Blackpool - Manchester Electrification

Status
Not open for further replies.
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

PN27

Member
Joined
31 Jul 2018
Messages
51
To clarify from a "layman's perspective"- are there now full wiring runs from the WCML all the way through to Bolton?

No, there's a gap through Lostock station- they've been rebuilding the platforms all week. I think it's continuous from the south end of Lostock through to Bolton, though there may be some bits and pieces missing around Bolton station.
 

td97

Established Member
Joined
26 Jul 2017
Messages
1,556

Foggycorner

Member
Joined
16 Nov 2016
Messages
202
Location
bolton
Re B006r, q & p; that slope behind the electrical kit looks q̶u̶i̶t̶e̶ dangerously steep to me. Has there been any work noted to remedy this? I understand a gabion wall may be installed there. Unfortunately a lot of this work is out of sight, hidden behind the transformer.
That slope was there before the transformer compound was built in front of it and has been for the last 25 years without any mishaps
 

59CosG95

Established Member
Joined
18 Aug 2013
Messages
6,853
Location
Beeston (Notts)
That slope was there before the transformer compound was built in front of it and has been for the last 25 years without any mishaps
In defence of td97's worry, failure of the slope would be much more disastrous now than it was for the past 25 years. Plus, the project's already been mired with ground problems; the last thing it needs is a landslip wiping out the feeder station. Slopes are notoriously fickle, and I personally think that any protection for the area around the feeder station is a good thing.
 

snowball

Established Member
Joined
4 Mar 2013
Messages
8,144
Location
Leeds
Presumably the slope has less far to fall now, since the construction of the ziggurat on which the feeder station sits?
 

wrinkley

Member
Joined
6 Feb 2015
Messages
130
Down line wired through Lostock station from the feeder point where they stopped yesterday, a few registration arms are missing and the wires are on slings at those points. The wiring roadrailers are parked on the down line near the feeder, but no-one on board. The platform work is still on going but all timber has been moved off the tracks. Photos to Dave for tomorrow.
 

59CosG95

Established Member
Joined
18 Aug 2013
Messages
6,853
Location
Beeston (Notts)
Down line wired through Lostock station from the feeder point where they stopped yesterday, a few registration arms are missing and the wires are on slings at those points. The wiring roadrailers are parked on the down line near the feeder, but no-one on board. The platform work is still on going but all timber has been moved off the tracks. Photos to Dave for tomorrow.
Good news indeed! How far towards Golf Course FB have the wires gone?
 

wrinkley

Member
Joined
6 Feb 2015
Messages
130
Good news indeed! How far towards Golf Course FB have the wires gone?

The wiring goes just past the footbridge to join up to the existing. They have just started on the up line from the station to the footbridge. Presumably they will work from where they finished on the up line yesterday back to the station next.
 

CAF397

Member
Joined
15 Sep 2010
Messages
1,095
Location
Lancashire
This weekend and next they must be connecting the Bolton line overheads to the existing network at Ordsall Lane and Deal St.

Only Network Rail isolated the overheads at Ordsall Lane Jn this morning and no electric trains could access the Chat Moss from Manchester Oxford Road. An ‘oversight’ apparently. The isolation was shortened and electric services resumed.

Next weekend is a full block, with TPE Scotland services starting and terminating at Preston.
 

LDECRexile

Established Member
Joined
30 Jan 2014
Messages
2,149
Location
Southport, UK
Reg has kindly sent a shot showing the dramatic changes south of Bolton station.

I've added it to his album here:

https://www.flickr.com/photos/127646831@N03/albums/72157671732263863

Wrinkley has been on hand to witness wiring at Lostock and kindly sent a suite of action shots:

I've added them to his album here:

https://www.flickr.com/photos/127646831@N03/albums/72157654034635234

I've added both their contributions to the Combined Volume here:

https://www.flickr.com/photos/127646831@N03/albums/72157661069863633

With this batch Wrinkley has passed the 1500 photos and films mark.

Thank you both, Reg and Wrinkley.
 

Baz123

Member
Joined
10 Jun 2018
Messages
15
More progress at Lostock - C&C now installed through the station and C&C being installed on the Wigan branch. I was under the impression the Wigan branch was going to be electrified at a later date?
 

