Gospel Oak to Barking Line (GOBLIN) electrification

Status
Not open for further replies.

DidcotDickie

Member
Joined
12 Mar 2017
Messages
160
Location
Oxfordshire
Has any of the GWML OHLE testing involved unusual locos, or off-piste EMU workings? In all the many months of discussions in the relevant thread I don't think that type of testing was ever mentioned...

Nothing that I'm aware of other than 387s and 800s have used the wires between Airport Junction and Didcot.

Test car Mentor ran between Tilehurst and Didcot last September when the test section was first energised, though it was diesel hauled.

https://www.networkrailmediacentre.co.uk/resources/first-mentor-pass-leaving-tilehurst#
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

Class 170101

On Moderation
Joined
1 Mar 2014
Messages
8,664
I would have thought a pair of Class 92s would be likely

Now you mention it I would be inclined to agree this is more likely.

I would guess the Pendolinos were useful in the North West (and Scotland going forward) as some of the routes in question would be used for diverting Pendolinos as where as I doubt one would be ever run on the GOB in anger. Howerver the use of a Class 92 or two on the GOB in anger seems more probable.
 

reddragon

Established Member
Joined
24 Mar 2016
Messages
3,275
Location
Churn (closed)
Blockade 1 (5 weeks) is to wire up GO to Queens Road & blockade 2 (5 weeks) to wire up from Queens Road to Forest Gate. Switch on in Xmas / NY.

Wiring work starts at GO before blockade 1, so get spotting in September!
 

reddragon

Established Member
Joined
24 Mar 2016
Messages
3,275
Location
Churn (closed)
https://tfl.gov.uk/status-updates/major-works-and-events/london-overground-closures-2017-8

September 2017 to January 2018
In the autumn there may be more weekend closures, and two longer closures from:

Sunday 17 September to Sunday 22 October
Monday 27 November to Sunday 14 January 2018 (might shorten)

From my HP sauce

Wiring plan

w/c 3 September = Gospel Oak to Upper Hollaway
w/c 10 September - Upper Hollaway to South Tottenham
w/c 17 September = South Tottenham area
w/c 24 September = ST to Queens Road

Please let us all know if that actually happens!
 

traji00

Member
Joined
17 Aug 2009
Messages
243
https://tfl.gov.uk/status-updates/major-works-and-events/london-overground-closures-2017-8

September 2017 to January 2018
In the autumn there may be more weekend closures, and two longer closures from:

Sunday 17 September to Sunday 22 October
Monday 27 November to Sunday 14 January 2018 (might shorten)

From my HP sauce

Wiring plan

w/c 3 September = Gospel Oak to Upper Hollaway
w/c 10 September - Upper Hollaway to South Tottenham
w/c 17 September = South Tottenham area
w/c 24 September = ST to Queens Road

Please let us all know if that actually happens!
I live between Upper Holloway & Crouch Hill stations so I'll be sure to spot any wires going up :)
 

class303

Member
Joined
5 Sep 2011
Messages
392
Severe delays and part closures all day this bank holiday due to a "damaged bridge at Harringay Green Lanes".

Was this a vehicle strike? Or something to do with the works?

This project seems cursed. :cry:
 

Juniper Driver

Established Member
Joined
17 Jul 2007
Messages
2,154
Location
SWR Metals
Severe delays and part closures all day this bank holiday due to a "damaged bridge at Harringay Green Lanes".

Was this a vehicle strike? Or something to do with the works?

This project seems cursed. :cry:

Patience.It will get there.I've lived local to this line for over 40 years.
 

snowball

Established Member
Joined
4 Mar 2013
Messages
8,144
Location
Leeds
Press release

https://www.networkrail.co.uk/feeds...re-about-gospel-oak-to-barking-line-closures/

Public information sessions will take place during early September at every station on the Gospel Oak to Barking line, ahead of its closure for electrification work.

Work continues to electrify the line ahead of the introduction of new double-length electric trains from spring 2018, which will carry twice as many passengers and improve air quality for lineside neighbours.

Weekend closures will continue up to Sunday 10 September and will be followed by a five-week long closure starting Sunday 17 September. The line will reopen for weekday passenger services on Monday 23 October, but weekend closures will continue.

Ahead of the five-week closure, a series of information sessions will be held at all stations between Gospel Oak and Barking from Tuesday 5 September to Thursday 14 September. Staff from Network Rail, Transport for London and Arriva Rail London (the operator of London Overground) will be available to answer questions at the following stations from 16:30-18:30:

* Tuesday 5 September, Gospel Oak and Upper Holloway

* Wednesday 6 September, Crouch Hill and Harringay Green Lanes

* Thursday 7 September, South Tottenham and Blackhorse Road

* Tuesday 12 September, Walthamstow Queen’s Road and Leyton Midland Road

* Wednesday 13 September, Leytonstone High Road and Wanstead Park

* Thursday 14 September, Woodgrange Park and Barking

Meliha Duymaz, Network Rail’s route managing director for Anglia, said: “The Gospel Oak to Barking line is set to benefit from a transformational upgrade with a new fleet of longer, electric trains so that twice as many people can travel comfortably on this route. We are carrying out work to electrify the line, which can only take place when the line is closed. Our teams will be on hand to explain the work and answer any questions passengers and neighbours may have.”

Discussions are ongoing with TfL, train and freight operators to finalise agreements for additional weekend and longer closures from the end of October onwards to complete electrification work. A second, longer closure is currently proposed from Saturday 25 November until Sunday 14 January 2018, however these dates are subject to change. Details will be confirmed nearer the time.

The electrification installation will be completed in January 2018, enabling testing of the new trains and so that driver training can begin. The new trains will start entering passenger service from spring 2018. Current diesel services will continue to run as normal until then.

Passengers should check before they travel and plan their journey in advance at tfl.gov.uk
 

traji00

Member
Joined
17 Aug 2009
Messages
243
So far no wires have been strung up in the Upper Holloway - Crouch Hill area, presumably this will be done during the blockade starting Sunday?

Sent from my VTR-L09 using Tapatalk
 

traji00

Member
Joined
17 Aug 2009
Messages
243
Wires have appeared on the Eastbound line between Upper Holloway & Crouch Hill!

I'll try to get some pictures when I'm near the line tomorrow.

Sent from my VTR-L09 using Tapatalk
 

Taunton

Veteran Member
Joined
1 Aug 2013
Messages
12,333
How much of this is extra Network Rail cost, and how much is being covered by the contractors out of the initial budget? I haven't noticed the original principal contractor giving any profits warning about it.
 

AndyNLondon

Member
Joined
20 Jan 2014
Messages
191
Here's a photo at Harringay Green Lanes this evening - wires are up on the eastbound line!
 

Attachments

  • IMG_20170925_183635.jpg
    IMG_20170925_183635.jpg
    108.8 KB · Views: 195

plcd1

Member
Joined
23 May 2015
Messages
788
"Sorry, that page doesn't exist!"

They deleted their earlier tweet for some reason and added a new one later. I had to go round and alter posts on other forums. :roll::roll::roll:

Still good to see some progress. Is it normal practice to wire one track / direction at a time and then do the adjacent track? I appreciate there are limits on how many wiring trains and teams there are so no facetious responses please. ;)
 

goblinuser

Member
Joined
12 May 2017
Messages
292
Wires are up under the Crouch Hill bridge - very tight fit indeed. Does anyone want some photos?
 

traji00

Member
Joined
17 Aug 2009
Messages
243
Both lines are now wired. This is at the site of the long-gone Hornsey Road station :
25b25524892f12ea8afa979aa14855dc.jpg


Sent from my VTR-L09 using Tapatalk
 