While planning a future trip I noticed for that most Sundays in February and March Network Rail are carrying out engineering work between Llandudno Junction and Chester all day Sunday, closing the line. There is also a weekend closure 25-26 March.


I was wondering where I could find details of the work being done. I searched here and didn't find anything. Maybe I'm just looking in the wrong place.
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

Welshman

Established Member
Joined
11 Mar 2010
Messages
3,068
As far as I know, there are two main projects on the North Wales Coast line at present:-

The removal of the down platform loop at Abergele and the widening of the existing platform to reach what was the down through line;

The creation of a new loop at Mostyn.


These two, plus routine relaying and maintenance.

Charlie Hulme's excellent website gives details of the work at Abergele [and earlier editions that at Mostyn]

http://www.nwrail.org.uk/nwnews.htm
 
Last edited:

The Planner

Veteran Member
Joined
15 Apr 2008
Messages
19,688
Yes, and the crossovers at Rockcliffe Hall move to Flint. Mostyn loop will be much longer than the ones at Holywell at 800 odd metres.
 

Welshman

Established Member
Joined
11 Mar 2010
Messages
3,068
Yes, and the crossovers at Rockcliffe Hall move to Flint. Mostyn loop will be much longer than the ones at Holywell at 800 odd metres.

As the new loop at Mostyn is on the up side, will it be bi-directional, with the associated crossovers, or just for up traffic?

[Also, but out of the scope of the original question, do you know if the emergency frame and crossover at Lysfaen is scheduled to remain, or be removed?]
 

snowball

Established Member
Joined
4 Mar 2013
Messages
8,144
Location
Leeds
What's the current expected date for the Chester to Llandudno Junction resignalling?

And will it include the Llandudno branch?
 
Last edited:

The Planner

Veteran Member
Joined
15 Apr 2008
Messages
19,688
Mostyn is bi di but a bit slow as 25mph. March 2018 is the date I have for commissioning but subject to change. Lysfaen stays. Talacre goes. Doesnt do the branch, Lysfaen is the limit.
 
Last edited:

Welshman

Established Member
Joined
11 Mar 2010
Messages
3,068
Mostyn is bi di but a bit slow as 25mph. March 2018 is the date I have for commissioning but subject to change. Lysfaen stays. Talacre goes. Doesnt do the branch, Lysfaen is the limit.

Thank you for that.
Much obliged.
 

Andrew*Debbie

Member
Joined
1 Feb 2017
Messages
323
Location
Llanfairpwllgwyngyll ...
Thanks for all the replies. Exactly what I was looking for.

I had too look Mostyn up. Have to admit I was relieved that it is a long closed station.




Off to go search on information about current engineering works at Llanfairpwll. :)
 