Blackpool - Manchester Electrification

Status
Not open for further replies.
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

Malay States

Member
Joined
24 Jan 2017
Messages
56
Is this maybe more about signalling than electrification?
The wires don't all need to be up to reopen the line to diesels, but they do need the signalling and new track layout to work.
I was told today by a friend who had spoken to the head of the signalling part of the project that the signalling was complete.
 

dk1

Veteran Member
Joined
2 Oct 2009
Messages
19,798
Location
East Anglia
Had a horrible feeling that this was going to happen when I booked Blackpool for the Grand National weekend last September. I'm now expecting RMT to call a strike on MerseyRail & Northern on Saturday 14th to add the icing to the cake :'(
 

Geeves

Established Member
Joined
6 Jan 2009
Messages
2,616
Location
Rochdale
Yes the signalling work station is all complete at the ROC. I had a visit and talked to the former Blackpool No 2 signaller who was settling in next to Victoria and Oxford Rd workstations, quite a change for him. All the displays were lit I can only imagine its more the fact the platforms are still an uneven death trap at some locations that might be the issue.
 

Chester1

Established Member
Joined
25 Aug 2014
Messages
4,440
Had a horrible feeling that this was going to happen when I booked Blackpool for the Grand National weekend last September. I'm now expecting RMT to call a strike on MerseyRail & Northern on Saturday 14th to add the icing to the cake :'(

Its so predictable that Merseytravel should have already reserved enough buses and coaches for a Liverpool Lime Street / Central to Aintree shuttle service and an Ormskirk stopping bus and in the event of a strike simply not provide a rail service on the Ormskirk line. In the event of strikes your probably better off with current rail replacement service compared with the limited trains that would otherwise run.
 

dk1

Veteran Member
Joined
2 Oct 2009
Messages
19,798
Location
East Anglia
Its so predictable that Merseytravel should have already reserved enough buses and coaches for a Liverpool Lime Street / Central to Aintree shuttle service and an Ormskirk stopping bus and in the event of a strike simply not provide a rail service on the Ormskirk line. In the event of strikes your probably better off with current rail replacement service compared with the limited trains that would otherwise run.

Around 10yrs ago we got caught up in a MerseyRail strike on National day. There where plenty of shuttle buses opp Lime St Stn but it is just chaos on the way back. That year we stayed in Manchester which was straight forward. This year will be able to RR to Preston then via Crewe if need be. On way back might go for South train as after so much alcohol a toilet will be priority. Failing this it might just be a minibus back all the way & sod the expense.
 

randyrippley

Established Member
Joined
21 Feb 2016
Messages
5,383
On my travels around various parts of the country in the name of work, last time was near Bradford - I have seen some structures under pylon cables that look like Faraday type cages - essentially wire cages underneath the power lines - I don't know if that's what they are, but can't think of what else they would be - will try and get some pictures next time I'm over there. Wonder if that type of thing would be a cheapish workaround for where the lines are low - happy to be ridiculed by experts! :D
Sounds like they are rewiring the pylons
The nets are to catch the cables in case anything breaks and drops. Also to catch any men if they have to walk the cables (rare) and fall........
I haven't actually seen anyone wirewalking for years, but it used to be done to unjam the cable bobbins which reeled out one cable as another was reeled in. In recent years they've not relaced cables that way - they've simply pulled them into place using ropes with Landrovers or Unimogs. I guess the bobbins wouldn't work when single cables are replaced by two or three (which is what usually happens now)
 

driver_m

Established Member
Joined
8 Nov 2011
Messages
2,248
Apologies if this has already been posted , the Weekly Ops notices are showing a OLE switch on for April 14th. (Full route Preston-Blackpool North)
 

totally

Member
Joined
13 Mar 2012
Messages
67
Apologies if this has already been posted , the Weekly Ops notices are showing a OLE switch on for April 14th. (Full route Preston-Blackpool North)
Yes, as a resident near the line we had a letter some time ago indicating this would happen. I'm just wondering if that can still hold true given the three week extension to the possession, taking us to 16th April restart to services.

Rather worryingly the company websites still show the line as re opening on March 26th and are selling tickets accordingly. There will be people booking to travel to Blackpool over Easter who will be none the wiser until they arrive at Preston!
 

jTrain

New Member
Joined
2 Feb 2018
Messages
3
Apologies if this has already been posted , the Weekly Ops notices are showing a OLE switch on for April 14th. (Full route Preston-Blackpool North)

Please could you let me know how to access the Weekly Ops Notices.
 

