A 4-car Electrostar will burn at least 1500kW including aux. Whatever replaces the Kent Networkers will be similar, if not more.
Considering this tranche of electrification was proposed to use up cascaded stock, not to introduce all singing all dancing new units, this is not that much of an issue.
Especially since routes that would get 4-car 319s would likely only get 3-car stock if it was ordered new.
What benefits are those? All that 750V DC does is remove the need for transformers, and the overhead clearances.
<=1500Vdc installations are regarded by the IEC and other suitable regulatory bodies as Low-Voltage installations which drastically simplifies the safety and earthing requirements for substations and the like. (You have no need to have HV certified staff on the railway side, or provide complex safety earthing arrangements, especially if it is a small substation that is fed from a 400V supply)
With the advances in power electronics we are starting to get close to having widespread use of solid state power transformers that take in power at any utility distribution voltage (400V-11kV+) and output a fully controllable DC output (controllable in both voltage and current) and which will fit onto a utility distribution pole with a power of several hundred kilowatts.
Cooperative use of intertripping and power-converter switches will enable an approach where commodity unit-substations drawing from any available utility supply can be added to the railway adhoc, utilising hall effect current sensors to detect a high current condition in the adjacent rail and a combination of their power electronic switches and their AC side circuit breakers to break faults without resorting to very expensive and bulky DC circuit breakers
It is an entirely new paradigm where you might have a 400V-fed substation of a few hundred kVA every few hundred metres.
I'm hardly the greatest fan of discontinuous electrification, but there may have to be a case for it in the future.
Discontinuous electrification has few advantages over simple battery electric operation though.
In most cases where discontinuous is practical, full blown batteries will probably come out on top.