1) Yes, with a slightly reduced service into Paddington over a number of days to accommodate the inspections and required remedial works.
2) They’re very specialist staff - presumably they were on another job; or even a day off. Takes time to arrange their attendance.
3) What can you do? The track formation is essentially a shallow concrete trough; with longitudinal timbers laid on top and rails on those. There is drainage but much of the waste is solid in nature; and thus blocks the drains. The problem is societal. The signage on trains says do not use/flush. Unfortunately many feel they are above such rules.
4) Shortening Platform 2 (and others later in the week) was considered. The issue was it would only have been good for a 5 Car turbo or a 180; neither are particularly common traction to see on the mainline side of Paddington station. The risk - of routing an over length train into a short platform; or a driver not realising the platform was shortened and ploughing into the worksite - was found to outweigh the benefits of having the platform available for 16x or 180s. As it was the train plan of starting/terminating the Bedwyns at Reading is well practised and generally frees up enough capacity for them to work around the reduced platforms. There were a couple of other peak cancellations but not much.
5) I’d hope staff know a whole lot better than to use on train toilets at Paddington.
2) They’re very specialist staff - presumably they were on another job; or even a day off. Takes time to arrange their attendance.
3) What can you do? The track formation is essentially a shallow concrete trough; with longitudinal timbers laid on top and rails on those. There is drainage but much of the waste is solid in nature; and thus blocks the drains. The problem is societal. The signage on trains says do not use/flush. Unfortunately many feel they are above such rules.
4) Shortening Platform 2 (and others later in the week) was considered. The issue was it would only have been good for a 5 Car turbo or a 180; neither are particularly common traction to see on the mainline side of Paddington station. The risk - of routing an over length train into a short platform; or a driver not realising the platform was shortened and ploughing into the worksite - was found to outweigh the benefits of having the platform available for 16x or 180s. As it was the train plan of starting/terminating the Bedwyns at Reading is well practised and generally frees up enough capacity for them to work around the reduced platforms. There were a couple of other peak cancellations but not much.
5) I’d hope staff know a whole lot better than to use on train toilets at Paddington.