LDECRexile

Established Member
Joined
30 Jan 2014
Messages
2,149
Location
Southport, UK
I travelled by train in both directions from Salford Crescent to Buckshaw Parkway today.

Progress visible as follows:

1. New footbridge just north of the M60: bases on southbound side curing in the sunshine, foundation work in evidence on northbound side.
2. A national grid pylon approx. 1 mile south of Kearsley station, southbound side, appeared to have been "cut off" ie wires led to it from the east, but not from it to the west over the railway. Is this progress to wards the oversail problem?
3. I could only see two bases without masts between Moses Gate and Lever St footbridge.
4. Fence has been erected on Bolton platform to prevent pedestrians falling onto the P2 bufferstop and to-be-erected terminating mast off the end of P2.
5. The presumed mast base immediately off the northern end of P1 is now revealed. It is a mast base.
6. Does the pile of rubbish opposite P5 hide a new mast base or it is just a pile of rubbish?
7. Orange on show on the ziggurat at Lostock.
8. Spotted two inclinometers in place as well as the one between P3 and P4 at Bolton.

Photos added to the Combined Volume here:

https://www.flickr.com/photos/127646831@N03/albums/72157661069863633
 

L+Y

Member
Joined
4 Jul 2011
Messages
502
Reported elsewhere that Network Rail have last week advised Northern to plan for a May 2019 completion of electrification of the Bolton line. Oh dear...
 

GRALISTAIR

Established Member
Joined
11 Apr 2012
Messages
10,461
Location
Preston Lancs
Reported elsewhere that Network Rail have last week advised Northern to plan for a May 2019 completion of electrification of the Bolton line. Oh dear...
I am sure that will mean full squadron electric service- not actually completion and energisation etc.
 

LDECRexile

Established Member
Joined
30 Jan 2014
Messages
2,149
Location
Southport, UK
Reported elsewhere that Network Rail have last week advised Northern to plan for a May 2019 completion of electrification of the Bolton line. Oh dear...

Oh dear indeed. Could you please say where it is reported or post a link?
 

YorkshireBear

Established Member
Joined
23 Jul 2010
Messages
9,661
I am sure that will mean full squadron electric service- not actually completion and energisation etc.

It is still an oh dear, that is now 3 postponements in less than 6 months.

I too had heard rumblings but nothing official so it will be interesting to see if this does indeed become official, and how locals will respond to further weekend closures (could we be looking at over a year!!!). I would certainly hope that Northern try and get money to cover loss of revenue.

A further nail in the coffin of electrification.
 

Chrisyd

Member
Joined
16 May 2015
Messages
210
I sat on the train this morning and if you were putting forward an argument for completion this May, considering the weekend closures, 4 days at Easter etc, I could have just about believed that with the Blackpool - Preston staff coming on board in late March (alright now mid April), it might be possible!!!! The idea that we are more than a year away, does not seem credible, but yet in my heart of hearts I admit it seems very credible.

So, have a couple of problems just come to light which when scoped have a completion time of a year which are causing this, or is it because it will need every weekend between now and then, with early closures Monday to Thursday until May 2019 to complete??

Whilst everyone focuses on the weekend closures, which are undoubtedly putting people off travelling to Manchester (possibly to Bolton's benefit!), since the Farnworth Tunnel works started, the last train from Manchester, Monday - Thursday has been before 10pm (currently 2124 Vic, 2146 Picc), which means anytime you are out it is a mixture of clock watching or replacement bus services....
 

Bertie the bus

Established Member
Joined
15 Aug 2014
Messages
3,216
The gap at Blackpool Road, Preston has now been wired on the up but there is still a gap to the UCLAN sports centre on the down.

They appear have done precisely nothing in the last 2 weeks around Kirkham & Wesham. There is still a mast lying on the ground west of the junction and no wires to be seen. Absolutely nobody about this afternoon either. So much for Team Orange working night and day to finish the job.
 

td97

Established Member
Joined
26 Jul 2017
Messages
1,556
Reported elsewhere that Network Rail have last week advised Northern to plan for a May 2019 completion of electrification of the Bolton line. Oh dear...
Network rail are still claiming Dec 2018 in a PR release from earlier today, detailing upcoming work as part of the GNRP over Easter
  • Continuous work on the Manchester – Preston line to support the introduction of new and improved trains by December 2018. There will be no trains through Bolton at weekends until later in the year.