Referring to post #5107 (1 Sept 2017) on the Bpl - Mcr Electrification thread..
Quote: "There are currently new sleepers in position on the downside of the Down/Up Lytham line, from about 50 metres after Kirkham North Jn progressing around the corner.
This was viewed from a Blackpool North train so it was difficult to see the extent of how far it goes"..
This wasn't commented upon on that thread, and I don't think it's been picked up on this thread...
If new double track was being laid at the Kirkham end in the direction of Wrea Green, this would have the effect of shortening the single-track length of the branch, and improve the resilience of the hourly timetable in the event of late running... (Bpl South trains are already timetabled to depart the platform at Kirkham before the service off the branch arrives, and are often/usually waiting at the junction for the train from Bpl Sth to exit the branch..)..
Is anyone able to comment any further on any of this..?