Maybe I will. I'll also look for something on the down slow from Stafford that doesn't go to Stoke!1619 LM goes up slow if you really want to do it.
Maybe I will. I'll also look for something on the down slow from Stafford that doesn't go to Stoke!1619 LM goes up slow if you really want to do it.
Bristol Temple Meads to Bristol Parkway (and in fact the whole area around Bristol Parkway), mind you they are currently making the track 4 lines instead of 2. XC services often get stuck behind slow GWR stoppers which are often running late.
Ah it is only to Filton, that would make sense.There is work currently taking place to 4 track the route as far as Filton Abbeywood where the South Wales line and it's trains turn off.
Since Reading was remodelled, Didcot East to Moreton Cutting has become the major pinch point on the GWML. Fast trains to Oxford having to cross both relief lines and the up main on the flat to access the Didcot avoider, vice versa in the opposite direction to join the up main.
It would be useful to have a Norton Bridge style flyover from the down main to the down Didcot Avoider without crossing the up main. I don’t know if the appetite will be there to carry out too much more work on the GWML since the electrification went bad though.
In the future I can see Wootton Bassett Jn becoming more of a pinch point with the extra services to Bristol via Hullavington.
If roads can have investment then why not build all these rail improvements? I agree Wootton Bassett is overdue for a major rebuild, given that it's still a minimal adaptation to the completely changed traffic nowadays. How many grade-separated rail junctions were put in between Rugby (1960s?) and Hitchin (2010s)Sort out the Worcester triangle and surrounding single lines, slightest problem screws up numerous routes.
If roads can have investment then why not build all these rail improvements? I agree Wootton Bassett is overdue for a major rebuild, given that it's still a minimal adaptation to the completely changed traffic nowadays. How many grade-separated rail junctions were put in between Rugby (1960s?) and Hitchin (2010s)
Since Reading was remodelled, Didcot East to Moreton Cutting has become the major pinch point on the GWML. Fast trains to Oxford having to cross both relief lines and the up main on the flat to access the Didcot avoider, vice versa in the opposite direction to join the up main.
It would be useful to have a Norton Bridge style flyover from the down main to the down Didcot Avoider without crossing the up main. I don’t know if the appetite will be there to carry out too much more work on the GWML since the electrification went bad though.
In the future I can see Wootton Bassett Jn becoming more of a pinch point with the extra services to Bristol via Hullavington.
Welwyn Viaduct (together with the two tunnels just north of it) is a 2-mile, 2-track section on the ECML just 22 miles from Kings Cross.I don't know Welwyn Viaduct so can't comment.
What about the flat crossing north of Newark Northgate station where the Nottingham-Lincoln line crosses the ECML?
Obviously a diveunder is unrealistic but I hope to live to see a flyover built. The key constraint on the vertical alignment coming from the SW would appear to be not Castle station but the bridge carrying the A46 Newark Relief Road over the line. However this bridge seems to be about 900m from the ECML crossing which I would have thought is comfortably enough.I can't see that ever being eliminated, much as I imagine they'd like to. A dive under for the Lincoln line is an impossibility due to the proximity of the river and a flyover would be extremely difficult because if it began where the track straightens out after Newark Castle station, I imagine the approach to the ECML would be too steep.
Many years ago, didn't the ECML franchisee at the time, I forget who, try to get Welwyn North closed to speed up long-distance trains?
Its only saving grace is that there is a 2-track alternative route via the Hertford loop.
Fortunately modern trains can cope with steeper gradients than Victorian ones could.
Bristol Temple Meads to Bristol Parkway (and in fact the whole area around Bristol Parkway), mind you they are currently making the track 4 lines instead of 2. XC services often get stuck behind slow GWR stoppers which are often running late.
It's not the late expresses that get any additional delay, it's the stopper that can't get out, and in 40 years travelling I think I have yet to go south on the up slow. There are southbound non-stop Glasgows every hour but it may be the recent weather in N England has been a cause of the problem. Luckily our stopper to Brum managed to make up time and didn't cause any further delays around New St.
I would suggest the section between Swinton Station (Sth. Yorks) and Aldwarke Junction.
It was quadruple tracked, reduced to 2 tracks by BR but in recent years has seen a big increase in usage with many services crossing each other, particularly at Aldwarke. I think the removed tracks should be reinstated for Doncaster line services and would also reduce dependency on the two junctions.
Thanks for the reminder/info, it's not quite as bad as I had imagined, but excluding the new-build lines (which clearly need to have junctions) it's only about 20 schemes in 50 years in round numbers.Well, off the top of my head (with particularly poor knowledge in the north and Scotland) and in no particular order:
Retford
Tanners Hill (the 1970s vintage)
Windmill Bridge Jn x2
Welwyn Garden City
Finsbury Park x2
Oxley Chord
Hambleton Jns
Airport Jn
Proof House Jn (in two bites, 1988 and 2000)
Shortlands Jn
Nine Elms Jn
Nuneaton x2
Allington Chord
Six on HS1
Langley Jn at Stevenage may also be of this vintage, but can't be sure
And since Hitchin, we've had:
Joan Croft
Airport Jn II
Acton
Reading x3
Norton Bridge
Bermondsey x3
Canal Jn
2 for the Crossrail portals
It's not the late expresses that get any additional delay, it's the stopper that can't get out, and in 40 years travelling I think I have yet to go south on the up slow. There are southbound non-stop Glasgows every hour but it may be the recent weather in N England has been a cause of the problem. Luckily our stopper to Brum managed to make up time and didn't cause any further delays around New St.
The xx19 LM Birminghams from P5 seem to go out on the up slow to Stafford (no real delay there, now it's 100mph).
The trouble here is quite how big a problem there actually is in this area.
From Sheffield, services are:
towards Barnsley 4tph
towards Moorthorpe 2tph soon to be 3tph (+1 in some hours)
towards Doncaster 5tph
Of which, 1 of the Moorthorpes and 2 of the Doncasters also go via Rotherham Central which, in the easterly direction means crossing on the flat, going down a single track chord into Rotherham, then crossing again on the flat at Aldwarke, and for those going to Doncaster, crossing again on the flat at Swinton. Added to all that is the less than optimal layout at (particularly) the north end of Sheffield station.
Now add 3 trams per hour through Rotherham Central, which will have to cross to their turnback siding at Parkgate...
Then add HS2 services coming north out of Sheffield Midland...(!)
I do wonder how much value resolving one of these problems would have, a package of measures will probably be needed to make any real difference.
Thanks for the reminder/info, it's not quite as bad as I had imagined, but excluding the new-build lines (which clearly need to have junctions) it's only about 20 schemes in 50 years in round numbers.
(And from the other replies it's clear that I am not the only person frustrated by over-simplified infrastructure.)