Attachments

  • IMG_20180901_181141106_HDR.jpg
    IMG_20180901_181141106_HDR.jpg
    4.3 MB · Views: 49
  • IMG_20180901_181220180_HDR.jpg
    IMG_20180901_181220180_HDR.jpg
    4.2 MB · Views: 45
  • IMG_20180901_181254999_HDR.jpg
    IMG_20180901_181254999_HDR.jpg
    3.9 MB · Views: 45
  • IMG_20180901_181747378_HDR.jpg
    IMG_20180901_181747378_HDR.jpg
    3 MB · Views: 43
  • IMG_20180901_181910277_HDR.jpg
    IMG_20180901_181910277_HDR.jpg
    3.5 MB · Views: 47
  • IMG_20180901_182103683_HDR.jpg
    IMG_20180901_182103683_HDR.jpg
    3.3 MB · Views: 45

59CosG95

Established Member
Joined
18 Aug 2013
Messages
6,853
Location
Beeston (Notts)
More progress at Lostock - C&C now installed through the station and C&C being installed on the Wigan branch. I was under the impression the Wigan branch was going to be electrified at a later date?
The Wigan Branch, as I recall, is only getting an overrun at this stage. I can assume that (if it hasn't got one already), the Atherton line from Salford Crescent is due to be similarly wired.
 

Joseph_Locke

Established Member
Joined
14 Apr 2012
Messages
1,878
Location
Within earshot of trains passing the one and half
The Wigan Branch, as I recall, is only getting an overrun at this stage. I can assume that (if it hasn't got one already), the Atherton line from Salford Crescent is due to be similarly wired.

Only the down Atherton line, as far as Frederick Road. The wiring of both Hindley lines was specifically as active provision for the future, otherwise only the down Hindley would have been done, and a way found to avoid rebuilding Rumworth Road bridge.
 

thealexweb

Member
Joined
5 Jan 2014
Messages
1,106
Only the down Atherton line, as far as Frederick Road. The wiring of both Hindley lines was specifically as active provision for the future, otherwise only the down Hindley would have been done, and a way found to avoid rebuilding Rumworth Road bridge.

Is there any chance if you know if the adjacent (two?) old sidings will survive all this/be electrified? Cheers.
 

59CosG95

Established Member
Joined
18 Aug 2013
Messages
6,853
Location
Beeston (Notts)
Looking at the photo's through Lostock station again, I notice there are no Earth or AT wires visible - to be installed later I guess?
I think the Earths may come through later, but I believe the ATFs are using the UTX "Dalek" cable routes that were sunk into the ground near the ATF Sectioning Station and in the "vee" between the Preston & Wigan lines earlier this year. The Earths might be using them too - @Joseph_Locke, am I presuming correctly?
 

PN27

Member
Joined
31 Jul 2018
Messages
51
ATF wires are definitely in lineside troughing/ducting through Lostock station. I may be wrong, but aren't earth wires used to avoid having to attach an earth bond to every mast? If so, either the masts are bonded individually, or they're bonded to an earth wire in the ducting.
 

wrinkley

Member
Joined
6 Feb 2015
Messages
130
I have just had a quick trip round the area, lots of orangemen at Lostock, the down line platform should get finished tonight, but the up line platform will be a push. The wiring gangs are still working on the fixings, but there were some missing registration arms and some with parts missing. The Wigan line is only wired on the down line.

There are no wires at Clifton and still only one line wired between the tunnel and Green Lane. It looks like the concentrated effort has been between Bolton and Lostock.
 

chorleyjeff

Member
Joined
3 May 2013
Messages
677
Living roughly half way between Blackpool and Manchester in Chorley my observations so far are
1. My railcard has been pretty well useless given that buses substitute for trains from mid evening and the line closes at weekends and now for a couple of weeks. Getting back from places such as Edinburgh, York, Furness and the Lakes before buses take over makes the days out short.
2 It seems I will no longer be able to get direct trains to Buxton, Edinburgh, Windermere or Furness without changing and it a pain waiting on Preston station when there are no planned connections.
3 It seems I will only be able to get stopping trains to Manchester given that Scotland trains will go via Wigan and the Furness/Lake District will not stop here.
4 why on earth has it taken so long do get the job nearly done? Passengers are getting fed up with the constant disruptions.
Anyhow rant over and decision made not to renew my old folks railcard.
 