Is the Crossrail project on time?

Status
Not open for further replies.

mrmartin

Established Member
Joined
17 Dec 2012
Messages
1,295
Seeing as nearly every major rail project in the UK has been horrendously delayed recently, is it likely that Crossrail will be on time?
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

JP

Member
Joined
1 Dec 2011
Messages
52
One engineering firm working for them is currently about 2% behind their completion target. So if that's an indication of the whole project, it's not too adrift from target.
 
Last edited:

Class 170101

On Moderation
Joined
1 Mar 2014
Messages
8,661
Almost certainly behind in places. Gidea Park will be at least 12 months late as it was meant to be finished in the Spring and yet to start.
 

matt_world2004

Established Member
Joined
5 Nov 2014
Messages
4,581
Apart from the year long delay caused by coalition budget cuts it will still launch on schedule. The single largest challenge the tunnelling is complete compared to that the station fitting out should be a relatively simple task, the eastern and western station construction is probably local to each site, the dive under at Acton freight looks complete with track being fitted out and the crossover at Heathrow junction is complete . Hayes and Ealing Broadway stations are still building sites. Although not due to be finished until next year.
 

najaB

Veteran Member
Joined
28 Aug 2011
Messages
33,689
Location
Scotland
Almost certainly behind in places. Gidea Park will be at least 12 months late as it was meant to be finished in the Spring and yet to start.
If you mean the station, there is definitely work happening on the ground, and has been for a while. Or is there upgrade work at the depot too?
 

coppercapped

Established Member
Joined
13 Sep 2015
Messages
3,334
Location
Reading
Seeing as nearly every major rail project in the UK has been horrendously delayed recently, is it likely that Crossrail will be on time?

Crossrail publishes an update on progress every so often, the current one may be found at:

http://www.crossrail.co.uk/news/quarterly-crossrail-update/
The project is more than 75% complete. There is a huge amount of work underway to complete the stations and fit-out the physical infrastructure with the systems required to turn it into an operational railway.​
 
Last edited by a moderator:

Chrisyd

Member
Joined
16 May 2015
Messages
210
This article suggests it is not all running smoothly everywhere:

http://www.constructionenquirer.com...spends-electrical-work-at-paddington-station/

Electrical work has been halted at Crossrail’s Paddington station because of concerns that project delivery has derailed.


The M&E package at the station has fallen seriously behind schedule and now Skanska’s in-house electrical contractor SRW Engineering Services has halted all work at the site.


Around 125 sparks have been told to down tools but still turn up for work to get paid.


Workers are being told that the suspension is taking place to deliver design changes and alter work planning....
 
Last edited by a moderator:

gsnedders

Established Member
Joined
6 Sep 2015
Messages
1,472
I guess a large part of the question is whether the stations that are unfinished are unfinished in such a way such that service can commence (with or without stopping at them!) and have them completed overnights.
 

LNW-GW Joint

Veteran Member
Joined
22 Feb 2011
Messages
21,923
Location
Mold, Clwyd
The Channel Tunnel project managed to lose a year between completion of tunnelling and opening for service.
The management/contractors took their eyes off the ball after the high-profile breakthrough.
The "easy" (surface) sections of Crossrail are not all that easy.
The GE and GW section upgrades, and joining them to the new tunnels, is a really complex project, and mostly in NR's hands.
Hopefully there is enough slack to make up any loss.
 

hwl

Established Member
Joined
5 Feb 2012
Messages
8,258
I guess a large part of the question is whether the stations that are unfinished are unfinished in such a way such that service can commence (with or without stopping at them!) and have them completed overnights.

They effectively have 2 years to get the core and Abbey Wood Branch sorted so a reasonable chance but likely to eat up contingency of 9-10 months rather quickly.

Lets hope they don't have any issues with live OHLE part heights at this stage.
 

edwin_m

Veteran Member
Joined
21 Apr 2013
Messages
28,675
Location
Nottingham
The Channel Tunnel project managed to lose a year between completion of tunnelling and opening for service.
The management/contractors took their eyes off the ball after the high-profile breakthrough.
The "easy" (surface) sections of Crossrail are not all that easy.
The GE and GW section upgrades, and joining them to the new tunnels, is a really complex project, and mostly in NR's hands.
Hopefully there is enough slack to make up any loss.

Most of the time and cost of this sort of project sits with the civil engineers, but most of the risk is in the systems and integration. So while every indication is that Crossrail is largely on time, it ain't over till it's over.
 

61653 HTAFC

Veteran Member
Joined
18 Dec 2012
Messages
19,354
Location
Yorkshire
Wasn't HS1 pretty much on time and on budget, if timed from when it was finally green-lit?

Or was that just Nigel Harris Propaganda?
 

Tom m

Member
Joined
28 Mar 2016
Messages
28
I am struggling to understand what is going take another 3 years to complete? Considering the tunneling and civil works are almost complete and a fair amount of track is already in place, is anyone able to give an idea of what's left on the to do list? I don't work in the industry and this is not a criticism but more of a genuine question as to understand what else has to happen before start of full service.

I understand the need for a phased introduction but December 2019 still seems a very long way away, especially as we are likely to see 387s running to maidenhead within a few months.
 

Muzer

Established Member
Joined
3 Feb 2012
Messages
2,784
Fitting out the stations I believe is a thing. I suspect the signalling systems too.
 

Ianno87

Veteran Member
Joined
3 May 2015
Messages
15,214
I guess a large part of the question is whether the stations that are unfinished are unfinished in such a way such that service can commence (with or without stopping at them!) and have them completed overnights.

One of the big aspects is whether the stations are completed to a state suitable for emergency/fire evacuation of a passenger train in the tunnels, even if trains are not making passenger calls there. Or the interim fire strategy does not require the ability to evacuate via that station (or the line is operationally managed to avoid needing to)
 
Last edited:

306024

Established Member
Joined
23 Jan 2013
Messages
3,974
Location
East Anglia
I am struggling to understand what is going take another 3 years to complete?........

The Paddington - Abbey Wood service is only two years away. Prior to that an awful lot of testing is required, not to mention some 20 odd trains need building to run the service. These follow on from the 15 units required for the Great Eastern, and other units required for the Paddington - Heathrow service.

Yes signalling systems are also a major consideration. The technology involved also requires comprehensive testing.
 

edwin_m

Veteran Member
Joined
21 Apr 2013
Messages
28,675
Location
Nottingham
That'd be a big fat NO then!

The difference is that Crossrail's budget has stayed the same in real terms over the design and construction period of nearly a decade. It actually reduced by a billion or so in 2010 when the government agreed to delay completion by a year to allow a more efficient construction sequence (something to do with building the tunnels before the stations or vice versa).

The Olympics cost the same sort of amount as Crossrail but that was a lot more than originally announced.
 