Interesting that Network Rail are in the DfT firing line more than Northern or GTR.
The Northern/TPE timetable planning of course goes back to the 2015 ITT and the various TSR schedules defined there.
It was also supposed to be introduced in December last, so NR can hardly complain about lack of planning time.
The sudden change due to the delay in Manchester-Preston wiring is also down to NR's IP (Infrastructure Projects) division not being able to forecast completion properly, even after repeated previous delays.
I'm sure Northern have contributed their own planning failures to the situation, but I can see why the NR System Operator function is seen as the primary culprit.
The problems also call into question the planning and business case for Northern Hub (eg Ordsall Curve) and the Picc/Oxford Road non-improvements.
As to wielding the axe, Mr Paonessa (head of IP) is still there despite the repeated failures of electrification projects.
It's right to place blame on Network Rail but Northern should be in a position where they are complaining they've recruited extra drivers and guards and they are unable to utilise them all due to delays outside of their control. Also Porterbrook's failure to deliver 769s in time keeps getting overlooked.