If you mean the station, there is definitely work happening on the ground, and has been for a while. Or is there upgrade work at the depot too?Almost certainly behind in places. Gidea Park will be at least 12 months late as it was meant to be finished in the Spring and yet to start.
If you mean the station, there is definitely work happening on the ground, and has been for a while. Or is there upgrade work at the depot too?
Okay, thanks. Thought for a moment I was imagining the platform extension work.In the sidings

Seeing as nearly every major rail project in the UK has been horrendously delayed recently, is it likely that Crossrail will be on time?
The project is more than 75% complete. There is a huge amount of work underway to complete the stations and fit-out the physical infrastructure with the systems required to turn it into an operational railway.
Electrical work has been halted at Crossrail’s Paddington station because of concerns that project delivery has derailed.
The M&E package at the station has fallen seriously behind schedule and now Skanska’s in-house electrical contractor SRW Engineering Services has halted all work at the site.
Around 125 sparks have been told to down tools but still turn up for work to get paid.
Workers are being told that the suspension is taking place to deliver design changes and alter work planning....
Indeed. It sounds bad. But for some perspective, that's one station out of 40 and one of the most complex jobs too.This article suggests it is not all running smoothly everywhere.
I guess a large part of the question is whether the stations that are unfinished are unfinished in such a way such that service can commence (with or without stopping at them!) and have them completed overnights.
The Channel Tunnel project managed to lose a year between completion of tunnelling and opening for service.
The management/contractors took their eyes off the ball after the high-profile breakthrough.
The "easy" (surface) sections of Crossrail are not all that easy.
The GE and GW section upgrades, and joining them to the new tunnels, is a really complex project, and mostly in NR's hands.
Hopefully there is enough slack to make up any loss.
I guess a large part of the question is whether the stations that are unfinished are unfinished in such a way such that service can commence (with or without stopping at them!) and have them completed overnights.
I am struggling to understand what is going take another 3 years to complete?........
Wasn't HS1 pretty much on time and on budget, if timed from when it was finally green-lit?
Or was that just Nigel Harris Propaganda?

Budget wise, about on a par with the London Olympics.![]()
That'd be a big fat NO then!
Budget wise, about on a par with the London Olympics.![]()
The Olympics ran under budget...That'd be a big fat NO then!