangways for working in multiple, like the 158s.
I'd say it's fair to expect 3 coach TfW services during the day, but they'll certainly be coupling units together for the peak workings. (Even if the extra unit is only used as far as Chester.) They've already done it with the 175s, haven't they?
Given that Manchester - South Wales will eventually be 4 or 5 coaches (once the last units are delivered and the First class service to Swansea is introduced), and the Liverpool - Llandudno / Shrewsbury (& Cardiff) will be at least 4 coaches at the Liverpool end (as the units will divide at Chester), I can't see the Manchester - Bangor services limited to no more than 3 coaches...
If anyone seriously agreed to that then they need shooting, doomed to fail within a day with no resiliance.IIRC the Piccadilly/Oxford Road package was supposed to increase the corridor capacity to 20tph (3 minutes planning headway). 16tph of passenger services then allows for 2tph freight, per the original Northern Hub requirements (each freight occupying two paths).
Warrington would get CLC services to the Airport. Llandudno services diverting to Stalybridge would provide 2tph between Chester and Victoria. It was an option provided to bidders for the new franchise. While its understandable that it was not chosen it is a reasonable option. The longest units on Llandudno-Manchester services in the long term will be 3 coaches.